This document is a Request for Proposals (RFP) for the replacement of a metal shed at Building #1420, Camp Henry in Korea, solicitation number W90VN924R0109. The RFP is being issued as a non-work plan task order under a Multiple Award Task Order Contract (MATOC) for MATOC contractors in Area IV only. The contractor shall provide all necessary resources to replace the metal shed in accordance with the Statement of Work, specifications, and contract terms. Proposals are due by 01:00 PM on June 7, 2024. Award will be made to the offeror submitting the lowest evaluated price proposal that meets the acceptability standards for non-cost factors. The contractor shall begin work within 10 calendar days and complete the project within 150 calendar days after notice to proceed. The contract includes Federal Acquisition Regulation (FAR) clauses related to electronic submission of payment requests, subcontracting, and tax exemptions for customs, excise, and value-added taxes in Korea.

View the file

Other files

File Type Posted
Amendment 0001-24R0109.pdf PDF
Drawing.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0012129752

Replace The Metal Shed at Bldg. #1420, Camp Henry (Project No. I5-10003-2J)

“THIS IS A NON-WORK PLAN TASK ORDER RFP TO MATOC CONTRACT, AREA IV CONTRACTOR ONLY”

This RFP is in accordance w ith terms and conditions of base year of MATOC General Construction contracts issued by 411th Contracting Support Brigade (CSB). The Proposals from of ferors other than these MATOC Contractors w ill not be considered for aw ard. Parent Contract Numbers: W91QVN24D0039 thru 0058, 0081, 0101, 0105 & 0110.

OFFERORS MUST COMPLY WITH THE FOLLOWING:

A. Site Visit: Offerors w ho intend to propose on this solicitation are encouraged to attend the site visit. See site visit clause FAR 52.236-27 in Section L. Offerors are required to have a valid Korean Identif ication Card w hen attending the site visit orientation.

B. If the contractor is unable to submit the proposal in response to this RFP, the contractor shall submit the “No-Offer Letter’ by date and the specif ied in this solicitation.

C. The contractor opportunity can be view ed through the https://w w w .sam.gov/. All pricing proposal and Section K (ATTACHMENT:

CONTRACTOR’S TAX EXEMPTION DECLARATION) of the solicitation shall be submitted by 1300 hours on the closing date of the RFP via hyeyong.chong1.ln@army.mil

MS. CHONG, HYE-YONG 315-763-5698

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

21-May-2024

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________150 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, X negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________07 Jun 2024 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO DAEGU, UNIT #15682

APO AP 96218-5682

UNITED STATES

W90VN9

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W90VN924R0109 22

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W90VN924R0109

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Work Type: "K"

FFP

Replace the Metal Shed at Bldg. #1420, Camp Henry. The Contractor shall provide all necessary resources for this requirement and Project No. I5-10003-2J in accordance with the Statement of Work (SOW), Specification, and terms and conditions of this contract contained.

FOB: Destination

PURCHASE REQUEST NUMBER: 0012129752

PSC CD: Z1AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Each Estimated Cost for War Hazard Losses

FFP

Is Zero (0) FOB: Destination

PSC CD: Z1AZ

NET AMT

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days, including 120 days for procurement of US origin materials after Notice to Proceed (NTP) is issued.

*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-13 System for Award Management Maintenance OCT 2018 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities

DEC 2023

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.204-27 Prohibition on a ByteDance Covered Application JUN 2023 52.229-12 Tax on Certain Foreign Procurements FEB 2021 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

DEC 2018

52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least 51 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

52.244-2 SUBCONTRACTS (JUN 2020)

(a) Definitions. As used in this clause--

Approved purchasing system means a Contractor's purchasing system that has been reviewed and approved in accordance with Part 44 of the Federal Acquisition Regulation (FAR).

Consent to subcontract means the Contracting Officer's written consent for the Contractor to enter into a particular subcontract.

Subcontract means any contract, as defined in FAR Subpart 2.1, entered into by a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.

(b) When this clause is included in a fixed-price type contract, consent to subcontract is required only on unpriced contract actions (including unpriced modifications or unpriced delivery orders), and only if required in accordance with paragraph (c) or (d) of this clause.

