This solicitation requests offers for the purchase and installation of one crankshaft grinder. Key details include:
-
The Army Materiel Command Contracting Command Redstone Arsenal is seeking the purchase and turnkey installation of a crankshaft grinder at Letterkenny Army Depot to support generator engine remanufacturing.
-
The grinder must be able to machine crankshafts from 9 to 52 inches in length with journal and throw sizes from 1 to 6 inches. It must have a distance between centers of 61 inches, swing over table of 19.5 inches, and grinding diameter of 8.1 inches.
-
Offers are due by 12:00 PM on March 14, 2024. The acquisition is a 100% small business set-aside. The government intends to make award without discussions to the lowest priced technically acceptable offer.
-
The contractor will be responsible for installation, utilities connection, training, documentation, and warrantying the grinder for a minimum of one year. The grinder must meet all safety and technical requirements detailed in the purchase description.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
( No Col lect Cal ls )
W911N222Q0014 17-Jan-2022
b. TELEPHONE NUMBER
717-267-9361
8. OFFER DUE DATE/LOCAL TIME
12:00 PM 14 Mar 2024
5. SOLICITATION NUM BER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
( SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t . Use Only)
23.
CODE 10. THIS ACQUISI TION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W911N29. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORM ATION CALL:
a. NAM E
MICHAEL S. LINDGREN
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRI NT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLI CI TATION INCORPORATES BY REFERENCE FAR 52. 212-1. 52.212-4. FAR 52. 212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRI ATION DATA
1. REQUISITION NUMBER
20.
ADDI TIONAL SHEETS SUBJECT TO THE TERMS AND CONDI TIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
W25G1Q130201AF
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52. 212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDI NG ANY ADDITI ONS OR CHANGES WHICH ARE
SET FORTH HEREIN, I S ACCEPTED AS TO I TEMS:
. YOUR OFFER ON SOLI CI TATION
28. CONTRACTOR IS REQUIRED TO SIGN THI S DOCUMENT AND RETURN
% FOR:SET ASI DE:UNRESTRI CTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILI TY
OFFEROR CODE
LETTERKENNY ARMY DEPOT
LETTERKENNY CONTRACTI NG OFFICE - ACC-RSA-LEAD
1 OVERCASH AVENUE, ATTN: CCAM-MLK, BLDG 2S
CHAMBERSBURG PA 17201-4150
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATI NG
CODE15. DELI VER TO CODE W25G1Q 16. ADMI NI STERED BY
12. DI SCOUNT TERMS11. DELI VERY FOR FOB DESTI NA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
OFFICE OF STRATEGIC MANAGEM ENT
BLDG 370 ASRS DOOR 18 AMLD- PLX
LETTERKENNY ARM Y DEPOT
CHAMBERSBURG PA 17201-4150
TEL: FAX:
717-2679834FAX:
TEL: SERVI CE-DISABLED
VETERAN-OWNED
SMALL BUSI NESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
NAI CS:
333517
OFFER DATED
29. AW ARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWI SE IDENTIFI ED ABOVE AND ON ANY
COPI ES TO ISSUI NG OFFI CE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOM EN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOM EN- OWNED
SM ALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF34
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTI TY IN COLUMN 21 HAS BEEN
RECEI VED I NSPECTED
32b. SIGNATURE OF AUTHORI ZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATI VE
32e. MAILI NG ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORI ZED GOVERNMENT REPRESENTATI VE
37. CHECK NUMBER
FI NALPARTI ALCOMPLETE
36. PAY MENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHI P NUMBER
PARTI AL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAI D BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAY MENT
41b. SIGNATURE AND TI TLE OF CERTIFYI NG OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/ MM/ DD) 42d. TOTAL CONTAI NERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W911N222Q0014
Section SF 1449 - CONTINUATION SHEET
SOLICITATION NOTES
1. System for Award Management (SAM): In accordance with FAR 4.1102, Offerors shall be registered in the SAM database in order to be eligible for contract award. No award will be made to an Offeror not registered.
Registration can be accomplished at https://www.sam.gov/portal/public/SAM/. Registration in this database shall remain active.
2. Annual Representations and Certifications: In accordance with FAR 4.1201, Offerors shall complete electronic annual representations and certifications within SAM as part of required registration. Registration in this database shall remain active and can be accessed at https://www.sam.gov/portal/public/SAM/.
3. Questions: Questions regarding this solicitation shall be submitted to the Contracting Officer, in writing, at least 5 calendar days prior to the closing date. Questions submitted after this time will be answered at the discretion of the Contracting Officer. The Contracting Officer for this action is Randy S Allison, randy.s.allison.civ@army.mil.
