RTA

REQUEST FOR PROPOSAL

US Army Corps of Engineers Alaska District

EIE342

REPAIR UTILITIES TO TLFS

EIELSON AFB, ALASKA

W911KB-14-R-0027

April 7, 2014

REQUEST FOR PROPOSAL

TABLE OF CONTENTS

TASK ORDER REQUIREMENTS CHECKLIST

TASK ORDER PROPOSAL SCHEDULE

DAVIS BACON WAGE RATES

TASK ORDER SUBMITTAL REGISTER

TASK ORDER - SCOPE OF WORK

DIVISION 01 – GENERAL REQUIREMENTS

01 19 10.00 29 DESIGN CRITERIA REQUIREMENTS

01 19 20.00 29 DESIGN AND CONSTRUCTION DELIVERABLES/PROCEDURES

01 19 20.00 39 65 AND 100 PERCENT DESIGN REQUIREMENTS

01 19 30.00 29 SPECIAL ITEMS

01 57 20.01 29 ENVIRONMENTAL PROTECTION

DIVISION 02 – EXISTING CONDITIONS

02 61 13 CONTAMINATED SOILS REMOVAL, HAULING AND STOCKPILING

02 82 14.00 20 HAZARDOUS MATERIALS ABATEMENT

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 57 10.00 10 FORCED HOT WATER HEATING SYSTEMS USING WATER AND STEAM

HEAT EXCHANGERS

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 12 16 ROADWAY

32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS

DIVISION 33 – UTILITIES

33 05 41.00 39 UTILIDOR SYSTEMS

33 11 00 WATER DISTRIBUTION SYSTEM

33 63 13 HEAT DISTRIBUTION SYSTEM

APPENDICES

APPENDIX A: GEOTECHNICAL SUMMARY REPORT

APPENDIX B: EIELSON AFB LANDSCAPE DESIGN GUIDE

APPENDIX C: EIELSON AFB UTILIDOR DESIGN GUIDE

APPENDIX D: EIELSON AFB HVAC STANDARDS

APPENDIX E: EIELSON AFB INSULATION GUIDE

APPENDIX F: EIELSON AFB UTILITY METERING REQUIREMENTS

APPENDIX G: EIELSON AFB CADD/GIS STANDARDS

APPENDIX H: DRAWINGS

APPENDIX I: MECHANICAL ROOM AND BUILDING ASBUILTS

APPENDIX J: ELECTRICAL ASBUILTS

TASK ORDER REQUIREMENTS CHECKLIST

DESIGN, CONSTRUCT, REPAIR UTILIDOR IDIQ

Project Name: EIE342, Repair Utilities to TLFs

Project Location: Eielson AFB, Alaska

(Fill-ins and checked blocks are applicable to this Task Order)

1. SECTION 00 21 00 EIE UTILIDOR IDIQ TASK ORDER INSTRUCTIONS TO OFFERORS

Type of Task Order

Firm-Fixed-Price

Competitive

Design/Build Construction Fully Designed Construction

Task Order Contract Cost Limitation or Magnitude: $2,037,000.00

Task Order Provisions (See Section 00 72 00 of the base contract for clause text)

52.217-3, Evaluation Exclusive of Options 52.217-5, Evaluation of Options 52.225-10, Notice of Buy American Act Requirement – Construction Materials (task order value < $7,864,000) 52.225-12, Notice of Buy American Act Requirement – Construction Materials Under Trade Agreements (task order value > $10,335,931) 52.225-12 Alt II, Notice of Buy American Act Requirement – Construction Materials under Trade Agreements, Alternate II (task order value $7,864,000 or more but less than $10,355,931)

52.236-27, Alt 1, Site Visit (Construction), Alternate 1 Date and Time of Site Visit:

Location:

2. SECTION 00 22 30 EIE UTILIDOR IDIQ TASK ORDER EVALUATION FACTORS

Method for Evaluating Task Order Proposals

Lowest Price

Trade Off See attached Task Order Selection Procedures and Basis of Award.

3. SECTION 00 45 00 EIE UTILIDOR IDIQ TASK ORDER REPRESENTATIONS AND

CERTIFICATIONS

Submit completed attached DFARS 252.247-7022 Representation of Extent of Transportation by Sea.

4. SECTION 00 72 00 EIE UTILIDOR IDIQ TASK ORDER CONTRACT CLAUSES

52.211-10 Commencement, Prosecution and Completion of Work:

(a) Commence work under this contract within calendar days after the date the Contractor receives the notice to proceed.

(b) Complete the entire work, as described in the Proposal Schedule above, ready for use not later than XXX calendar days after receipt of NTP. The time(s) stated for completion shall include final cleanup of the premises.

52.211-10 Commencement, Prosecution and Completion of Work – Alt I:

(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed.

(b) Complete permanent steam, condensate, water and sewer and return to service not later than 15 September 2015. Complete landscaping, seeding, site restoration and all other work not later than 15 June 2016. The time stated for completion shall include final cleanup of the premises.

