Technical Exhibit F - Deliverables
PWS Title Due Date Submit To
1.12 Key Control Plan Within five (5) business
days of award of the first task order.
KO
1.12 Lost or compromised
keys/locks/combinations
Verbally within four (4) hours following discovery.
Written report within 24 hours.
KO
1.14.1 Safety Plan
A change to the Safety Plan
Within five (5) business days of award of the first task order.
After two (2) business days of the change.
1.14.1 Each accident or incident Verbally within four (4)
hours of the incident.
In writing within two (2) business days.
KO and the III Corps G1 Safety Office
1.14.1 OSHA 300 log of
occupational injuries/illnesses
Serious injury or death incidents.
The 5th business day of each month.
Immediately
1.14.2 Identify safety hazards on
DA Form 4755 and submit the completed DA Form
Project Manager shall submit within 24 hours after receipt from Contractor employees.
KO
1.16 Submit all travel and
supporting documentation for approval prior to issuance of a task order
At a minimum of ten (10) business days prior to the travel date.
KO
1.18 Quality Control Plan Within 30 calendar days of
award of the first task order.
KO
1.20.1 DA Form 5479-R and
Corrective Action Plan
(CAP)
Upon receipt of a Contract Discrepancy Report
KO
1.24 Provide the name, address, and phone number for the
onsite Project Manager and Alternate Project
Manager
Within three (3) hours following award of the first task order.
KO
1.28 Personnel List In writing within five (5)
business days of the first task order award. Changes in writing no later than 24 hours prior to the implementation. In emergency situations, and cases of adverse actions where this notice is not possible, in writing no later than 24 hours after the change is implemented.
1.32 Antiterrorism Training
(AT) Level I Submit certificates of completion within three
(3) business days after completion of training by all employees and subcontractor personnel
KO
1.33 iWatch Training No later than ten (10) business days after award of the first task order and ten (10) business days after initial hire for new employees.
KO
1.34 OPSEC –Standard
Operating Procedure
(SOP)/Plan
Within 90 business days of award of the first task order.
Government OPSEC Officer
1.34 Identify an Level II
OPSEC Coordinator
Within 30 calendar days of award of the first task order.
KO
1.34.1 New Contractor
employees shall complete
OPSEC Level I
Within 30 business days of reporting for duty
KO
1.34.1 All Contractor employees
shall complete OPSEC
Awareness Training
Annually KO
1.35 All Contractor employees
shall complete and provide certificate of completion for the DoD IA/Cyber awareness training
Before issuance of network access and annually thereafter
KO
1.36 Contractor and
Subcontractor shall submit proof of valid accreditation
At proposal submission KO
1.37 Contractor shall submit a
Phase-in Plan to the KO for approval
Within two (2) business days of award of the first task order.
KO
1.38 Phase-Out Plan Within 120 calendar days
prior to contract expiration.
KO
1.40 The Contractor shall
submit Individual
Subcontract Reports (ISRs) and/or Summary
Subcontract Reports (SSR) in eSRS.
Semi-Annually KO
4.3.1 Contractor shall submit
requests for new or extended services, Within five (5) business days after award communication equipment, email, any modification necessary to accommodate such equipment, and the use of existing equipment not specifically issued to or provided for use by the Contractor for approval
4.5.2 Contractor shall submit a
verbal request for insect and rodent control service
Within two (2) hours ESO/Building Manager
4.5.2 Contractor shall submit a
written request
Within 24 hours ESO/Building Manager
4.6 Contractor shall submit an
Energy Conservation Plan
Within five (5) business days of award of the first task order.
KO
5.4 Contractor shall provide
course instruction for MSE instruction
Within five (5) business days after verbal notification by the KO followed by the receipt of the task order
KO
5.4.1 Contractor shall provide a
projected schedule of courses
By 1 September of each year for review and approval
KO
5.4.3 Contractor shall
incorporate upgraded POIs into the instructional courses
Within thirty (30) days of receipt
KO
5.4.3 Contractor shall update, edit, print, and compile
POIs / instructional tools (such as training aids, pamphlets, discs)
Semi-annually or as required by TRADOC
KO
5.4.3.1 Provide all lesson material Seven (7) business days
prior to scheduled course start date
KO
5.4.3.2 Contractor shall use and
review publications and guidance listed in Section 6 of this PWS, and regulatory guidelines published by the State, Federal or military organization
Every six (6) months, to develop instructional materials
KO
5.10.1 Contractor shall provide a
copy of the roster
One (1) business day after the course start date and a roster one (1) business day after the course completion date.
5.10.2 Contractor shall provide a
written report by MSC, course title, number of soldiers, DA civilians, and Contractor personnel who attended MSE instruction during the month and the cost for each course. The report shall also include pass, fail, and drop from course information.
Three (3) business days after the end of the month
KO
5.10.3 Contractor shall provide a
written report by MSC, course title, number of soldiers, DA civilians, and Contractor personnel who attended MSE courses during the quarter and the cost for each course. The report shall also include pass, fail, and drop from course information.
Three (3) business days after the end of the quarter.
5.10.4 The Contractor shall
provide an annual report at the end of each fiscal year of students attending courses. The report shall provide by course taken:
the name, rank/grade, last four digits of the social security number, unit, MSC, and graduation status of each student.
Seven (7) business days after the end of each fiscal year.
KO
5.11 Contractor shall ensure
each student completes an
“Individual Evaluation Sheet”.
One (1) business day after course completion.
KO
5.12 Maintain test scores for
each student
One (1) fiscal year after course completion.
5.15 Contractor Manpower
Reporting
While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year