The contract specialist for this action is Jonathan K. Carroll, jonathan.k.carroll.civ@army.mil .
4. Award without Discussions: The Government intends to award without discussions, offerors should submit their best prices in their initial offer. If FAR Provision 52.212-2, Evaluation-Commercial Items, is included, Offerors must submit all information requested therein in order for the Government to determine technical acceptability.
5. Amendments: The Offeror shall submit to the Contracting Officer signed copies of all amendments issued to this solicitation. Failure to comply may cause your proposal to be rejected.
6. Payment: Payment for this action will be made by Electronic Funds Transfer (EFT) through the Defense Finance and Accounting Services (DFAS) utilizing Wide Area Work Flow (WAWF). See 252.232-7006 for more information.
7. Period for Acceptance of Offers: The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers
8. Set- Aside: The proposed contract is 100% set-aside for small business concerns.
9. Destination: Unless otherwise stated in the solicitation, Offerors shall provide FOB Destination prices.
10. Site Visit: A site visit is scheduled for 16 March 2022 @ 09:00 am Eastern Daylight Time. Site visit attendance is urged but is not mandatory; however, failure to attend a site visit shall not be a reason for price increases to the contract after contract award. Submit the names of all attendees to Jonathan K. Carroll at jonathan.k.carroll.civ@army.mil, no later than 3:00 PM EST on 10 March 2022.Offerors who do not submit this information will not be given access to the site. All attendees will meet at Building 2S, Directorate of Contracting, 1 Overcash Avenue, Letterkenny Army Depot, Chambersburg, PA. Offerors are required to obtain a visitor’s pass from the Badge Office, Building 2 South, located beside the Contracting Office, prior to arriving at the Contracting Office. Please allow at least 45 minutes for this process. You must provide a current picture identification, vehicle registration and proof of insurance to obtain a pass. The documentation you receive with your visitor pass must remain with you during the site visit and returned after the site visit and prior to departure of the Depot. **NOTE:
FOR THIS SITE VISIT, PLEASE WEAR STEEL TOED SHOES, HEARING PROTECTIONS AND SAFETY
GLASSES.
PURCHASE DESCRIPTION
LETTERKENNY ARMY DEPOT
PURCHASE DESCRIPTION
CRANKSHAFT GRINDER FOR
GENERATOR ENGINE REMANUFACTURING
1.0 General Information:
1.1 Scope: Request the purchase of one (1) crankshaft grinder. This specification establishes the minimum requirements for the purchase of a contractor installed crankshaft grinder at Letterkenny Army Depot (LEAD). The contractor shall provide all professional architectural, engineering and construction services for the preparation of all necessary drawings, specifications, calculations, cost estimates and related design, permits, fabrication, construction, installation and testing services for the completion of this project. The crankshaft grinder shall be installed turnkey in accordance with Original Equipment Manufacturer specification and standards. Specifications are based upon commercially available products and shall meet or exceed the minimum requirements specified in section 4.0 Specifications. The grinder shall have proper guarding to protect the operator and meets paragraph 4.6.5 requirements.
1.2 Place and Performance of Installation: All work shall be performed in building 350 Annex between the hours of 6:00 AM and 3:30 PM, Monday thru Thursday, exclusive of Federal Holidays and special depot closures (typically the Monday before or Thursday after Federal Holidays that fall on a Saturday, Sunday, Tuesday or Thursday). Other hours, weekend, and holiday work will be considered separately as requested by the contractor with adequate advanced notice and approved by the Contracting Officer.
1.3 Security Requirements: Contractor and all associated sub-contractor’s employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Risk Management or Security Office. Contractor workforce shall comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy.
Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. The contractor and all associated subcontractor employees shall also comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014- 05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.3.1 Security, Safety and Fire Protection: All work shall comply with LEAD Regulation 385-1 and Pamphlet
385-1. The equipment and the installation shall also meet all the safety criteria set forth in OSHA 1926.501 and ANSI/ASSE Z359.
1.3.2 Media Devices: All pictures shall be taken by LEAD representative and approved before release.
1.3.3 AT Level I Awareness Training: All contractor employees, to included subcontractor employees, requiring access to Army Installations, facilities, and controlled access areas shall complete AT Level 1 awareness training within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. AT level 1 awareness training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.
1.3.4 Physical Security: The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.3.5 iWATCH Training: The contractor and all associated sub-contractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program.