(c) The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 10 June 2014.

52.211-12 Liquidated Damages—Construction

$1048.00 / calendar day*

*Liquidated damages apply only to the completion of the utilidor work identified in FAR 52.211-10(b) above.

52.211-13, Time Extensions

52.211-18, Variation in Estimated Quantity

52.225-9, Buy American Act – Construction Materials

52.225-11, Buy American Act – Construction Materials under Trade Agreements (task order value > $10,335,931)

52.225-11, Alt I, Buy American Act – Construction Materials under Trade Agreements, Alternate I (task order value $7,864,000 or more but less than $ 10,355,931)

52.232-5000 Payment for Materials Delivered Off-Site

52.236-5000 thru 52.236-5010 (applies to Design Build task orders)

52.236-16, Quantity Surveys

52.236-17, Layout of Work

52.246-21, Warranty of Construction

(ALT 1)

5. SECTION 00 73 00.00 29 SPECIAL CONTRACT REQUIREMENTS

SCR-DB050, Proposed Betterments (applies to Design-Build task orders)

SCR-DB060, Sequence of Design-Construction (applies to Design-Build task orders)

6. EIE UTILIDOR IDIQ DIVISION 01 SPECIFICATIONS (Check applicable specifications)

01 22 00.00 10 Measurement and Payment

01 32 01.00 29 Project Schedule

01 33 00 Submittal Procedures

01 35 26 Government Safety Requirements

01 36 00.00 29 Radioactive Materials Procedures

01 42 00 Sources for Reference Publications

01 45 00.10 10 Quality Control System (QCS)

01 45 04.00 29 Contractor Quality Control

01 50 00 Temporary Construction Facilities and Controls

01 57 34.00 29 Storm Water Pollution Prevention Measures

01 58 23.00 29 Air Force Project Sign

01 62 35 Recycled/Recovered Materials

01 74 19.01 29 Construction and Demolition Waste Management

01 78 00 Closeout Submittals

7. ATTACHMENTS:

1) Task Order Proposal/Bid Schedule

2) Task Order Specific Terms And Conditions (Section 00 21 00)

3) Task Order Representation Of Extent Of Transportation By Sea

4) Task Order Selection Procedures and Basis of Award (Section 00 22 30)

5) Task Order Wage Rate Determination

6) Section 01 33 00 Submittal Register

7) Task Order Scope of Work/Specific Division 01 Specifications/Technical Specifications

8) Task Order Drawings

9) Other

RTA REPAIR UTIILITIES TO TLFS EIE342

Task Order Schedule Base Items

Item Estimated No. Description Quantity Unit Amount

001. Design and construct a utilidor from

Mech. Bldg 75135 to Bldgs 5133, 5134, 5135, 5145, 5146 and 5147. 1 Lump sum $_____________

001. Design and construct a utilidor from Manhole 350-6 to Bldgs 5111 and 5112 1 Lump sum $

Total of Base Items 001 thru 002 $

Option Items

Item Estimated No. Description Quantity Unit Amount

002. Design and construct the replacement of heating, domestic water and electric utilities and components in Mech. Bldg 75135 1 Lump sum $_____________

003. Design and construct the replacement of heating, in the mechanical rooms of Bldgs 5111. 1 Lump sum $

004. Design and construct the replacement of heating, in the mechanical rooms of Bldgs 5112. 1 Lump sum $

005. Design and construct the replacement of heating, in the mechanical rooms of Bldgs 5133. 1 Lump sum $

006. Design and construct the replacement of heating, in the mechanical rooms of Bldgs 5134. 1 Lump sum $

007. Design and construct the replacement of heating, in the mechanical rooms of Bldgs 5135. 1 Lump sum $

008. Design and construct the replacement of heating, in the mechanical rooms of Bldgs 5145. 1 Lump sum $

009. Design and construct the replacement of heating, in the mechanical rooms of Bldgs 5146. 1 Lump sum $

010. Design and construct the replacement of heating, in the mechanical rooms of Bldgs 5147. 1 Lump sum $

012. Excavate, stockpile and treat offsite POL contaminated soil. 10 Cubic Yards $

Total of Option Items 003 to 012 $

EVALUATION OF OFFERS.

1. AWARD: Award will be made in accordance with Section 00 22 20 - EVALUATION FACTORS FOR AWARD.

2. INCOMPLETE OFFERS: Failure to submit an offer on all items in the schedule will result in an incomplete offer and the proposal will be rejected. Lump sum or unit prices must be shown for each item within the schedule.

3. EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

4. SPECIAL CONDITION: If a modification to a offer based on unit prices is submitted which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the proposal schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the proposal schedule.

5. For CLINs 003-011, the Contracting Officer may exercise the option(s) by written notice to the Contractor not later than 90 days after contract award. Exercised items shall be completed within the contract completion period, unless the parties otherwise agree.