(c) If the Contractor does not have an approved purchasing system, consent to subcontract is required for any subcontract that—

(1) Is of the cost-reimbursement, time-and-materials, or labor-hour type; or

(2) Is fixed-price and exceeds—

(i) For a contract awarded by the Department of Defense, the Coast Guard, or the National Aeronautics and Space Administration, the greater of the simplified acquisition threshold, as defined in FAR 2.101 on the date of subcontract award, or 5 percent of the total estimated cost of the contract; or

(ii) For a contract awarded by a civilian agency other than the Coast Guard and the National Aeronautics and Space Administration, either the simplified acquisition threshold, as defined in FAR 2.101 on the date of subcontract award, or 5 percent of the total estimated cost of the contract.

(d) If the Contractor has an approved purchasing system, the Contractor nevertheless shall obtain the Contracting Officer’s written consent before placing the following subcontracts:

None

(e)(1) The Contractor shall notify the Contracting Officer reasonably in advance of placing any subcontract or modification thereof for which consent is required under paragraph (b), (c), or (d) of this clause, including the following information:

(i) A description of the supplies or services to be subcontracted.

(ii) Identification of the type of subcontract to be used.

(iii) Identification of the proposed subcontractor.

(iv) The proposed subcontract price.

(v) The subcontractor’s current, complete, and accurate certified cost or pricing data and Certificate of Current Cost or Pricing Data, if required by other contract provisions.

(vi) The subcontractor’s Disclosure Statement or Certificate relating to Cost Accounting Standards when such data are required by other provisions of this contract.

(vii) A negotiation memorandum reflecting—

(A) The principal elements of the subcontract price negotiations;

(B) The most significant considerations controlling establishment of initial or revised prices;

(C) The reason certified cost or pricing data were or were not required;

(D) The extent, if any, to which the Contractor did not rely on the subcontractor’s certified cost or pricing data in determining the price objective and in negotiating the final price;

(E) The extent to which it was recognized in the negotiation that the subcontractor’s certified cost or pricing data were not accurate, complete, or current; the action taken by the Contractor and the subcontractor; and the effect of any such defective data on the total price negotiated;

(F) The reasons for any significant difference between the Contractor’s price objective and the price negotiated; and

(G) A complete explanation of the incentive fee or profit plan when incentives are used. The explanation shall identify each critical performance element, management decisions used to quantify each incentive element, reasons for the incentives, and a summary of all trade-off possibilities considered.

(2) The Contractor is not required to notify the Contracting Officer in advance of entering into any subcontract for which consent is not required under paragraph (c), (d), or (e) of this clause.

(f) Unless the consent or approval specifically provides otherwise, neither consent by the Contracting Officer to any subcontract nor approval of the Contractor’s purchasing system shall constitute a determination—

(1) Of the acceptability of any subcontract terms or conditions;

(2) Of the allowability of any cost under this contract; or

(3) To relieve the Contractor of any responsibility for performing this contract.

(g) No subcontract or modification thereof placed under this contract shall provide for payment on a cost-plus-a-percentage-of-cost basis, and any fee payable under cost-reimbursement type subcontracts shall not exceed the fee limitations in FAR 15.404-4(c)(4)(i).

(h) The Contractor shall give the Contracting Officer immediate written notice of any action or suit filed and prompt notice of any claim made against the Contractor by any subcontractor or vendor that, in the opinion of the Contractor, may result in litigation related in any way to this contract, with respect to which the Contractor may be entitled to reimbursement from the Government.

(i) The Government reserves the right to review the Contractor’s purchasing system as set forth in FAR Subpart 44.3.

(j) Paragraphs (c) and (e) of this clause do not apply to the following subcontracts, which were evaluated during negotiations:

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

2-in-1 (Construction)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC _W56GBU_

Issue By DoDAAC _W90VN9_

Admin DoDAAC** _W90VN9_

Inspect By DoDAAC _WT4KB6_

Ship To Code _N/A_

Ship From Code _N/A_

Mark For Code _N/A_

Service Approver (DoDAAC) _WT4KB6_

Service Acceptor (DoDAAC) _WT4KB6_

Accept at Other DoDAAC _N/A_

LPO DoDAAC _N/A_

DCAA Auditor DoDAAC _N/A_

Other DoDAAC(s) _N/A_

(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert “See Schedule” or “Not applicable.”)

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.

