This document is an amendment to Solicitation W90VN924R0078 for the repair of Buildings 1910 and 1911 (Ammo Depot #2) in Young Cheon. The primary changes are an extension of the solicitation due date from May 26, 2024 to May 28, 2024, and revisions to the Statement of Work for architectural, electrical, and civil work on the two buildings. The work includes replacing flooring, walls, ceilings, doors, windows, lighting, HVAC, and exterior elements. The performance period is 180 calendar days, including 120 days for procurement of U.S. origin materials. Contractor shall provide all labor, materials, tools, and equipment necessary to complete the scope of work. This is a non-work plan task order under a MATOC contract, only open to contractors in Area IV. The government will hold a site orientation on April 19, 2024 at 10:00 AM at the project location.

View the file

Other files

File Type Posted
SolicitationW90VN924R0078-0001.pdf PDF
SolicitationW90VN924R0078.pdf PDF
Attachment 1-K9-00001-3J Drawing.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0012111730 K9-00001-3J

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

A. The purpose of this amendment is as follow ing:

a. To extend the solicitation due date from 01:00 PM, 26 May 2024 to 01:00 PM, 28 May 2024.

b. To change specif ications of multiple items in the sections listed below in the Statement of Work.

i. B. Architectural Work (B1910)

ii. C. Electrical Work (B1910)

iii. E. Architectural Work (B1911)

iv. F. Electrical Work (B1911)

B. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W90VN924R0078

X 9B. DATED (SEE ITEM 11)

15-Apr-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-May-2024

CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO DAEGU, UNIT #15682

APO AP 96218-5682

UNITED STATES

W90VN9 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W90VN924R0078

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been added by full text:

AMENDMENT 0002 - REVISED SOW

STATEMENT OF WORK

FOR

REPAIR B1910 & B1911 (AMMO DEPOT #2),

YOUNG CHEON

PROJECT NO. K9-00001-3J

TECHNICAL PROVISIONS - I

GENERAL DESCRIPTION OF WORK TO BE COMPLETED

PROJECT NO TITLE LOCATION

K9-00001-3J REPAIR B1910 & B1911 (AMMO DEPOT #2) YOUNG CHEON

DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.

a. Work by Contractor:

1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary accomplish the scope of work contained herein as indicated in the drawings and specifications.

2) The contractor shall repair B1910 & B1911(AMMO DEPOT #2), YOUNG CHEON in accordance with the specifications and drawings.

3) Performance Period: Shall be 180 calendar days, including 120 days for procurement of US origin materials after Notice to Proceed (NTP) is issued.

b. Work by In-House Labor: Not applicable to this project.

c. Work by Troop Labor: Not applicable to this project.

PRINCIPAL FEATURES: This project shall include the following:

General Services:

The contractor shall submit completed material lists and shop drawings to DPW, Engineering Division, Design and Technical Review Branch through the COR.

Schedule #I, Replace/Repair (K): All work shall be in accordance with the attached drawings and specifications.

A. Civil Work (B1910)

1. The contractor shall install and remove 63LM temporary EGI fence around B1910.

2. The contractor shall install a concrete pad (600mm W x 1200mm L x 150mm thk) for heat pump condensing unit in front of B1910 in accordance with attached drawing #3/11.

B. Architectural Work (B1910)

3. The contractor shall replace vinyl composition tile (DECO Tile, 450mm x 450mm x 3mm thick) at main office and leader’s office in accordance with attached drawing #3/11.

4. The contractor shall replace wall board (15mm thick gypsum board incl. joint taping & compound, regular type), metal stud/runner (100 mm wide, at 400 mm O.C) for wall, wood base board (100mm high x 25mm thick), insulation with aluminum foil jacket (100mm thick) in main office and leader’s office in accordance with attached drawing #3/11.

5. The contractor shall replace suspended ceiling system (UL Listed), acoustical ceiling tiles (15mm thick) and 200mm thk. insulation in main office and leader’s office in accordance with attached drawing #3/11.