6. CLIN 012 shall be the cost for work identified in Section 02 61 13 “Excavation and Handling of Contaminated Material”.

For CLIN 012, the Contracting Officer may exercise the option by written notice to the Contractor at any time prior to the contract completion date. Exercised items shall be completed within the contract completion period, unless the parties otherwise agree. CLIN 012 shall be exercised throughout the contract period of performance, up to 100 cubic yards.

General Decision Number: AK140001 03/07/2014 AK1

Superseded General Decision Number: AK20130001

State: Alaska

Construction Types: Building and Heavy

Counties: Alaska Statewide.

BUILDING AND HEAVY CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Modification Number Publication Date 0 01/03/2014 1 01/17/2014 2 02/07/2014 3 02/21/2014 4 03/07/2014

ASBE0097-001 09/02/2013

Rates Fringes

Asbestos Workers/Insulator (includes application of all insulating materials protective coverings, coatings and finishings to all types of mechanical systems).........................$ 34.88 18.67

ASBE0097-002 09/02/2013

Rates Fringes

HAZARDOUS MATERIAL HANDLER

(includes preparation, wetting, stripping, removal scrapping, vacuming, bagging, and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 34.88 18.67

BOIL0502-002 01/01/2013

Rates Fringes

BOILERMAKER......................$ 42.97 26.60

BRAK0001-002 07/01/2013

Rates Fringes

Bricklayer, Blocklayer, Stonemason, Marble Mason, Tile Setter, Terrazzo Worker.....$ 39.03 18.86 Tile & Terrazzo Finisher.........$ 33.27 18.86

CARP1501-001 09/01/2013

Rates Fringes

MILLWRIGHT.......................$ 34.99 20.54

CARP2520-003 09/01/2013

Rates Fringes

Diver Stand-by....................$ 40.90 22.59 Tender......................$ 39.90 22.59 Working.....................$ 80.70 22.59 Piledriver Carpenter...................$ 36.59 22.59 Piledriver; Skiff Operator and Rigger..................$ 36.59 22.59 Sheet Stabber...............$ 36.59 22.59 Welder......................$ 42.15 22.59

DEPTH PAY PREMIUM FOR DIVERS BELOW WATER SURFACE:

50-100 feet $1.00 per foot 101 feet and deeper $2.00 per foot

ENCLOSURE PAY PREMIUM WITH NO VERTICAL ASCENT:

5-50 FEET $1.00 PER FOOT/DAY

51-100 FEET $2.00 PER FOOT/DAY

101 FEET AND ABOVE $3.00 PER FOOT/DAY

SATURATION DIVING:

The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.

CARP4059-001 09/01/2013

CARPENTER

Carpenter...................$ 36.59 22.59 Lather/Drywall Applicator...$ 36.59 22.59

ELEC1547-004 04/01/2013

Rates Fringes

CABLE SPLICER....................$ 39.87 3%+$22.93

Electrician;Technician...........$ 38.12 3%+$22.93

ELEC1547-005 10/01/2013

Line Construction

Rates Fringes

CABLE SPLICER....................$ 50.52 3%+26.18

Linemen (Including Equipment Operators, Technician)...........$ 48.77 3%+26.18 Powderman........................$ 46.77 3%+26.18

TREE TRIMMER.....................$ 34.12 3%+19.48

ELEV0019-002 01/01/2014

Rates Fringes

ELEVATOR MECHANIC................$ 50.42 26.785+a+b

FOOTNOTE: a. Employer contributes 8% of the basic hourly rate for over 5 year's service and 6% of the basic hourly rate for 6 months to 5 years' of service as vacation paid credit. b. Eight paid holidays:

New Year's Day; Memorial Day; Independence Day;

Labor Day; Veteran's Day; Thanksgiving Day; Friday after Thanksgiving and Christmas Day

ENGI0302-002 01/01/2014

Rates Fringes

Power equipment operators:

GROUP 1.....................$ 39.28 20.35

GROUP 1A....................$ 41.04 20.35

GROUP 2.....................$ 38.51 20.35

GROUP 3.....................$ 37.79 20.35

GROUP 4.....................$ 31.58 20.35

TUNNEL WORK

GROUP 1....................$ 43.21 20.35

GROUP 1A...................$ 45.14 20.35

GROUP 2....................$ 42.36 20.35

GROUP 3....................$ 41.57 20.35

GROUP 4....................$ 34.74 20.35

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Roller: Breakdown, Intermediate, and Finish; Back Filler; Barrier Machine (Zipper); Beltcrete with power pack and similar conveyors; Bending Machine;

Boat Coxwains; Bulldozers; Cableways, Highlines and Cablecars; Cleaning Machine; Coating Machine; Concrete Hydro Blaster; Cranes-45 tons and under or 150 foot boom and under (including jib and attachments): (a) Hydralifts or Transporters, all track or truck type,(b) Derricks;

