Site Visit Agenda 19-B-0018 Replace Communications Trailor BLDG 56410 8 July 2020.doc
DOC document 33 KB Posted
- Solicitation number
- W91151-20-B-0018
About this file
This document provides details for a site visit agenda and federal contract opportunity to replace a communications trailer at Fort Hood, Texas. The solicitation is for a firm fixed price construction contract between $1,000,000 to $5,000,000 with a 180-day period of performance to construct a new communications server building. The site visit will take place on July 8, 2020 and interested parties must submit any requests for information by July 15. The bid opening is scheduled for August 4, 2020. The contract is set aside for total small businesses under NAICS code 236220 with a size standard of $39.5 million. The Mission and Installation Contracting Command at Fort Hood is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agenda – Site Visit
W91151-20-B-0018 Replace Communications Building 56410 08 July 2020, 1:00 P.M.
a. Sign-In attendees
Description of Work: The purpose of this project is to construct a new communication server building to replace the temporary trailer known as Bldg. 56410. New building shall house both NIPR and SIPR.
Administrative Matters
· Side bars need to be kept to a minimum during the site visit as not to miss important information from the Program Manager.
· No paper copies of the specifications and/or drawings will be provided. This information was provided via email.
· Attention is directed to the Specifications at Division I. The government takes these contract performance requirements seriously and intends to enforce them to the full limit of the law.
· Project Manager, Quality Control and Superintendent positions are considered key positions. These positions SHALL not be subcontracted below the prime contractor.
· All questions resulting from this meeting and site visit will be submitted in the form of a Request for Information (RFI). Any changes discussed here or the site will not be official unless an RFI is submitted.
· RFIs must be submitted through email. No RFIs should go directly to the program manager. Contracting will consolidate the questions and coordinate with the PM for answers.
sonja.s.fields.civ@mail.mil
· As a contractor you are not permitted to discuss any open requirements with DPW or their staff, all questions, comments and/or concerns MUST go through your contract specialist at Contracting (Pre-Award). Any communication with the Program Manager and/or COR between this site visit and the award of the contract could cause your company to be ineligible for award.
· In accordance with FAR 52.236-6 you will have a superintendent on every job. The QC is required to provide adequate quality control, but the superintendent must be on site whenever work is being performed. Pay attention to Division One Requirements. Please bid accordingly.
· When you turn in your proposal be sure to turn in the line item estimate like RS Means.
Note: RS Means line item estimate is the preferred method, but alternate compatible/equal to RS Means methods that include a line item breakdown will be acceptable to the government.
· The site visit is your time and your subcontractors’ time to take all measurements and pictures, view the existing site conditions and conditions of area surrounding the job site. This is the only authorized visit to the job site. Use your time wisely since you will not be able to return the site after this visit.
· If you need access to an area that is not accessible please bring it to my attention during this site visit and I will let the PM know.
a. Project Info:
a. Magnitude: In accordance with FAR 36.204 the magnitude of this project is between $1,000,000 and $5,000,000.
b. NAICS Code: 236220 Commercial and Institutional Building Construction
c. Period of Performance: 210 Calendar days (15 days for bonds and 30 days for contract admin time included)
b. Dates:
a. RFIs by email no later than 2:00 P.M CST. on 15 July 2020
b. Amendment/response due no later than 22 July 2020
c. Bid Opening conducted at 2:00 P.M CST on 04 August 2020
i. Intent to Bid is due by 30 July at 2:00 PM CST