Mr. Yim, Tae Hyon at (315) 763-4815 or taehyon.yim.ln@army.mil

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

5152.229-4012 TAX EXEMPTION CUSTOMS, REPUBLIC OF KOREA

Pursuant to Article IX of the Status of Forces Agreement between the Republic of Korea and the United States of America, the United States and its contractors are exempt from Republic of Korea customs duties and other related charges. By submission of its offer or quote, the Contractor certifies that the price for all material, supplies, and equipment to be imported for the performance of this contract do not include any otherwise applicable customs duties. To obtain an exemption or reimbursement for customs duties paid pursuant to performance of the contract, the contractor must provide the Contracting Officer with the total amount of customs duties that have been excluded from the contract price. The Contracting Officer will return USFK Form 75 to the contractor for filing with the Republic of Korea Customs Office at the time of import declaration or later if the customs duties were paid before award of the contract.

5152.229-4013 TAX EXEMPTION SPECIAL EXERCISE TAX, REPUBLIC OF KOREA

This clause is in implementation of Article XVI of the Status of Forces Agreement between the Republic of Korea and the United States, granting Contractors exemption from Republic of Korea Special Excise Taxes. At the time this contract is awarded the Contractor shall indicate to the Contracting Officer which items will be purchased for the contract that are subject to Special Excise Tax. It shall indicate the name of the item, the number of units to be purchased, the cost per unit without tax, the percentage of tax, the tax amount per unit, the total tax, and the manufacturer of the item. The Contracting Officer will verify the reasonableness of the quantities claimed and ensure that the Contractor has certified that the contract price excludes Special Excise Tax on those items subject to the tax. The Contractor shall purchase the special-excise-taxed items from the manufacturer, tax-inclusive. For construction and single-delivery type supply and service contracts, the Contractor shall employ the following procedure: At the time it purchases the items it shall present the manufacturer with a notification letter requesting refund of the Special Excise Tax. (Copies of this letter can be obtained from the 411th CSB, Korea Contracting Officer.) The manufacturer will endorse the letter to the manufacturer's District Tax Office which will make refund to the manufacturer. The manufacturer will make subsequent refund to the Contractor. Requests for refund under requirements-type contracts will be submitted monthly and will be accompanied by copies of the USFK delivery orders issue

5152.229-4014 TAX EXEMPTION VALUE ADDED TAX (VAT), REPUBLIC OF KOREA

This clause implements Article XVI of the Status of Forces Agreement between the Republic of Korea and the United States of America, which exempts contractors from paying the Republic of Korea Value-Added Taxes.

When the contractor submits an offer, it shall certify to the Contracting Officer that all the costs in the offer will be exclusive of any Value-Added Tax; and further, that the proposed contract price includes no Value-Added Tax. The contractor shall also indicate the amount and type of Value-Added Taxes excluded from the contract price. If supplies and/or services which the contractor purchases for this contract include Value-Added Taxes, it can obtain a full refund for the amount of the Value-Added Tax by submitting to the ROK District Tax Office tax invoices which the contractor receives when it purchases materials and/or services for this contract. The contractor must submit a copy of the USFK contract with its first tax invoice submission. Subsequent tax invoice submissions must be accompanied by a letter which references the USFK contract submitted with the first tax invoice submission.

5152.229-4015 – Tax Exemption POL Products, Republic of Korea

As prescribed in 29.402-1.d, insert the following clause:

TAX EXEMPTION Petroleum, Oil and Lubricant (POL) PRODUCTS, REPUBLIC OF KOREA

(a) This clause is an implementation of Article XVI of the Status of Forces Agreement (SOFA) between the Republic of Korea and the United States of America, granting Contractors exemption from Republic of Korea taxes for petroleum products (POL) utilized on USFK acquisitions in the Republic of Korea.

(b) At the time this contract is awarded, the Contractor shall make a final nomination in writing of its point of purchase for POL products to be used on this contract. The Contractor shall also state the estimated quantity and amount of POL to be purchased from each refinery/gas station. The USFK Contracting Officer will verify the amounts claimed for use on the contract and, based on this verification, the USFK Issuing Officer will issue USFK POL Tax Exemption Coupons.

(c) If the Contractor elects to purchase directly from an oil company refinery, it may nominate any of the three ROK oil companies below which have agreed to sell to Contractor at a fixed exempt price. Pre-selected oil company refineries will sell their POL products at the fixed exempted prices upon presentation of coupons by the contractor.