Crushers; Deck Winches-Double Drum; Ditching or Trenching Machine (16 inch or over); Drilling Machines, core, cable, rotary and exploration; Finishing Machine Operator, Concrete Paving, Laser Screed, Sidewalk, Curb and Gutter Machine; Helicopters; Hover Craft, Flex Craft, Loadmaster, Air Cushion, All Terrain Vehicle, Rollagon, Bargecable, Nodwell, and Snow Cat; Hydro Ax: Feller Buncher and similar; Loaders (2 1/2 yards through 5 yards, including all attachments): Forklifts with telescopic boom and swing attachment, Overhead and front end, 2 1/2 yards through 5 yards, Loaders with forks or pipe clamps; Loaders, elevating belt type, Euclid and similar types; Mechanics, Bodyman; Micro Tunneling Machine; Mixers: Mobile type w/hoist combination; Motor Patrol Grader; Mucking Machines:

Mole, Tunnel Drill, Horizontal/Directional Drill Operator, and/or Shield; Operator on Dredges; Piledriver Engineers, L. B. Foster, Puller or similar Paving Breaker; Power Plant, Turbine Operator, 200 k.w. and over (power plants or combination of power units over 300 k.w.); Scrapers-through 40 yards; Service Oiler/Service Engineer; Sidebooms-under 45 tons; Shot Blast Machine; Shovels, Backhoes, Excavators with all attachments, and Gradealls (3 yards and under), Spreaders, Blaw Knox, Cedarapids, Barber Greene, Slurry Machine; Sub-grader (Gurries, Reclaimer, and similar types); Tack tractor; Truck mounted Concrete Pumps, Conveyor, Creter; Water Kote Machine; Unlicensed off road hauler

GROUP 1A: Camera/Tool/Video Operator (Slipline), Cranes-over 45 tons or 150 foot (including jib and attachments): (a) Clamshells and Draglines (over 3 yards),

(b) Tower cranes; Licensed Water/Waste Water Treatment Operator; Loaders over 5 yds.; Certified Welder, Electrical Mechanic, Camp Maintenance Engineer, Mechanic (over 10,000 hours); Motor Patrol Grader, Dozer, Grade Tractor, Roto-mill/Profiler (finish: when finishing to final grade and/or to hubs, or for asphalt); Power Plants: 1000 k.w.

and over; Quad; Screed; Shovels, Backhoes, Excavators with all attachments (over 3 yards), Sidebooms over 45 tons;

Slip Form Paver, C.M.I. and similar types; Scrapers over 40 yards;

GROUP 2: Boiler-fireman; Cement Hog and Concrete Pump Operator; Conveyors (except as listed in group 1); Hoist on steel erection; Towermobiles and Air Tuggers;

Horizontal/Directional Drill Locator;Licensed Grade Technician; Loaders, (i.e., Elevating Grader and Material Transfer Vehicle); Locomotives: rod and geared engines;

Mixers; Screening, Washing Plant; Sideboom (cradling rock drill regardless of size); Skidder; Trencing Machine under 16 inches; Waste/ Waste Water Treatment Operator.

GROUP 3: "A" Frame Trucks, Deck Winches: single power drum;

Bombardier (tack or tow rig); Boring Machine; Brooms-power;

Bump Cutter; Compressor; Farm tractor; Forklift, industrial type; Gin Truck or Winch Truck with poles when used for hoisting; Grade Checker and Stake Hopper; Hoist, Air Tuggers, Elevators; Loaders: (a) Elevating-Athey, Barber Green and similar types (b) Forklifts or Lumber Carrier (on construction job site) (c) Forklifts with Tower (d) Overhead and Front-end, under 2 1/2 yds. Locomotives:Dinkey (air, steam, gas and electric) Speeders; Mechanics (light duty); Oil, Blower Distribution; Post Hole Diggers, mechanical; Pot Fireman (power agitated); Power Plant, Turbine Operator, under 200 k.w.; Pumps-water; Roller-other than Plantmix; Saws, concrete; Skid Steer with all attachments; Straightening Machine; Tow Tractor

GROUP 4: Rig Oiler/Crane Assistant Engineer;Parts and Equipment Coordinator; Swamper (on trenching machines or shovel type equipment); Spotter; Steam Cleaner; Drill Helper.

FOOTNOTE: Groups 1-4 receive 10% premium while performing tunnel or underground work. Rig Oiler/Crane Assistant Engineer shall be required on cranes over 85 tons or over 100 feet of boom.