This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or contracting officer. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. iWATCH training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.
1.3.6 OPSEC Training: Per AR 530-1, Operations Security, new contractor employees and associated sub-contractor employees shall complete Level I OPSEC training within 30 calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. Level 1 OPSEC training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.
2.0 Government Responsibilities:
2.1 Government Furnished Property and Materials: The Government will provide the facilities, equipment, materials and/or services listed below:
2.1.1 Facilities: The Government will provide clear access to all working areas necessary for the contractor to perform the installation outlined, during the specified hours listed in section 1.2.
2.1.2 Equipment: none
2.1.3 Materials: Stock material for testing.
2.1.4 Services: none
2.2 Site Preparation: Letterkenny Army Depot will provide a clear area for installation of the equipment.
2.3 Utilities: LEAD will provide adequate utilities for the installation and operation of the machines in a disconnect. LEAD will also provide temporary utilities for the operation of equipment required for the installation of the industrial equipment.
2.3 Site Preparation: Letterkenny Army Depot will provide a clear area for installation of the equipment.
2.4 Utilities: LEAD will provide adequate utilities and connect them to the equipment. LEAD will also provide temporary utilities for the operation of equipment required for the installation of the industrial equipment.
2.5 Delivery and Storage: The Government will unload equipment but there will not be any extended storage.
The contractor will be required to be present for unloading and installing the equipment. The contractor will oversee and aid in unloading, and installing of equipment.
3.0 Contractor Responsibilities: The contractor shall be responsible to inform all of his workers, direct or contracted, and ensure they follow the information within this specification. The contractor shall also have a representative onsite to manage the project and be the point of contact (POC) to communicate and coordinate with Letterkenny’s POC.
3.1 Foundation: The grinder must operate properly and accurately on a 6 inch thick concrete slab floor. If the
6 inch slab isn’t sufficient for proper operation, the contractor is responsible to design and install an adequate foundation.
3.2 Utility Installation: Utilities are to be run overhead. The contractor shall provide all materials, equipment, tools, and labor necessary for the installation of all utilities. The contractor is responsible for connection of utilities.
3.3 Disposal Of Materials And Equipment: All salvageable materials and equipment removed by the contractor shall be delivered to the Depot Property Disposal Yard, Facilities Engineering Division warehouse, or other sites as directed by the Contracting Officer, or his representative and shall remain the property of the Government. Delivery shall be made during normal operating hours of the receiving activity. No Government materials or equipment shall be removed from the reservation by the contractor.
All packing, packaging, and scrap material accumulated during the performance of the contract shall be removed and disposed of properly by the contractor.
3.4 Dust Control: The contractor shall control the amount of dust generated during the installation of the system foundation and components, and shall prevent the spread of dust to occupied portions of the building. Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding or pollution.
3.5 Protection of Existing Structures and Equipment: The contractor shall take all necessary precautions to insure against damage to existing structures and equipment to remain in place.
3.6 Installation of New Equipment: The contractor shall be present, aid, and oversee the installation of the equipment provided under this contract. This shall include off-loading equipment, moving it to the installation site, positioning and installing floor mountings if needed. The contractor is responsible to remove all packaging and preservative material. Removed components shall not be taken from the Depot property. Removed components shall be placed in a location designated by the TPOC.
3.7 Wiring: All electrical work and materials shall be in compliance with the National Electrical Code and
National Electrical Manufacturers Association. All electrical installations shall be inspected and accepted by a certified electrician. All work shall be subject to inspection by LEAD electricians.
3.8 Pipe: Schedule 40 (minimum) black steel pipe, valves, and all materials necessary, shall be supplied and installed to provide the equipment with required adequate air and water supplies.
3.9 Fluids: The contractor shall provide all necessary fluids and chemical additives required for the start-up and proper operation of the equipment. The contractor shall supply LEAD with MSDSs for all the necessary fluids within 30 days after award of contract.
3.10 Permits: none.
4.0 Requirements:
4.1 Machine Capacities: The crankshaft grinding machine shall have the necessary minimum options to machine the stem, main journals, pin journals, and rear flange for a large number of different sized crankshaft from one cylinder to six cylinder.
4.1.1 The crankshaft grinder will have the capacity to machine crankshafts with the following feature sizes (All dimensions are in inches):
Crankshaft length range of 9 ¼” – 52”, journal sizes of 1 ¾” – 4 ½”, and a throw radius of 1”- 6”.
