Repair Mechanical in Bldg 1001
Solicitation number
W91151-17-B-0005
Issued by

About this file

Amendment 0001

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0010961680 AD005953P

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Add the questions and answ ers resulting in the site visit on 27 March 2017.

2) Change performance period from 120 days to 210 days w ithin the solicitation.

3) Delete FAR 52.225-1, BUY AMERICAN-SUPPLIES from the solicitation.

4) Remove the w ords “mandatory and required”, from paragraph 5. Pre-Bid and Pre-Construction Conferences, of the Instructions to Offerors

5) All other terms and conditions w ill remain the same, to include the Bid Opening date of 17 April 2017 at 2:00PM.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Apr-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91151-17-B-0005

X 9B. DATED (SEE ITEM 11)

15-Mar-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Apr-2017

CODE

MISSION AND INSTALLATION CONTRACTING

MISSION CONTRACTING OFFICE (MCO)

BUILDING 1001, ROOM W103

1001 761ST TANK BATTALION AVE

FORT HOOD TX 76544-5025

W91151 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W91151-17-B-0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The Issued By organization below has been added:

MISSION AND INSTALLATION CONTRACTING

MISSION CONTRACTING OFFICE (MCO)

BUILDING 1001, ROOM W103

1001 761ST TANK BATTALION AVE

FORT HOOD TX 76544-5025

The contractor period of performance end date has increased by 90 days from 120 days to 210 days.

The following have been added by full text:

QUESTIONS FROM INDUSTRY

W91151-17-B-0005 Repair Mechanical Systems

Building 1001, Fort Hood, Texas Questions from Industry

April 4, 2017

1. The performance period is noted as 165 calendar days. Half of that will be taken up by submittal approval and fabrication. Each of the four air handlers has to be installed one at a time. Each one needs to be fully operational before the next can be taken down. The performance period is too short. Recommend 300 days. Contract duration to be extended to 210 days plus 30 days for processing of award.

Solicitation page 3 of 60 CLIN 0002 Contractor Manpower Reporting. What is this? We have tried to access the website from the web access shown. Both the “US Army CMRA Help and Definitions” and the “View an on line demo” prompt a “Cannot reach this page” response. Why is there a cost associated with it? Please disregard CLIN 0002 Contractor Manpower Reporting (CMR), this line will be deleted prior to award..

2. Clauses incorporated by full Text: page 13 of 60 in the Solicitation: Cost Limitations: It states that limitations are stated in the schedule. What schedule is this? It is not included in the construction documents. The schedule is located on page 3 of 60. If there is no cost limitation stated on under CLIN 0001 then this does not apply to this solicitation. DFARS 252.236-7006, COST LIMITATION is a required provision to allow the Government to call out any cost limitations as needed.

3. Page 36 of 60 of the Solicitation “Buy American Supplies” (c) Offerors may obtain from the Contracting officer a list of foreign articles that the Contracting Officer will treat as domestic for this contract. Can you issue this list, please? FAR Clause 52.225-1 BUY AMERICAN-SUPPLIES will be omitted from this solicitation.

4. Sheet MH111 has a sheet note symbol with a 6 in it in room 127 but there is no description for it at the sheet notes. There is an error, the note symbol with #6 shall be removed and replaced with note symbol #3.

5. Solicitation page 7 of 60 – Submission of bids: “The offeror shall submit a bid that provides a complete line item breakout of tasks, quantities, and unit prices, that reflects the complete work effort required by the contract”. Why is this necessary in a project that is being bid by a large group of Contractors? Not everyone has a seat for RS Means. Also, what method would they use, Overhead and Profit? Bare Costs?

City Cost Index? Coefficients? The subcontractor numbers come in barely in time to get the bid together for submission. There is no time to prepare or coordinate the estimate with the subcontractors’ bids. We can understand this need for the line item back up for sole source projects but not for open bids. Can this be waived, please? This requirement will not be waived. Please submit a complete line item breakout to support your overall bid.

6. During the site visit we did not get into every room to investigate what devices are embedded in the ceiling, such as sprinkler heads that may have to be capped to prevent a flood in case they are broken, mass notification and fire alarm devices mounted in the ceilings, light fixtures to be supported while ceiling is being replaced, smoke detectors, speakers, etc. Room 185 comes to mind. The user would not let us in.

Room 185 will not be occupied during construction. The COR will coordinate with the user to ensure this room and other affected areas are ready for construction when contract is awarded.

The contractor will be responsible to field verify all surrounding and concealed items prior to demolition.

All items damaged during demolition that are to remain will be the responsibilities of the contractor to repair to the original state. (See notes on sheet A-001 to A-116 for ceiling repair and replacement.)