List of Oil Companies and their Respective Tax Offices

Hyundai Oil Refinery Co., Ltd.: Seo San District Tax ATTN: POL Tax Administrator Seo San City, Korea

SK Energy: Ulsan District Tax Office S-Oil ATTN: POL Tax Administrator Ulsan City, Kyongsang Nam Do, Korea

GS Caltex: Yosu District Tax Office ATTN: POL Tax Administrator Yosu City, Chonla Nam Do, Korea

(d) If the contractor elects to purchase POL products from an individual gasoline station, the Contracting Officer will advise the contractor as to which stations will sell at the fixed exempt price. The contractor shall specify from which of those stations it will purchase and will be required to make advance payment for the amount of POL covered by the coupons. Advance payment will be at the fixed-exempt price and will be made to the station previously nominated. Representatives from the chosen gas station shall be present at the issuing session to collect the advance payment, mark “paid” on the back of the original copy of the issued coupons, and provide the Contractor with tax invoices by which to obtain a refund from the governing ROK District Tax Office. Having collected POL payment in advance, the gas station will accept pre-paid USFK POL Tax Exemption Coupons from the contractor and provide the POL amount reflected on tendered coupons without further charge.

(e) All coupons for construction contracts shall be issued at the time of award. Coupons for requirements-type contracts shall be issued on a delivery order incremental basis or on a monthly basis.

Section J - List of Documents, Exhibits and Other Attachments

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Drawing

TECHNICAL INFORMATION

TECHNICAL DETAIL SPECIFICATIONS

PROJECT NO TITLE LOCATION

I5-10003-2J Replace the Metal Shed at Bldg. #1420 Camp Henry

GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications are Acrobat® PDF format and can be read with the Acrobat Reader® software.

APPENDIX "A"

LIST OF APPLICABLE CONTRACT DRAWINGS

PROJECT NO TITLE LOCATION

I5-10003-2J Replace the Metal Shed at Bldg. #1420 Camp Henry

GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.

Drawing No. Ref. No. Sheet No. Description Date

D1 1 of 11 Location plan & General note N/A

D2 2 of 11 Existing and removal plan

D3 3 of 11 Construction plan

D4 4 of 11 Roof elevation plan – Area 1

D5 5 of 11 Roof floor plan – Area 1

D6 6 of 11 Roof elevation plan – Area 2-1

D7 7 of 11 Roof elevation plan – Area 2-2

D8 8 of 11 Roof elevation plan – Area 2-3

D9 9 of 11 Roof floor plan – Area 2

D10 10 of 11 Lighting plan

D11 11 of 11 Guard post detail

Section K - Representations, Certifications and Other Statements of Offerors

ATTACHMENT: CONTRACTOR’S TAX EXEMPTION DECLARATION

(1) References:

(i) Contract clause, "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."

(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.

(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.

(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.

(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

This item will be imported specifically for this contract? Yes _________ No ________

(ii) Special Excise Tax:

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

Name of item manufacturer

(iii) Value Added Tax (VAT):

Input VAT on materials purchased for this contract. _________ Input VAT on transportation leased/rented for this contract. _________ Input VAT on equipment leased/rented for this contract. _________ Input VAT on services purchased for this contract. _________ Output VAT on total contract amount. _________

(iv) Special Excise (Petroleum) Tax:

No. of Unit Price Total Tax Liters w/o Tax Tax/Unit Amount

Regular Gasoline __________ (L) ₩_________ ₩________ ₩_________

Premium Gasoline __________ (L) ₩_________ ₩________ ₩_________

Diesel __________ (L) ₩_________ ₩________ ₩_________

Other __________ (L) ₩_________ ₩________ ₩_________

(3) Name of Oil Company Refinery from which POL products will be purchased:

Oil Company: _________________________________________ (Name only)

(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except for ROK MND-funded contracts and delivery orders), and Special Excise Tax.

Contractor’s Signature

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --

(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or

(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

(End of Provision)

52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO

SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services-- Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Products and Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.

(a) Definitions. As used in this provision-

Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Prohibition.

(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.

115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--

(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.

115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to--

(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services."

(d) Representations. The Offeror represents that--

(1) It [ ___ ] will, [ ___ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this section; and

(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that--

It [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.

(e) Disclosures.

(1) Disclosure for the representation in paragraph (d)(1) of this provision. If the Offeror has responded "will" in the representation in paragraph (d)(1) of this provision, the Offeror shall provide the following information as part of the offer:

(i) For covered equipment--

(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known);

(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and

(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.

(ii) For covered services--

(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or

(B) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.

(2) Disclosure for the representation in paragraph (d)(2) of this provision. If the Offeror has responded "does" in the representation in paragraph (d)(2) of this provision, the Offeror shall provide the following information as part of the offer:

(i) For covered equipment--

(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);

(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and

(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.