6. The contractor shall replace 6ea aluminum sliding windows & aluminum frames (0.98 W x 0.98 L), minimum AT/FP blast windows (9.52mm clear laminated glass + 12mm air space + 6mm tinted low-e tempered glass) incl. insect screens & window latch at main office and leader’s office in accordance with attached drawing #3/11.

7. The contractor shall replace 6ea horizontal blinds (0.96 W x 0.98 L) at main office and leader’s office in accordance with attached drawing #3/11.

8. The contractor shall replace 6ea window security bars (1.20 W x 1.20 L) at main office and leader’s office in accordance with attached drawing #3/11.

9. The contractor shall replace a steel flush single door incl. steel door frame (900mm x 2,150mm, 45mm thick), hinge butts 4-1/2" x 4-1/2" A8111, kick plate J102, aluminum weather strip (Door sweep, ANSI/BHMA.R5G165 type, UL Listed), door lockset (mortise lockset, F-08, UL Listed), door closer (C02021 or C02011, UL Listed), door stopper with hook, aluminum threshold (150mm W x 1000mm L, UL Listed) in main office entrance door in accordance with attached drawing #3/11.

10. The contractor shall replace a wood flush solid core single door (UL Listed) incl. steel door frame (900mm x 2,150mm, 45mm thick), hinge butts (4-1/2" x 4-1/2" A8111), kick plates, door holder L01361, L01371, L02141, L01381, L02121, L01241 & etc, bored type lockset F-82 (UL Listed), door closer (UL Listed) and aluminum threshold 150mm W x 1000mm L (UL Listed) for locker room door in accordance with attached drawing #3/11.

11. The contractor shall install caulking for painting area (included doors, windows, base board, wall, ceiling, etc.) at main office and leader’s office in accordance with attached drawing #3/11.

12. The contractor shall paint 2 coats on entire interior wall with doors/frames, base board, etc. at main office and leader’s office in accordance with attached drawing #3/11.

13. The contractor shall remove and reinstall various furniture incl. 2ea refrigerators, 6ea steel or wooden cabinets, 4ea desks, 6ea shelves, 5ea bookcases, 4ea chairs, 1ea microwave oven, 1ea table, etc. at main office and leader’s office in accordance with attached drawing #3/11.

14. The contractor shall install & remove plastic sheets outdoors to cover various pieces of furniture in accordance with attached drawing #3/11.

15. The contractor shall repair an existing 25mm dia. steel pillar of concrete canopy above the entrance door at B1910 in accordance with attached drawing #4/11.

16. The contractor shall replace wood soffit board (trim & nailed with 12mm thick plywood), wood fascia board & nailed (250mm high x 25mm) at B1910 in accordance with attached drawing #4/11.

17. The contractor shall replace sheet metal rain gutter (#24 gauge, 150mm wide), 6ea basket strainers, sheet metal downspout & strap and hanger incl. painting at B1910 in accordance with attached drawing #4/11.

18. The contractor shall replace galvanized sheet metal flashing (#24 gauge) incl. painting for fascia board at B1910 in accordance with attached drawing #4/11.

19. The contractor shall paint 2 coats on entire exterior wall, wood soffit board, wood soffit board, etc. at B1910 in accordance with attached drawing #4/11.

C. Electrical Work (B1910)

20. The contractor shall replace 3ea 2'x4' LED lighting fixtures (Recessed type, UL Listed), toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate, UL Listed), power line and conduits at main office in accordance with attached drawing #5/11.

21. The contractor shall replace 1ea 2'x4' LED lighting fixture (EM battery pack type, Recessed type, UL Listed), toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate, UL Listed), power line and conduits at main office in accordance with attached drawing #5/11.

22. The contractor shall replace 1ea 1'x4' LED lighting fixture (Recessed type, UL Listed), toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate, UL Listed), power line and conduits at leader’s office in accordance with attached drawing #5/11.