IRON0751-003 08/01/2013

Rates Fringes

Ironworkers:

BRIDGE, STRUCTURAL,

ORNAMENTAL, REINFORCING

MACHINERY MOVER, RIGGER,

SHEETER, STAGE RIGGER,

BENDER OPERATOR.............$ 33.55 25.53

FENCE, BARRIER AND

GUARDRAIL INSTALLERS........$ 30.05 25.53

GUARDRAIL LAYOUT MAN........$ 30.79 25.53

HELICOPTER, TOWER...........$ 34.55 25.53

LABO0341-005 07/01/2013

Laborers: South of the 63rd Parallel & West of Longitude 138 Degrees

GROUP 1.....................$ 29.25 22.32

GROUP 2.....................$ 30.25 22.32

GROUP 3.....................$ 31.15 22.32

GROUP 3A....................$ 34.43 22.32

GROUP 3B....................$ 35.26 22.32

GROUP 4.....................$ 18.82 22.32

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 32.18 22.32

GROUP 2....................$ 33.28 22.32

GROUP 3....................$ 34.27 22.32

GROUP 3A...................$ 37.87 22.32

GROUP 3B...................$ 38.79 22.32

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting; Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

LABO0942-001 07/01/2013

Rates Fringes

Laborers: North of the 63rd Parallel & East of Longitude 138 Degrees

GROUP 1.....................$ 29.25 22.32

GROUP 2.....................$ 30.25 22.32

GROUP 3.....................$ 31.15 22.32

GROUP 3A....................$ 34.43 22.32

GROUP 3B....................$ 35.26 22.32

GROUP 4.....................$ 18.82 22.32

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 32.18 22.32

GROUP 2....................$ 33.28 22.32

GROUP 3....................$ 34.27 22.32

GROUP 3A...................$ 37.87 22.32

GROUP 3B...................$ 38.79 22.32

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting; Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill

Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

PAIN1959-001 03/01/2013

NORTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

BRUSH/ROLLER PAINT OR WALL

COVERER.....................$ 30.15 19.10

TAPING, TEXTURING,

STRUCTURAL PAINTING,

SANDBLASTING, POT TENDER,

FINISH METAL, SPRAY,

BUFFER OPERATOR, RADON

MITIGATION, LEAD BASED

PAINT ABATEMENT, HAZARDOUS

MATERIAL HANDLER............$ 30.67 19.10

PAIN1959-002 03/01/2013

SOUTH OF THE 63RD PARALLEL

Painters:

Brush, Roller, Sign, Paper and Vinyl, Swing Stage, Hand Taper/Drywall, Structural Steel, and Commercial Spray............$ 28.39 18.85 Machine Taper/Drywall.......$ 29.64 18.85 Spray-Sand/Blast, Epoxy and Tar Applicator..........$ 29.74 18.85

* PAIN1959-003 01/01/2014

NORTH OF THE 63RD PARALLEL

Rates Fringes

GLAZIER..........................$ 36.51 19.31

PAIN1959-004 07/01/2012

Rates Fringes

FLOOR LAYER: Carpet.............$ 30.09 13.02

* PAIN1959-006 01/01/2014

SOUTH OF THE 63RD PARALLEL

Rates Fringes

GLAZIER..........................$ 36.51 18.59

PLAS0867-001 02/01/2014

Rates Fringes

PLASTERER

North of the 63rd parallel..$ 35.94 19.89 South of the 63rd parallel..$ 35.69 19.89

PLAS0867-004 02/01/2014

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

North of the 63rd parallel..$ 35.69 19.89 South of the 63rd parallel..$ 35.44 19.89

PLUM0262-002 07/01/2013

East of the 141st Meridian

Plumber; Steamfitter.............$ 36.02 25.62

PLUM0367-002 07/01/2013

South of the 63rd Parallel

Rates Fringes

Plumber; Steamfitter.............$ 38.46 20.74

PLUM0375-002 07/01/2013

North of the 63rd Parallel

Rates Fringes

Plumber; Steamfitter.............$ 39.96 20.85

PLUM0669-002 07/01/2013

Rates Fringes

SPRINKLER FITTER.................$ 42.05 21.67

SHEE0023-003 07/01/2012

South of the 63rd Parallel

Rates Fringes

Sheet Metal Worker...............$ 39.49 19.88

SHEE0023-004 07/01/2012

North of the 63rd Parallel

Rates Fringes

Sheet Metal Worker...............$ 44.08 19.59

TEAM0959-003 09/01/2013

Rates Fringes

TRUCK DRIVER

GROUP 1.....................$ 38.89 18.57

GROUP 1A....................$ 40.16 18.57

GROUP 2.....................$ 37.63 18.57

GROUP 3.....................$ 36.81 18.57

GROUP 4.....................$ 36.23 18.57

GROUP 5.....................$ 35.47 18.57

GROUP 1: Semi with Double Box Mixer; Dump Trucks (including rockbuggy and trucks with pups) over 40 yards up to and including 60 yards; Deltas, Commanders, Rollogans and similar equipment when pulling sleds, trailers or similar equipment; Boat Coxswain; Lowboys including attached trailers and jeeps, up to and including 12 axles; Ready-mix over 12 yards up to and including 15 yards); Water Wagon (250 Bbls and above); Tireman, Heavy Duty/Fueler