4.1.2 Machine Features: The crankshaft grinder will have the following features and specifications of minimum capacities:
61 inch distance between centers
19.5 inch swing over table
8.1 inch grinding diameter
Hand wheel feed of 0.0002 inch graduations Grinding wheel speed of 900-1000 rpm Max grinding wheel diameter of at least 28 inches Max width of grinding wheel of at least 2.5 inches Steady rest capacity of at least 1- 3.75 inches Chuck hold diameter of at least 8.5 inches Max weight capacity on centers of at least 430 pounds Max weight capacity on rests of at least 1000 pounds Maximum floor space of 157 inches (long) x 66 inches (wide) Maximum work space of 220 inches (long) x 55 inches (wide)
4.1.3 Standard Equipment Package: The equipment package to operate the grinder at standard operating conditions will include the following minimum items:
Grinding wheel and hub Narrow steady rest with dial indicator Universal steady rest Length of stroke setting tool Throw setting tool Set up tool with dial indicator Diamond dresser Wheel balancing arbor Pair of extra counterweights Grinding motor reduction pulley Coolant nozzles (pair) Wrench set Service tools
4.2 Machine Control System:
4.2.1 Control Features: The crankshaft grinder shall have a CNC, PLC (electronic) type control, or equivalent.
All machine functions shall be controlled and monitored through the operator’s control panel/interface;
shall be capable of being set through machine code input into the control, Human Manual Interface (HMI).
Machines that are network capable must have an Ethernet connection and be Win10 compliant.
4.2.2 Control Software Compatibility: If the machine has a CNC control or equivalent and part programs can be written and loaded onto the control, the control software must be Win10 compliant and shall be compatible with Mastercam 2020 and current version software.
4.3 Machine Features: The machine shall include, but not limited to, hydraulic dresser, hydraulic table feed, in process measuring of journal diameters, coolant system, and steady rests.
4.4 General Requirements:
4.4.1 Painting: All surfaces to be painted shall be cleaned of all foreign matter. The equipment shall be painted
IAW standard commercial practice that shall not be less than one coat of primer and one coat of finish color.
4.4.2 Lubrication: Means shall be provided to ensure adequate lubrication to all moving parts. All oil holes, grease fittings and filler caps shall be easily accessible.
4.4.3 Power Requirements: All power requirements shall be 220V 3ph. If any requirement is not, the contractor shall supply all required transformers.
4.4.4 Automatic Lubrication: The system shall include a centralized lubrication system to automatically provide lubricant to critical components.
4.4.5 Energy Efficiency: All equipment that directly consumes energy in normal operation shall be designed and constructed for the highest degree of energy efficiency as governed by the latest developments available within industry.
4.4.6 Documentation: Two sets (each) of paper and one (each) CD of operator instruction manuals, maintenance service manuals, and parts listing manuals shall be provided for the furnished systems. These manuals shall be written in the English language.
4.4.7 Preservation, Packaging and Delivery: The contractor shall utilize standard commercial methods for preservation and packaging appropriate for each unit and acceptable to commercial carriers. As a minimum, all areas susceptible to damage from exposure to the elements shall be preserved and/or packed to prevent damage. The contractor shall be responsible for ensuring the equipment is delivered to LEAD in good condition.
4.4.8 Warranty: The contractor shall furnish with the equipment a standard commercial warranty or full one year warranty (parts, labor, and shipping, at minimum), whichever is greater. The contractor shall provide commercial warranties for any subcontracted components that will be underwritten. The contractor shall supply all corresponding warranty contact names and phone numbers before the end of the project. The warranty shall be effective beginning immediately after final acceptance of the equipment and not before that time.
4.4.9 Inspection and Acceptance: The equipment shall be examined for design, construction, materials, components, and workmanship to determine compliance with the contract and this specification. Any deviation from these requirements shall be cause for rejection.
4.5 Environmental Requirements:
4.5.1 Mercury Restriction: The equipment shall not contain mercury compounds nor be exposed to free mercury during manufacture.
4.5.2 Asbestos Restriction: Asbestos and materials containing asbestos shall not be used in or on the equipment.
4.5.3 PCB Restriction: Equipment and materials containing Polychlorinated Biphenyl (PCB) shall not be shipped to Letterkenny Army Depot.
4.6 Safety Requirements:
4.6.1 Equipment Hazards: All hazards inside the machinery shall be guarded against unauthorized access.
Clearly visible signs and symbols shall warn personnel in the area, and interlocks, safety mats and redundant deactivation systems shall guard against accidental access to the tooling and moving parts. Guards shall be easily removable to facilitate inspection, maintenance, or repair.
