DIRECTORATE OF PUBLIC WORKS
ENGINEERING DIVISION (CONTRACTING SECTION)
BLDG 4610, ENGINEER DRIVE
FORT HOOD TX 76544-5055
0010795560 CA900375P
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Answ er questions from industry, RFI's
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Sep-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91151-16-B-0010
X 9B. DATED (SEE ITEM 11)
16-Aug-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Sep-2016
CODE
MISSION AND INSTALLATION CONTRACTING
MISSION CONTRACTING OFFICE (MCO)
BUILDING 1001, ROOM W103
1001 761ST TANK BATTALION AVE
FORT HOOD TX 76544-5025
W91151 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W91151
FACILITY CODECODE
EMAIL:TEL:
W91151-16-B-0010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
RFI ANSWERS
1. In the submission of bids the solicitation states that we are supposed to submit a draft progress schedule. Is there a certain format it should be submitted in?
A. No
2. Certain specifications sections note that the work includes systems or equipment that is not outlined in the drawings. ie. There is no fire alarm and mass notification system outlined in the drawings, however, in the specifications 28 31 76 para 1.1.1 a “this work includes completion of a design and providing a new, complete, and modifying the existing fire alarm and mass notification system as described herein and on the contract drawings for the building…provide systems complete and ready for operation.” What is the government’s intent? To include the system or do the drawings dictate the scope of work of the project as a whole?
A. The submittal will be scrubbed upon contract award. Only adhere to what applies to this scope of work.
3. There are 2 submittal registers in the specifications which is to be used? Will the register be scrubbed after award to reflect the project?
A. Yes, the submittal will be scrubbed and tailored for this project upon contract award.
4. Drawing G-102 #3 under General Air Barrier notes states that the contractor is suppose to verify that all wall and window assemblies are adequately sealed, and that assemblies exhibit air tightness and water tightness. How does the government wish us to verify? Is there a certain test that they are expecting?
A. Air Barrier testing for airtightness, specifically for the affected areas. These areas are to be isolated from the rest of the library prior to testing. Drawings will be amended to remove the requirement of testing for water tightness.
5. Drawing AD-101 note #2 says to “assume affected areas contain mold…” Is it the government’s intention for all bidders to consider the demolition areas affected and therefore to be covered under Mold remediation?
A. Yes.
6. Drawing G-102 #1 States “new exterior walls shall be constructed utilizing closed-cell spray foam insulation and flashing techniques to minimize air leakage. Spray foam shall be applied to all exterior walls and columns.” I the government’s intent to only foam the NEW exterior walls or ALL existing and new exterior walls? If the government’s intent is to apply to all exterior walls will a different foam be acceptable?
W91151-16-B-0010
A. Only the cavities new walls are required to receive closed-cell polyurethane spray foam insulation.
7. The government wishes to construct and new walls and window assemblies capable of meeting a 3-second equivalent design blast load in accordance with ASTM F 2248. Is the rest of the building blast rated? If not it would it not be in the best interest of the government to match existing for cost and time purposes?
A. The concern is valid and noted. However, the contractor is expected to execute the work as described in the bidding documents and drawings. This guidance is an installation-wide requirement.
8. Has to roof leak been repaired / source of water leak for warranty purposes?
A. Yes, roof has been repaired.
9. Will there be a staging area for materials at rear of building?
A. Yes.
10. Will negative air machine be acceptable to have inside work area to help maintain dust control? The units will have a noise factor like a low fan sound.
A. Yes, this is acceptable.
11. Is insulation required above areas of new acoustical ceiling systems?
A. Insulation is required to be applied on new wall cavities, and be applied continuous from new wall up to lap existing portion of wall above and terminate at roof decking above.
12. Does the government have the manufacture name and style of carpet?
A. The Floor finish schedule featured in the as-built drawings shows the carpet flooring color to be “Scholar, 14820 Textbook” by Shaw/Stratton.
SECTION 00010 - SOLICITATION CONTRACT FORM
The Issued By organization has changed from
MISSION AND INSTALLATION CONTRACTING CMD
MISSION CONTRACTING OFFICE (MCO)
BUILDING 1001, ROOM W103
1001 761ST TANK BATTALION AVE
FORT HOOD TX 76544-5025
to
MISSION AND INSTALLATION CONTRACTING
MISSION CONTRACTING OFFICE (MCO)
BUILDING 1001, ROOM W103
1001 761ST TANK BATTALION AVE
FORT HOOD TX 76544-5025
(End of Summary of Changes)