7. The project requires that any work outside of the mechanical rooms will have to be done after hours. Will there be government security during after-hours work to safeguard the areas?

After-hours work and all work will need to be coordinated with the COR. The bldg. is critical and cannot be shut down. Construction outside mechanical rooms during normal hours will not be allowed. Therefore, weekends and after-hours work outside the bldg. will be permitted through the COR. The contractor will be responsible to secure the construction areas as mentioned in the scope of work.

8. Most of the rooms visited, where above ceiling work will be required, are full of furniture and equipment.

Furniture can be moved around a bit to gain entry but the contractors cannot be responsible for the computers, printers and other expensive equipment that is in the rooms. The User will have to remove these items.

All work will be coordinated with the COR. The users will only be responsible to move their computers and other electronic devices. Contractor will be responsible for moving around furniture and place it back in original place when work is complete.

9. Confirm that any ruts made in the grassed areas outside, caused by the lifting equipment used while installing in the air handlers, will need to be repaired. Yes. Contractor will be responsible to repair any damages or ruts made in the grassed areas outside the bldg.

10. Per Observation on Job Walk, it was noticed that the existing floor mounted air handling units have external isolation on air handling units. The new air handling units will come with internal vibration isolation on the fan section itself. Please confirm that external isolation is not required if complete fan section is isolated and meets the requirements of note # 7 on M-0002 and Section 23 05 48.00 40/ Paragraph 2.2.10?

It is acceptable to use internal isolation provided it meets the requirements of the specifications.

11. Would Government like an extended compressor warranty? If so, parts only or parts and labor? It is recommended to do parts and labor to a betterment for the government for the duration of the warranty so that there are no procurement hoops to jump through something where to happen after the 1st year warranty period.

Warranty requirements should comply with the project specifications.

12. The scope of work for this project requires the controls contractor to tie new controllers onto an existing building network. In order to do this, the controls contractor will need to be provided with the current LNS database for the building once the contract has been awarded.

Contractor will be responsible for installing and programming new DDC controllers for the equipment installed on this contract. Contractor shall connect to the existing LON Trunk. If there are existing network points necessary to complete the controls on this contract (i.e. outside air temp, occupancy, etc.), the contractor will need to provide new devices on this contract and not expect to receive data via the existing LON network. At the conclusion of construction, the contractor shall provide the government with all software/databases (in accordance with the specifications) to allow for future integration of new controllers into the existing building network (by others). At that time, any duplicate network points will be consolidated (by others).

Please confirm that the DDC Control Data base can be accessible during construction to ensure that connecting everything back to the Lon Truck is correct and able to be tested?

See above response.

13. The design drawings call for some of the new equipment to be shut down by an ATFP emergency shutdown button. Clarification is needed as to whether this will be a new ATFP shut down button for just these units or if these units will need to be shut down but an existing shut down push button(s). If these units will tie into existing buttons, it is requested that the control contractor be provided with information regarding where these points are terminated and what SNVTs are used to achieve this shutdown.

A new emergency shutdown button will be installed in the 1st Floor bldg. supervisor’s office that will shut down the AHU’s installed on this contract.

14. Please confirm if there are any ATFP requirements during the period of the mechanical room exterior walls/windows being removed? If all the work cannot be completed in one day is there anything that needs to be done with except of temporary plywood or something of this sort to secure exterior wall?

The contractor will be responsible to secure the exterior wall/windows being removed as stated in the drawings.

15. New Drawings call for all shut-off valves to be replaced at each air handler. Can the new shut-offs go after existing one and existing valve be abandoned in place or would the Government prefer the lines be frozen and valve removed being that we cannot shutdown the complete system of the building? Please advise. Existing shutoff (isolation) valves may be installed after the existing valves and existing valves may be abandoned in place.

16. Is commissioning required on the new work only or any other equipment/systems in the building not being worked on? Commissioning will be required on new work only.

17. Is Test and Balance required on new work only or any other equipment/systems in the building not being worked on? Test and Balance will be required on the new and existing equipment in the entire 1st floor of the bldg.

18. On the test and balance of the air handlers, are we balancing just the new air handling units or does there need to be a grille to grille balance. If needs to be grille to grille, can the government confirm that we shall assume that all required balancing devices are installed and present? Yes. Test and Balance is required for the entire 1st floor of the building to include grille to grille balance.

19. Please post the pre-bid/site visit sign in sheet on FBO. The pre-bid/site visit sign sheet is not required to be posted to FBO.

20. Please furnish fire sprinkler “as built” drawings. We need to know what areas are covered by fire suppression risers in case we have to cut off the water to cap sprinkler heads.

As-built drawings for the existing fire sprinkler system will be provided, but the government will not be responsible if there is any discrepancy in the as-built or the as-built doesn’t match the existing. The contractor shall field verify sprinkler system prior to any demolition.