GROUP 1A: Dump Trucks (including Rockbuggy and Trucks with pups) over 60 yards up to and including 100 yards; Jeeps (driver under load)

GROUP 2: Turn-O-Wagon or DW-10 not self-loading; All Deltas, Commanders, Rollogans, and similar equipment; Mechanics;

Dump Trucks (including Rockbuggy and Trucks with pups) over 20 yards up to and including 40 yards; Lowboys including attached trailers and jeeps up to and including 8 axles;

Super vac truck/cacasco truck/heat stress truck; Ready-mix over 7 yards up to and including 12 yards; Partsman;

Stringing Truck

GROUP 3: Dump Trucks (including Rockbuggy and Trucks with pups) over 10 yards up to and including 20 yards; batch trucks 8 yards and up; Oil distributor drivers; Oil Distributor Drivers; Trucks/Jeeps (push or pull); Traffic Control Technician

GROUP 4: Buggymobile; Semi or Truck and trailer; Dumpster;

Tireman (light duty); Dump Trucks (including Rockbuggy and Truck with pups) up to and including 10 yards; Track Truck Equipment; Grease Truck; Flat Beds, dual rear axle; Hyster Operators (handling bulk aggregate); Lumber Carrier; Water Wagon, semi; Water Truck, dual axle; Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted "A" Frame manufactured rating over 5 tons; Bull Lifts and Fork Lifts with Power Boom and Swing attachments, over 5 tons; Front End Loader with Forks; Bus Operator over 30 passengers; All Terrain Vehicles; Boom Truck/Knuckle Truck over 5 tons; Foam Distributor Truck/dual axle; Hydro-seeders, dual axle;

Vacuum Trucks, Truck Vacuum Sweepers; Loadmaster (air and water); Air Cushion or similar type vehicle; Fire Truck/Ambulance Driver; Combination Truck-fuel and grease;

Compactor (when pulled by rubber tired equipment); Rigger (air/water/oilfield); Ready Mix, up to and including 7 yards;

GROUP 5: Gravel Spreader Box Operator on Truck; Flat Beds, single rear axle; Boom Truck/Knuckle Truck up to and including 5 tons; Pickups (Pilot Cars and all light duty vehicles); Water Wagon (Below 250 Bbls); Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted "A" Frame, manufactured rating 5 tons and under; Bull Lifts and Fork Lifts (fork lifts with power broom and swing attachments up to and including 5 tons); Buffer Truck; Tack Truck; Farm type Rubber Tired Tractor (when material handling or pulling wagons on a construction project); Foam Distributor, single axle; Hydro-Seeders, single axle; Team Drivers (horses, mules and similar equipment); Fuel Handler (station/bulk attendant); Batch Truck, up to and including 7 yards;

Gear/Supply Truck; Bus Operator, Up to 30 Passengers;

Rigger/Swamper

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.

The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rates.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007 5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 8 PAGES

REPAIR UTILITIES TO TLFs

01 19 30.00 29 SD-01 Preconstruction Submittals

1.4.1.2 GTraffic Control Plan

1.4.1.4.1 GTemporary Facilities Site Plan

1.6.1.1 GTemporary Facilities Site Plan

01 32 01.00 29 SD-01 Preconstruction Submittals

3.4.1 GPreliminary Project Schedule

3.4.2 GInitial Project Schedule

1.3 GProject Scheduler Qualifications

3.4.4 GPeriodic Schedule Updates

01 33 00 SD-01 Preconstruction Submittals

1.9 GSubmittal Register

01 35 26 SD-01 Preconstruction Submittals

1.6 G AAccident Prevention Plan (APP)

1.7 G AActivity Hazard Analysis (AHA)

1.6.1 G ACrane Critical Lift Plan

1.5.1.2 G ACrane Operators

SD-06 Test Reports 1.11Notifications and Reports 1.11.2Accident Reports 1.11.3Crane Reports

SD-07 Certificates 1.11.4Certificate of Compliance 1.8Confined Space Entry Permit 1.8Hot work permit

01 50 00 SD-01 Preconstruction Submittals

1.4 GConstruction site plan

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

AM#1

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 8 PAGES

REPAIR UTILITIES TO TLFs

01 50 00 3.3.1 GTraffic control plan SD-06 Test Reports

2.2.5 GBackflow Preventer Tests

01 57 20.01 29 SD-01 Preconstruction Submittals

1.7 GEnvironmental Protection Plan

3.4.1Eielson AFB Waste

Disposal\Borrow Pit Plan 3.4.4.1HAZMAT Inventory 3.4.4.2Material Safety Data Sheet

(MSDS)

01 57 34.00 29 SD-01 Preconstruction Submittals

1.4.1 GStorm Water Pollution Prevention

Plan (SWPPP)