4.6.5 Safety Guarding: The grinder design must meet OSHA standards for safety and guarding of the machine.
This is addressed in OSHA subpart O, paragraphs 1910.211-1910.219. The machine must meet applicable requirements.
4.7 Installation Requirements:
4.7.1 Design and Installation: The contractor shall provide all parts, labor, and services for the design, fabrication and installation of the crankshaft grinder and accessory equipment. The contractor shall provide competent English speaking personnel to place the system in operation and to conduct the acceptance tests and training of depot personnel. The contractor, through his service personnel, shall oversee and aid in the offloading and installation of the equipment. The contractor or their service personnel will be fully responsible for the activation and testing of the system and the service personnel shall remain until system activation and testing has successfully been completed.
4.7.2 Badges: Identification badges will be issued for admittance of personnel before performing work or service on this contract. The identification badge is the property of the US Government and must be returned upon termination or demand. The contractor/vendor agrees that he will ensure all badges issued to employees are returned to the Badge and Identification Section, Security Division, Letterkenny Army Depot promptly on termination of need or on expiration, which occurs first. The badge room is located in Bldg 2, phone # 717- 267-5301. Hours of operation are 7:30 AM to 3:30 PM, Monday thru Friday, exclusive of Federal Holidays.
4.7.3 Fire Extinguishers: The LEAD R 385-1 designates the type and number of fire extinguishers required to perform the contracted work. The LEAD Fire Department will not provide any extinguisher support. The contractor can gain the above information through a pre-construction conference, visiting the fire department, or phone 717-267-8231.
4.7.4 Use of Portable Gas or Arc Equipment: The contractor shall obtain a permit, from the LEAD Fire
Department, to use portable gas or arc equipment for cutting, welding or open flame operations. The Fire Department will require one day advance notice to permit necessary inspection before actually starting work, and notification when work is finished to allow for re-inspection. The Fire Department can be notified by calling ext. 8231. The contractor shall take necessary precautions to prevent fires IAW NFPA Standard No.
51B and LEAD R 420-13.
4.7.5 Spills: Any spills or releases of materials or wastes must be reported immediately to the site supervisor, the
LEAD Fire Department, and the LEAD Environmental Office per the LEAD Installation spill Contingency Plan (ISCP). Any such spills or releases generated by the contractor shall be contained, cleaned and disposed of by the contractor per the direction of the LEAD on-scene coordinator.
5.0 Applicable Documents:
OSHA Safety and Health Standards 29 CFR 1910 Occupational Safety and Health Standards (copies may be obtained at http://www.osha.gov)
Letterkenny Army Depot (LEAD) Publications:
LEAD Regulation 385-1: LEAD Safety and Occupational Health Program LEAD Pamphlet 385-1 – Safety Requirements for Security, Safety, and Fire Prevention for Contractors Performing Work on LEAD (Copies may be obtained at LEAD Directorate of Contracting, Bldg 2)
National Fire Protection Association NFPA Standard 70 – National Electric Code NFPA Standard 79 – Electrical Standard for Industrial Machinery (copies may be obtained from http://www.nfpa.org/)
6.0 Quality Assurance:
6.1 Quality Conformance Inspection: The vertical mill and all accessory components shall be subject to a quality conformance inspection, performed by a designated Depot representative, to determine compliance with this specification.
6.2 Tests:
6.2.1 Accuracy: If an accuracy test was performed by the OEM before the machine was shipped, the contractor shall repeat the accuracy test at LEAD after complete installation. The results of the test performed at LEAD shall be compared to those from the test at the factory. If no accuracy test was performed at the factory, the contractor shall be responsible for developing test procedures to demonstrate the accuracy and operation of the machine to be in compliance with the requirements of this specification. All test procedures shall be submitted to and approved by Depot Technical Point of Contact (TPOC) prior to the start of testing.
To support the testing procedures, LEAD will provide a supply of mild steel material of various thicknesses for use during the performance tests and training. If mild steel is not available, other readily available materials may be used. The contractor shall prove out all problems.
6.2.2 Post Processing Verification: none.
6.3 Technical Instruction: The contractor shall be responsible for providing technical instruction of four (4)
Depot personnel in the operation of the equipment and software and four (4) Depot personnel in the maintenance of the equipment supplied under this contract. All instructions, oral and written, shall be in the English language. The project LEAD TPOC will coordinate with individuals to be trained upon successful completion of all installation and test specifications.