(ii) For covered services--

(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or

(B) If not associated with maintenance, the PSC of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.

(End of provision)

52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT

2020)

(a) Definitions. As used in this provision, “covered telecommunications equipment or services” and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.

(c) Representations.

(1) The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.

(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.

Section L - Instructions, Conditions and Notices to Bidders

INSTRUCTIONS TO OFFEROR

1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:

a. Site Visit: Offerors who intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit Clause FAR 52.236-27. Offerors are required to have a valid Korean Identification card when attending the site visit orientation.

b. Offeror(s) are cautioned to follow the detailed instructions fully and carefully, as the Government reserves the right to make award based on initial offers received, without discussions of such offers.

c. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted. The proposal is intended to be evaluated, and award made, without discussions with the offerors unless discussions are determined to be necessary. If the Government conducts discussions, the Government shall conduct discussions with all offerors in accordance with FAR 15.306, Exchanges with offerors after receipt of proposals.

2. SUBMISSION DOCUMENT: Offers shall be via email to hyeyong.chong1.ln@army.mil by the due time and date specified in block 13.A. of this solicitation. All questions are due No Later than 13:00 hours (01:00PM) Local Time, three (3) work days after the site visit date specified in Provision FAR 52.236-27 within this solicitation.

a. PRICING PROPOSAL: The pricing proposal shall include the following:

(1) Offer Breakdown: Offerors shall submit an offer breakdown that identifies Materials, Labor, and Transportation and Equipment (T&E), and other resources upon which the offeror intends to rely to perform this contract in accordance with the Statement of Work. The offer breakdown must demonstrate that the offeror understands the requirement in the RFP by listing an appropriate amount of materials, labor, and transportation and equipment required to perform the contract in accordance with the Statement of Work and drawings. The Offeror’s proposal must contain all contractor’s costs including mobilization, demobilization, overhead, profit, insurance, design fee and all other costs including but not limited to compliance with environmental laws, tax laws, protection or moving of Government property, engineering services (to include survey work and drawings) and waste disposal inherent to accomplish the work request. No allowance will be made later for any other purpose whatsoever unless specifically allowed elsewhere in the contract. Offeror shall provide one (1) original offer breakdown with price and one (1) copy of the offer breakdown without price in accordance to the provided template below:

(a) Materials:

(I) Local Materials:

(A) Type of material with item description, capacity or model number;

(B) Quantity

(II) U.S. Origin Materials:

(A) Type of material with item description, capacity or model number;

(b) Quantity Labor:

(I) Category of labor;

(II) Quantity (man-days in each category);

(c) Transportation and Equipment:

(I) Description of all transportation and equipment (category and capacity);

(II) Quantity (per trip or equipment-day);

(d) Other Critical Resource(s): Must be fully described.

(2) Section K (ATTACHMENT: CONTRACTOR’S TAX EXEMPTION DECLARATION): Offerors must complete all portions of Section K. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, any proposed exemption of a specific ROK tax shall be legitimate, attributable to the contract, and authorized by the applicable stated references.

Failure to submit the above requirements may be grounds for determining the proposal to be non-responsive and not eligible to be considered for award.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Time & Date: 09:00 AM, 29 May 2024

Technical POC: Mr. Chu, Kwang Chung at 0503-363-4833 Email; kwangchung.chu.ln@army.mil Location: In front of Bldg. #1420, Camp Henry

Section M - Evaluation Factors for Award

BASIS OF AWARD

1. BASIS OF AWARD: An award shall be made on the basis of the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost factors that satisfy all terms and conditions of this solicitation.

Proposals will be evaluated for acceptability

2. EVALUATION CRITERIA

a. COST FACTOR: The proposal shall be evaluated to determine whether it is complete and reasonable. A complete and reasonable pricing proposal will be deemed acceptable.

b. NON-COST FACTOR: The proposal shall be evaluated to determine the offeror’s ability to satisfactorily accomplish the Government’s intent and achieves the desired quality end-products. A complete proposal which indicates an adequate understanding and approach of the requirements will be deemed acceptable.

Rating Adjective Definitions Technically Acceptable

Proposal meets requirements and indicates an adequate understanding and approach of the requirements.

Technically Unacceptable

Proposal does not meet requirements and contains one or more deficiencies. Proposal is un-awardable.

Failure to submit the required documents identified in Section L: Instructions to Offeror may be grounds for determining the proposal to be non-responsive and not eligible to be considered for award.