1.4.2 GNotice of Intent (NOI)

3.1.2 GRecords

1.4.4 GNotice of Termination (NOT)

01 74 19.01 29 SD-01 Preconstruction Submittals

1.6 GWaste Management Plan

SD-11 Closeout Submittals 1.7Records

01 78 00 SD-03 Product Data 1.3.2As-Built Record of Equipment and Materials 1.7.1Warranty Management Plan 1.7.4Warranty Tags 1.4Spare Parts Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 8 PAGES

REPAIR UTILITIES TO TLFs

01 78 00 SD-06 Test Reports

1.8.3VIDEO RECORDINGS OF

TESTS AND O & M TRAINING

SD-08 Manufacturer’s Instructions

1.5Preventative Maintenance 1.5Condition Monitoring (Predictive

Testing) 1.5Inspection 1.7.1Instructions

SD-10 Operation and Maintenance Data

1.8Operation and Maintenance Manuals

SD-11 Closeout Submittals 1.3.1Record Drawings

1.6 GCertification of EPA Designated

Items

1.10 GInterim Form DD1354

1.10 GChecklist for Form DD1354

02 61 13 SD-01 Preconstruction Submittals 1.7Sampling and Analysis Plan 1.6Work Plan 1.5.1Qualifications 1.8Correspondence

3.4.3 GDisposal of Contaminated Soil

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 8 PAGES

REPAIR UTILITIES TO TLFs

02 61 13 3.4.3 GCertificates of Thermal Remediation

SD-06 Test Reports 3.7Site Assessment Report

02 82 14.00 20 SD-01 Preconstruction Submittals

3.2 GHazardous Materials Abatement

Plan SD-02 Shop Drawings

3.2 GDesign Drawings

SD-03 Product Data

GAsbestos Waste Shipment Records

GWeight Bills and Delivery Tickets SD-05 Design Data

3.2 GDesign Analysis

3.2 GSpecifications

23 07 00 SD-02 Shop Drawings

3.2.2.4 GMICA Plates

2.3Pipe Insulation Systems 3.2Pipe Insulation Systems 3.3Equipment Insulation Systems

SD-03 Product Data Certification

2.3 GPipe Insulation Systems

3.2 GPipe Insulation Systems

3.3 GEquipment Insulation Systems

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 8 PAGES

REPAIR UTILITIES TO TLFs

23 07 00 SD-08 Manufacturer’s Instructions

2.3 GPipe Insulation Systems

3.2 GPipe Insulation Systems

3.3 GEquipment Insulation Systems

23 57 10.00 10 SD-02 Shop Drawings Heating System

SD-03 Product Data 2.1.6Catalog Cuts 1.5Spare Parts 3.3Welding 3.16Framed Instructions

2.1EQUIPMENT

SD-06 Test Reports 3.15Testing and Cleaning

SD-07 Certificates 2.2.6.3Bolts

SD-10 Operation and Maintenance Data

3.17Operation and Maintenance Manuals

31 00 00 SD-06 Test Reports 2.1.3Structural Fill Sieve Analysis

31 09 20.00 29 SD-01 Preconstruction Submittals

3.3 GSampling and Analysis Plan

(SAP)

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 8 PAGES

REPAIR UTILITIES TO TLFs

31 09 20.00 29 3.8.1 GSafety and Health Program

(SHP)

SD-06 Test Reports

3.7 GField Report

3.1 GCorrespondence

SD-07 Certificates

3.4.1 GQualifications

32 12 16 SD-02 Shop Drawings 2.1Design Drawings

SD-05 Design Data 2.1Design Analysis 2.1Specifications

SD-06 Test Reports 2.1.3Subbase Analysis 2.1.4Aggregate Base Course

32 16 13 SD-02 Shop Drawings 2.1Design Drawings

SD-05 Design Data 2.1Design Analysis 2.1Specifications

2.7 GConcrete mix design

33 05 41.00 39 SD-02 Shop Drawings 2.2.6Design Drawings

SD-04 Samples 2.2.9Waterproofing and Dampproofing 2.2.8Insulation

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 8 PAGES

REPAIR UTILITIES TO TLFs

33 05 41.00 39 2.2.10Chemical Grouting 2.2.11Access Hatch 2.2.12Exterior Paint for Above Grade

Structure 2.2.13Concrete Masonry Units (CMU) for Facade SD-05 Design Data

2.2.5Manhole Ladders 2.2.6Pipe Support System 2.2.6Design Analysis 2.2.6Specifications

3.4.1.4 GConcrete mix design

2.2.7Corrosion Protection

33 11 00 SD-02 Shop Drawings 2.1Design Drawings

SD-03 Product Data 2.1.1Pipe Material 2.1.2Fittings and Specials 2.1.3Joints and Gaskets 2.1.4Pipe Insulation and Jacket

System 2.1.4.1Water Valve and Equipment

Insulation Covers 2.1.6Gate Valves 2.1.7Check Valves 2.1.8Expansion Joints

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 8 PAGES

REPAIR UTILITIES TO TLFs

33 11 00 2.1.9Supports 2.1.9Hangers 2.1.9Thrust Restraints 2.1.10Guides

SD-05 Design Data 2.1Design Analysis 2.1Specifications

33 63 13 SD-02 Shop Drawings 2.1.1Design Drawings

SD-03 Product Data 2.2Piping and fittings 2.3Valves 2.4Pressure gauges 2.5Temperature gauge 2.6Strainers 2.7Alignment guides 2.9Expansion Joints 2.10Insulation

SD-05 Design Data 2.1.1Design Analysis 2.1.1Specifications

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

TASK ORDER-SCOPE OF WORK

General Scope The project consists of the design and construction to renovate and repair utilities and construct new utilidor structures at Eielson Air Force Base. The new utilidors will include domestic water, recirculation piping and heating supply and return piping.