21. Please provide a spec on the metal ceiling tiles to be replaced in the auditorium/conference room 108.

Contractor shall match existing for the metal ceiling tiles - 24’’x 24’’ perforated metal pans with black acoustical liners.

22. Sheet A-111 states that existing ceiling tile is Armstrong Cirrus. It was noticed during the site visit that the existing ceiling tile is mostly fissured tile. Please advice what type of ceiling tile is required to be installed in the rooms where the ceilings are to be replace – those marked as 1 on the sheet notes?

As stated in the drawings; replacement ceiling shall match existing (grid and tiles)

23. Will underground site survey be marked to locate irrigation sprinkler system or other utilities in the exterior landscaped areas to be crossed to get access for the air handlers?

Contractor shall apply for and obtain a dig permit from DPW dig permit office for this project prior to any type of soil penetration or use of lifting equipment. All utility outages shall be scheduled through the COR.

24. Confirm that any damage to landscaped areas caused by cranes or other lifting equipment needs to be repaired.

Yes, the contractor will be responsible to repair any damage to the landscaped areas caused by cranes or other lifting equipment.

25. Will landscape irrigation be disabled during construction?

All work shall be Coordinated with the COR.

26. Sheet M-002 General Note 11, “Provide 20 temporary plug in type heating/cooling units….” Will condenser discharge heat be required to be ducted to the exterior of the building or is above ceiling ok?

Condenser heat discharge can be ducted to above ceiling.

27. Will individual electric circuits need to be provided for spot coolers?

No.

28. Will areas for duct relocation and additions of VAV boxes be occupied during construction?

Yes, some areas will be occupied and some will not. All work will be coordinated with the COR.

29. Will chillers be required to have five year parts, labor and compressor warranty?

Provide warranty in accordance with the specifications.

30. Will provisions be provided for access to building exterior for equipment, lifts, and crane?

This needs to be coordinated with the COR.

31. Will underground site survey be performed to mark underground utilities? See above response for question # 24.

32. Will Contractor be responsible for any landscaping or underground repair required for damage to grass or irrigation system? Yes.

33. Will irrigation system be disabled during construction period?

Any necessary outages will be scheduled through the contract COR.

34. For temporary spot coolers will condenser discharge heat be required to ducted to the exterior of the building or is above ceiling acceptable? Above the ceiling is acceptable.

35. Will individual electrical circuits need to be provided for spot coolers?

There is no need for individual electrical circuits.

36. Will areas for duct relocation and additions of VAV boxes be occupied during construction?

Yes. Some areas will be occupied and some will not. All work shall be coordinated with the COR.

37. Will Chillers be required to have Five year parts, Labor and Compressor warranty?

Provide warranty in accordance with the specifications.

38. Please clarify cost magnitude. On the synopsis page it says 500k-1mill. In the solicitation it says 1mill- 5mill. The correct cost magnitude for this project is $1,000,000.00 to $5,000,000.00.

39. Will it be acceptable to install copper and copper propress type fittings for the new AHU piping?

See specs for details.

40. Do to the expected lead time on materials will the Government extend the POP beyond the given 120 calendar days? Contract duration to be extended to 210 days plus 30 days for processing of award.

41. Where will the contractor’s waste container be placed? This needs to be coordinated with the COR and discussed during pre-con meeting.

42. Will the contractor be given a laydown area inside of the facility? No.

43. During the removal and replacement of the AHU’s, turfed areas will be disturbed. Can you please provide what type of Sod will be required? Contractor shall be responsible for any damage to the facility or surrounding areas due to the construction process. Sod replacement shall match existing.

The following have been modified:

SYNOPSIS

PROJECT SYNOPSIS

RPR MECHANICAL SYSTEMS

Building 1001 Project No. AD005954P

DESCRIPTION OF WORK:

The work shall be located at building 1001, located at the intersection of TJ Mills Blvd, and Tank Destroyer Blvd, Fort Hood Texas. The exact location will be shown by the Contracting Officer. Building(s) will be occupied during performance of work under this Contract.

The purpose of this project is to replace the existing (4) air handling units and associated return fans on the 1st floor of bldg. 1001 with new. Adding new VAV boxes with ductwork in rooms with insufficient airflow and adjust existing ductwork and diffusers as shown on the drawings. Remove CRAC units from room 183 and install VAV boxes with ductwork and diffusers. Adding new exhaust fan with ductwork and grilles in the Blimpie’s shop.

Replacing the existing (3) centrifugal chillers with new chillers. Connecting new chillers, air handling units and VAV boxes with new DDC controls.

The following drawings are included as part of the Solicitation.

