Technical_Exhibit_E _W91151-16-B-0028 _24_Aug_16.pdf
PDF 65 KB Posted
- Attached to
- Repair South Range Road Federal contract opportunity
- Solicitation number
- W91151-16-B-0028
About this file
Technical Exhibit E W91151-16-B-0028 24 Aug 16
View the file
Other files for this federal contract opportunity
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Exhibit E AD000344P‐ Reconstruct South Range Road
Headquarters III Corps, Fort Hood Directorate of Public Works (DPW)
Technical Exhibit “E”
AD000344P –
Repair South Range Rd
Contract No. W91151-16-C-XXXX
Directorate of Public Works Engineering Division US Army, III Corps
4612 Engineer Dr.Fort Hood, TX 76544
Pulverizing
1. DESCRIPTION
This specification shall govern pulverizing an existing pavement and base in-place, adding crushed aggregate if required, mixing this material with water, and shaping and compacting the mix to produce a base.
2. MATERIALS
If required, add crushed aggregate to bring the finished surface to the established line, grade, and cross-section. Furnish hard, durable particles or fragments of crushed stone or gravel conforming to the size and quality requirements for crushed aggregate material normally used locally in the construction and maintenance of highways by Federal or state agencies. Furnish crushed aggregate with a maximum size of 1 inch (25 millimeters) as determined by AASHTO T 27 and AASHTO T 11. Furnish crushed aggregate uniformly graded from coarse to fine and free of organic matter, lumps or balls of clay, and other deleterious material. Crushed aggregate will be paid for under line item 205, Flexible Base Material.
3. EQUIPMENT
Pulverizing. Furnish a road reclaimer that is:
(a) Self-propelled;
(b) Specifically manufactured for in-place reclamation;
(c) Capable of reducing the existing material to the required size;
(d) Equipped with at least an 8-foot (2.4-meter) minimum cutting width
(e) Equipped with standard automatic depth controls adjustable in increments of ½ inch (13 millimeters); and
(f) Equipped with sufficient horsepower to constantly pulverize to the required depth in a single pass.
4. CONSTRUCTION OR WORK METHODS
Use the reclaimer to pulverize the existing roadway material, in-place until 100 percent passes the 2-inch (50-millimeter) sieve. Reprocess or remove larger particles, debris, unsuitable material, and excess material as follows:
Remove from project:
Recycle or dispose of material legally off the project or as directed by the Contracting Officer. Submit a statement documenting the nature and quantity of material processed or sold for recycling. Otherwise, submit a signed copy of the disposal agreement before disposal begins.
Mixing and Spreading:
Add water as necessary to adjust the moisture content of the mixture to within 2 percent of the optimum for compaction. Mix to produce a homogenous full depth mixture. Spread the mixture uniformly across the existing roadbed to provide a final compacted shape according to the established line, grade, and cross-section.
Compacting:
Determine the maximum density of the mixture according to AASHTO T 180, Method D.
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and places not accessible to the roller, compact the material with approved tampers or compactors.
Compact each layer to at least 95.0 percent of maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures.
Surface Tolerance:
If grade finishing stakes are required, finish the surface to within ±0.05 feet (±10 millimeters) from staked line and grade elevation.
If grade finishing stakes are not required, shape the surface to the required template and check the surface with a 10-foot (3-meter) straightedge. Defective areas are surface deviations in excess of ½ inch (13 millimeters) in 10 feet (3 meters) between two contacts of the straightedge with the surface.
Correct defective areas by loosening the material, adding or removing material, reshaping, and compacting.
Maintenance:
Maintain the aggregate course to the correct line, grade, and cross-section by blading, watering, rolling, or combination thereof until placement of the next course. Correct defects according to the Surface Tolerance specification.
5. MEASUREMENT
Measurement and payment for Full Depth Reclamation shall be measured in square yards for the depth indicated in the plan drawings.
6. PAYMENT
The accepted quantities will be paid at the contract price per unit of measurement. Payment will be full compensation for the work prescribed in this Section.
SAMPLING, TESTING AND ACCEPTANCE REQUIREMENTS
Material or Product
Characteristic Test Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Existing roadbed material or aggregate surfacing
Classification
Moisture-density
Density
AASHTO
M 145
T 180 Method D
Or
AASHTO T 99
Method C
T310
1 test Per soil type
1 test per mixture or change in material
In-place after compaction
Roadbed
Processed material
Yes
No
N/A
Before using in work
End of shift