Additionally, all piping and equipment inside one central Mechanical Building and inside 8 Mechanical Rooms shall be removed and replaced. Bidders shall perform a site visit to verify existing conditions and gather information necessary to develop this task order proposal.

All work shall be in accordance with the IDIQ contract and the requirements of this task order scope of work.

Along with the required temporary utilities such as potable cold water, the contractor shall provide temporary potable hot water to each housing unit during construction.

Notifications of planned utility outages, planned duration of outages and any other impacts to base operations and housing occupants shall be in compliance with the following: No work to begin prior to 0800 on weekdays. No work to begin prior to 0900 on Saturday and Sundays. Work activities shall cease by 1900 daily (weekdays/weekends). No outages or closures prior to 0900. No work to occur on holidays, unless approved by EAFB at their discretion. Temporary utility services provided to all buildings affected. All work areas must be fenced. All road closures must be properly signed. All outages, traffic revisions or impacts must have 2 week notice to USAF prior to work. The Contractor shall post notices 48 hours prior to the begin of construction, and all subsequent outages, traffic revisions or impacts.

Environmental Notifications

Immediately notify the Contracting Officer followed by the 354th Civil Engineer Squadron, Environmental Flight (354 CES/CEVQ) if suspected contaminated soil or groundwater is discovered or a hazardous material spill occurs. Contact 354 CES/CEVQ at (907) 377-7745 or FAX (907) 377-1645 to report contaminated soil and/or groundwater, and (907) 377-7745 for hazardous material spills. The appropriate Eielson AFB environmental representative will provide the necessary notifications to ADEC or EPA.

Follow requirements of the IDIQ contract and specification 01 57 20.01 29 Environmental Protection and the Eielson AFB Environmental SOP regarding all environmental issues.

Health and Safety A confined space entry permit shall be issued in accordance with the contractor’s confined space entry program. Notify the Base Fire Department just prior to entry and again immediately upon exiting any confined space.

Any open flame work requires a permit issued at Fire Station No. 2, Bldg. 4870.

Notify the Security Forces and the Fire Department 72 hours prior to any road closure.

Notify the Fire Department a minimum of 72 hours prior to any fire hydrant outage.

The Contractor shall provide temporary water service to all occupied housing units when the existing water main is out of service. The contractor is not required to provide temporary fire hydrant service during construction.

The contractor shall comply with the latest edition of the Corps of Engineers safety and health requirements manual, EM 385-1-1.

General – Survey Data Government support for survey and location work shall be limited to provision of coordinate information for base survey monuments and provision of existing information from the base Geographic Information System (GIS) as appropriate to facilitate contractor design and as-built surveys.

Contractor shall perform field surveys as required to locate elements of existing systems that will affect the design, enable government review of the design, and tie project work to the base coordinate system.

General – AutoCadd drawings

Government-provided electronic CADD files referenced in Specification 01 78 00, 1.3.1.1, will be limited to information from the base GIS. Contractor shall be responsible for initiating and developing all other required CADD files and drawings.

General Site Work. 1) Buildings 5111, 5112, 5133, 5134, 5135, 5145, 5146, 5147 will be occupied during the construction of this project. The contractor shall provide pedestrian access to each building unit when access to the units are impacted by construction activities. Each unit shall have an access pathway separate from adjacent buildings and units. The access pathway shall be a hardened surface. Well compacted gravel is acceptable as long it is properly compacted and drained to prevent rutting or standing water. The contractor shall provide a temporary parking area(s) for the residents of the housing units impacted by this work. The size and location of the parking area(s) shall be coordinated with and approved by the Contracting Officer. If temporary parking is located in a non-paved area, the contractor shall provide and maintain a recycled asphalt pavement surface properly compacted and with suitable drainage to prevent rutting or standing water. After completion of work, the contractor shall remove the temporary parking area and restore the area. The contractor shall also provide a pathway from the temporary parking area(s) to the access pathways to the building units. All pathways shall be safe and conform to the requirements of this RFP, OSHA, State and local regulations.

2) All trenching and excavation shall be barricaded to prevent general public entry.

3) Restore those existing facilities which are disturbed in the course of construction to condition equal or better than the condition at the start of construction.

4) Existing utility locations are approximate.