After award, one set of Adobe PDF contract drawings and PDF specifications, and one set of Micro Station format drawings will be furnished to the Contractor on a CD. Reference publications will not be furnished. Contractor shall immediately check furnished drawings and notify the Government of any discrepancies.

A project construction sign will be required for this project. Contractor shall keep all permits and other documents required to be on the job site in a 3-ring binder or posted on a bulletin board within the construction area.

PERFORMANCE PERIOD: Complete the project within 210 calendar days unless the Government extends the period of performance by written contract modification. Completion is defined as completion of all contractual obligations.

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

INSTRUCTION TO OFFERORS

Any bids received in response to this solicitation SHALL carry a 120 day acceptance period before prices need to be verified, extended or re-negotiated.

1. Submission of Bids The Offeror shall submit a bid that provides a complete line item breakout of tasks, quantities, and unit prices, that reflects the complete work effort required by the contract. The cost of project management, superintendence, quality control and fee shall be provided separately from the pricing provided for the various task area (s). The priced bid shall be supported by a draft progress schedule that demonstrates the offeror's understanding of the work requirements, phasing of work between buildings (if more than one building is involved in the project), and estimated time frames for ordering and installing equipment.

2. Public Bid Openings: Please refer to Block 13A of the 1442. Anyone wishing to attend the bid opening MUST notify the Contracting Officer (kay.d.brown.civ@mail.mil) and Contract Specialist (bentura.fernandez.civ@mail.mil) by email no later than 3 April 2017, 14:00 (2:00PM) CDT with a firm commitment to attend.

Public Bid Openings and Mailing Address:

Directorate of Public Works ATTN: Engineering Division (CONTRACTING SECTION) Building 4610, Engineer Drive Fort Hood, Texas 76544

Bid Opening will be conducted in Quality Assurance Conference Room, Building 4610 Engineer Drive, Fort Hood, Texas.

3. Pre-requisites for Specialty Trade licensure and certification:

Mechanical HVAC license class A (with minimum 5 years of experience), Certification Master electrician, Certification

In responding to this solicitation for bids, the bidder shall provide copies of certifications/training identified above and below as a part of the bid. Failure to provide this documentation will render the bid non- responsive and no further consideration will be given to that bidder for award of this contract. No substitution of the individual possessing the required pre-qualifications will be authorized without the written approval of the Contracting Officer, and no time will be allowed for the contractor to acquire the required training/certification after the contract is awarded.

4. Work Experience:

The prime contractor shall demonstrate that it possesses general construction contract management by providing at least three examples of relevant work experience in an awarded contract similar to the requirements stated in this solicitation. Documentation shall be submitted with the bid and include the contract number, the date of contract award, the customer's name and contact information, the awarded dollar value, the value of the contract at completion, a description of all work elements included in the contract, the number and type of specialty trades needed to complete the contract, the period of time allocated for completion of the work and actual time required to complete the work (include reasons for time extensions). Federal work experience is preferred; however, the Government will accept work experience from both State and institutional and commercial contracts as well. No residential work experience will be considered appropriate for this purpose. Failure to provide this documentation will render the bid/offer non-responsive and no further consideration will be given to that bidder for award of this contract.

5. Pre-Bid and Pre-Construction Conferences The Contracting Officer shall conduct a pre-bid/pre-proposal conference in conjunction with the site visit. Information on the scheduled Site Visit is located in FAR 52.236-3 SITE VISIT (CONSTRUCTION) (FEB 1995) of this solicitation. When such conference is scheduled, all potential bidders/offerors attending the site visit will be encouraged to attend the pre-bid/pre-proposal conference. Space limitations dictate that no more than two representatives from each company attend. The Contracting Officer will review Bid submission requirements, and other administrative matters critical for successful and timely performance of the work.

The Contractor shall attend a Government coordinated preconstruction conference within 10 calendar days of contract award. As a minimum, the conference shall be attended by the contractor’s appointed project manager, the superintendent, the QCM, and administrative personnel responsible for preparation of contract documents, certified payroll records and invoices. The contractor shall deliver letter appointments of its key personnel that include each individual’s duties, roles and responsibilities.

6. Subcontractor List Offerors shall submit a list of proposed subcontractors as an attachment to their bid. If offeror does not intend on utilizing subcontractors (self-perform), offeror shall state so in their bid. Failure to provide this listing or statement will render the quote nonresponsive and eliminate the offer from further consideration for award.

(End of special requirements)

SECTION 00700 - CONTRACT CLAUSES

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 30 calendar days after the date the Contractor receives the notice to proceed and BONDS are due no later than 15 calender days after receipt of contract award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 210 days after contract award. The time stated for completion shall include final cleanup of the premises.

(End of clause)

The following have been deleted:

52.225-1 Buy American--Supplies MAY 2014

(End of Summary of Changes)