7.0 Information Technology (IT) Industrial System Requirements:
7.1 Operating System (OS) Specifications:
7.1.1 If applicable, the system’s OS must be Microsoft Windows 10, Windows Server 2012R2, or Red Hat Linux v6.X. Any OS supplied with the system must contain all service packs, updated patches, and hot fixes. All patching and fixes will be current as of a predefined date agreed upon by the vendor and the government.
7.1.2 Defense Information System Agency (DISA) Security Technical Implementation Guides (STIGS) are configuration standards for the Department of Defense and contain technical guidance to lock down information systems and software applications that might otherwise be vulnerable to malicious attacks. The contractor shall be responsible for ensuring all appropriate STIGs are implemented and their software runs acceptably while secure.
7.1.3 The Army Golden Master (AGM) is a collection of security settings for Microsoft Operating systems which must be applied to all Army computer systems. LEAD will supply the AGM to the contractor who shall ensure their software functions as intended, when installed on top of the AGM.
7.2 Programmable Logic Controllers (PLC): If a PLC is to be installed within the system, it shall be manufactured by a government approved source and shall provide an Ethernet adapter to allow for connection to the Industrial Network if required. If an Ethernet connection is used to interconnect the PLC to peripheral equipment, an additional Ethernet port shall be provided.
7.3 System Software Specifications:
7.3.1 Software Installations: If installing application code at LEAD, the contractor shall install the code within a standard container (E.g., Program Files) and located in a volume separate from the standard System Files.
Interactive applications are required to run as services and daemons and any time WEB services are used, file types (E.g., XML and HTML) must be separated.
7.3.2 Software Licensing: When installed, the software licensing for computers, control units and other IT systems will be surrendered to the Information Technology Configuration Manager and will become the property of the Government upon acceptance of the system.
7.3.3 If software has been customized for LEAD’s use or is any software other than Commercial Off The Shelf
(COTS); the contractor shall provide copies of all source code, firmware and software used in the system, as well as one set of backup and configuration software for PLC’s, control and communication computers, and data acquisition. All programs shall be tested and fully operational before acceptance. All acceptance testing will adhere to common User Acceptance Testing (UAT) standards as defined by the government.
7.3.4 If any special programming software or programming software interface devices such as hardware "keys", dongles or "PIC" modules, are required to access software, these programs and devices shall be provided to
LEAD along with the necessary registration information. If custom application software was written and provided, a copy of the required compiler and compiler license shall also be provided. At acceptance, all items shall become property of the government. Software and hardware purchased for this project shall be registered to Commander, Letterkenny Army Depot, Chambersburg, PA 17201.
7.4 System Environment Specifications:
7.4.1 All supplied software must be capable of operating in a multi-user environment and data which contains permissions information shall be hidden from view and inaccessible to those with less than administrator level access. Shared accounts shall not be used, and users shall only be authorized the minimum security rights to operate the application software. Users will not have access to system or software configuration items (e.g., Control Panel, software and hardware installation). Under no circumstances will the intended end user log in using the Administrator or Root account for routine operation of the equipment. The use of these accounts will be restricted to only administrative activities which will be carried out by LEAD Information Technology personnel. All software products shall employ a minimum of three permission based levels of access.
7.4.1.1 Administrator - Full control at root level, restricted to LEAD IT personnel and when required, the Contractor.
7.4.1.2 Maintenance - Mid-level control required to perform maintenance and alter control parameters as needed.
7.4.1.3 Operator - Minimum control necessary to perform the routine operation of software. The Operator shall not be able to alter the programming of software, make changes to executable files, or modify control parameters.
7.4.2 Application Interoperability: If an application will interfere with the operation of the industrial system, E.g., (McAfee Anti-Virus), the Contractor shall provide a written statement to the LEAD IT Directorate explaining the technical restrictions placed upon them.
7.4.3 Auditing: If applicable, the contractor shall enable audit files and data logs for access by LEAD
Cybersecurity personnel to audit access and actions on the equipment.
7.4.4 User Acceptance Testing (UAT): LEAD Cyber Security Personnel will have the ability to conduct validation testing with approved security tools prior to equipment being introduced to the shop floor. This testing will also satisfy any UAT requirements. A UAT Plan will be furnished prior to testing and all equipment documentation will be made available for review during the test. If discrepancies are discovered the contractor shall remediate identified issues prior to government acceptance.
7.5 Documentation Requirements:
7.5.1 A complete set of instruction manuals containing all of the information necessary to operate, maintain, and reinstall all software and hardware contained within the system shall be provided by the Contractor. These manuals shall include step-by-step instructions which facilitate the rebuilding of the system in the event of a fatal system crash.
7.5.2 If networked, the Contractor shall provide the system’s network design drawings to the Information
Technology Directorate. These drawings should include complete directional data flow diagrams that include all ports and protocols in use.
7.5.3 The Contractor shall provide to Industrial Automation at least two electronic copies of all control unit programs. These copies should include description files of the ladder logic and any cabling required to connect to the control systems. No control units will be password protected and no other form of lockout measure shall be implemented by anyone other than LEAD IT employees. The Contractor shall also provide electrical wiring diagrams for all installed control systems to this LEAD Industrial Automation group.
7.5.4 Certificate of Networthiness: Certificate of Networthiness (CoN) certification ensures Automated
Information Systems (AIS) utilizing the Army Network are developed in compliance with the Clinger Cohen Act and are secure, supportable, sustainable, and compatible with the Army Enterprise Infrastructure (AEI) (as defined in AR 25-1). All new AIS capabilities and all capability modifications and upgrades must be assessed to validate their Networthiness (network security, network impact, compatibility with the infrastructure, infrastructure requirements, spectrum support, security policy compliance, Joint Technical Architecture –Army (JTA-A) standards compliance, communications and information manpower, training, logistics support, schedule, and funding). If software is installed within the system, the Contractor shall work with LEAD Directorate of Information Management (DOIM) personnel to check for CoN availability and when not available, ensure a CoN is requested and all documentation is submitted.
7.6 Proposal Deviations:
7.6.1 Proposals or specifications that deviate from those described herein shall be coordinated for specific approval or rejection by the LEAD Information Technology representatives prior to shipment, installation, or acceptance of the equipment.
8.0 Final Acceptance: Once all conditions of this contract are met, final acceptance will be after 100 hours of continuous operation without a breakdown or failure, or 14 days, whichever comes first. If the machine has a failure or breakdown and it is determined that is the fault of the machine hardware or software, the operating time and 14 days timeframe start over each time this happens. After the 100 hour operating time or 14 days have been met, final payment of this contract will be made.
QUESTIONS & ANSWERS
Q1: Will you consider a machine that is supplied by (a domestic small business) but manufactured in Europe for award?
A1: Yes, as long as the equipment meets the specifications in the Purchase Description and the offeror is a small business entity. Service should be completed by US base technicians.
Q2: Paragraphs 1.2., 2.2, 3.5 and 3.6:
What are open dimensions of building doorway machine must pass thru?
How far apart are canopy support bollards in front of building doorway machine will pass thru?
A2: The Block Machining Center must fit through a doorway in the building where the machine will be located.
The door opening is 117 inches high and 117 inches wide.
Q3: Paragraph 3.1: Is existing 6” concrete floor capable of supporting 250 Lbs/in²?
A3: Yes
Q4: Paragraph 4.1.2: What is distance between wall and aisleway where machine will be installed?
A4: There is no wall. Open room with crane support columns, 20 feet on center. 17-1/2 foot opening.
Q5: What is the application for your crankshaft grinder? Is it for crankshaft rebuilding ?
A5: Rework and regrinding, initially. Could expand applications.
Q6: We are confused because it appears in because in 4.2.1 it states:
4.2.1 Control Features: The crankshaft grinder shall have a CNC, PLC (electronic) type control, or equivalent. All machine functions shall be controlled and monitored through the operator’s control panel/interface; shall be capable of being set through machine code input into the control, Human Manual Interface (HMI). Machines that are network capable must have an Ethernet connection and be Win10 compliant. So this means:
- there must be some type of control but it may be a PLC or other sort?
- functions are to be set thru input to the HMI?
- But there does not have to be a CNC necessarily?..
Is this interpretation correct?
If the machine is for rebuilding it does not require a CNC?
A6: Control does not have to be CNC but must meet all functional requirements of grinder as stated in purchase description. If it is CNC (computer based), it must also meet network requirements of 4.2.1 Changes and grinder function adjustments must be done through the operator’s control/panel, whatever type it may be as described in purchase description.
Q7: Could you send us a drawing of the location where we must install your machine on your plant floor showing where the shop doors are in relation to the location, the width of any aisles and the width and height of the shop door through which we must enter?
A7: No Q8. Are we to understand that LEAD will unload and move our equipment to the location on your plant floor where it will be installed or do we require the use of our own riggers?
A8: Contractor is responsible to rig, move, and install machine.
Q9. If we require the use of our own riggers, can you refer us to a list of rigging companies which you use at your facility who are experienced in working on your base so that we may contact them for a rigging quote?
A9: The following riggers have done work on the depot. They have been hired by contractors for equipment that the depot purchased. None of these riggers are required to be hired and the contractor may use them or any other rigger they choose.
Al Smith Rigging 26 Track Dr, Binghamton, NY 13904 607-729-3090
Specialty Rigging Co LLC 601 Water St STE A, Temple, PA 19560 610-406-5188
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Each
CRANKSHAFT GRINDER
FFP
CRANKSHAFT GRINDER IN ACCORDANCE WITH ATTACHED
PURCHASE DESCRIPTION.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
NSN: 1500:8U850
MILSTRIP: W25G1Q130201AF
PURCHASE REQUEST NUMBER: W25G1Q130201AF
PSC CD: 3415
NET AMT
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 60 dys. ADC 1 OFFICE OF STRATEGIC MANAGEMENT
BLDG 370 ASRS DOOR 18 AMLD-PLX
LETTERKENNY ARMY DEPOT
CHAMBERSBURG PA 17201-4150
FOB: Destination
W25G1Q
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions JUN 2020 52.203-2 Certificate Of Independent Price Determination APR 1985 52.203-6 Alt I Restrictions On Subcontractor Sales To The Government
(JUN 2020) -- Alternate I
NOV 2021
52.203-12 Limitation On Payments To Influence Certain Federal Transactions
JUN 2020
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-21 Basic Safeguarding of Covered Contractor Information Systems
NOV 2021
52.204-22 Alternative Line Item Proposal JAN 2017 52.204-23 Prohibition on Contracting for Hardware, Software, and
Services Developed or Provided by Kaspersky Lab and Other Covered Entities
NOV 2021
52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment
NOV 2021
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
NOV 2021
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
NOV 2021
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.212-1 Instructions to Offerors--Commercial Products and Commercial Services
NOV 2021
52.212-3 Alt I Offeror Representations and Certifications--Commercial Products and Commercial Services (NOV 2021) Alternate I
OCT 2014
52.212-4 Contract Terms and Conditions--Commercial Products and Commercial Services
NOV 2021
52.219-6 (Dev) Notice of Total Small Business Set-Aside (DEVIATION 2020-O0008).
OCT 2020
52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies JAN 2020 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-35 Equal Opportunity for Veterans JUN 2020 52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020 52.222-50 Combating Trafficking in Persons NOV 2021 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
JUN 2020
52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.225-18 Place of Manufacture AUG 2018 52.232-30 Installment Payments for Commercial Products and
Commercial Services
NOV 2021
52.232-33 Payment by Electronic Funds Transfer--System for Award Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
NOV 2021
52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.237-1 Site Visit APR 1984 52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
52.242-13 Bankruptcy JUL 1995 52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984 52.247-34 F.O.B. Destination NOV 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7009 Limitations on the Use or Disclosure of Third-Party Contractor Reported Cyber Incident Information
OCT 2016
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism
MAY 2019
252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.237-7999 (Dev) Requirement for Accounting Firms Used to Support
Department of Defense Audits (DEVIATION 2019-O0007)
MAR 2019
252.243-7001 Pricing Of Contract Modifications DEC 1991 252.245-7000 Government-Furnished Mapping, Charting, and Geodesy
Property
APR 2012
252.247-7023 Transportation of Supplies by Sea FEB 2019
CLAUSES INCORPORATED BY FULL TEXT
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT
2020)
(a) Definitions. As used in this provision, “covered telecommunications equipment or services” and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representations.
(1) The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.
(End of provision)
52.211-8 TIME OF DELIVERY (JUN 1997)
(a) The Government requires delivery to be made according to the following schedule:
REQUIRED DELIVERY SCHEDULE
(Contracting Officer insert specific details)
Within Days 60 days ADC
The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.
OFFEROR'S PROPOSED DELIVERY SCHEDULE
Within Days
After Date
Item No. Quantity of Contract
(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed, or otherwise furnished to the successful offeror, results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day award is dated. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the Contractor's date of receipt of the contract or notice of award by adding (1) five calendar days for delivery of the award through the ordinary mails, or (2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term "working day" excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.
(End of clause)
52.212-1 INSTRUCTIONS TO OFFERORS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
(NOV 2021)
ADDENDUM TO FAR 52.212-1, INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS:
Paragraph (c) is changed to read: Period for acceptance of offers. The Offeror agree to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers, unless another time period is specified in an addendum to the solicitation.
52.212-2 EVALUATION--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
(b) Options.