23. The contractor shall install 1ea 1'x4' LED lighting fixture with EM battery pack (Recessed type, UL Listed), power line and conduits at leader’s office in accordance with attached drawing #5/11.

24. The contractor shall install 1ea EXIT sign (LED type, 120/277V, aluminum housing material, single type, w/battery charger, UL Listed), power line and conduits in main office in accordance with attached drawing #5/11.

25. The contractor shall replace a LED exterior lighting fixture (exterior wall, wall packs weatherproof type, 100 Watt, 120V, UL Listed), toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate, UL Listed), power line and conduits at above the main entrance door in accordance with attached drawing #5/11.

26. The contractor shall remove an existing safety switch (3P-30A) with power line and conduits for heat pump unit at main office in accordance with attached drawing #6/11.

27. The contractor shall install a safety switch (3P-30A, fusible type, UL Listed), power line and conduits at main office in accordance with attached drawing #6/11.

28. The contractor shall replace 9ea outlets (110V-6ea, 220V-3ea, UL Listed), power line and conduits at main office and leader’s office in accordance with attached drawing #6/11.

29. The contractor shall install 2ea outlets (220V), power line and conduits at main office in accordance with attached drawing #6/11.

TP I-3

30. The contractor shall install 4ea electric conduits (22mm dia.), 4ea Jacks (2 port, CAT6 RJ-45, UL Listed) and 4ea LAN cables (The LAN cable is provided by the user) at main office in accordance with attached drawing #6/11.

31. The contractor shall replace a heat pump unit 23 pyong, 220V, 60Hz, Heating capacity: 9,300W/49.7m2, Cooling capacity: 8,300W/75.5m2, Power consuming: 2.80 kw, Freon gas type: R410A (UL Listed), power line and conduits at main office in accordance with attached drawing #6/11.

D. Civil Work (B1911)

32. The contractor shall install and remove temporary EGI fence around B1911.

33. The contractor shall install 2ea concrete pads (600mm W x 1200mm L x 150mm thk) for condensing units of heat pump units at the back of B1911 in accordance with attached drawing #7/11.

34. The contractor shall replace existing concrete pavement (900mm W x 285mm thk) from near B1913 to B1911 to install the water line in accordance with attached drawing #11/11.

35. The contractor shall excavate a trench (900mm W x 1000mm Deep) from near B1913 from B1911 in accordance with attached drawing #11/11.

36. The contractor shall install stainless steel water pipe (16mm dia.) with 50mm thk. pipe insulation from near B1913 from B1911 and connect to existing water purifier at B1911 in accordance with attached drawing #11/11.

37. The contractor shall Install concrete encasement (330mm W x 330mm H) from near B1913 from B1911 for 16mm water pipe in accordance with attached drawing #11/11.

E. Architectural Work (B1911)

38. The contractor shall remove existing raised (500mm high) wood/soil/concrete floor, wall board, metal stud/runner, insulation, base board, ceiling system and insulation at locker room in accordance with attached drawing #7/11.

39. The contractor shall remove existing floor tiles, wall board, metal stud/runner, insulation, base board, ceiling system and insulation at main office in accordance with attached drawing #7/11.

40. The contractor shall install concrete floor slab (100 mm thk) with 2-ply wire mesh (WWF #8-150 x 150) at locker room and main office in accordance with attached drawing #7/11.

41. The contractor shall install vinyl composition tile (DECO Tile, 450mm x 450mm x 3mm thick) at locker room and main office in accordance with attached drawing #7/11.

42. The contractor shall install wall board (15mm thick gypsum board incl. joint taping & compound, regular type), metal stud/runner (100 mm wide, at 400 mm O.C) for wall, metal casing bead, wood base board (100mm high x 25mm), insulation with aluminum foil jacket (100mm thick) in locker room and main office in accordance with attached drawing #7/11.

43. The contractor shall install suspended ceiling system (Floor-to-ceiling height is 8 FT, UL Listed), 15mm thick acoustical ceiling tiles and 200mm thk. insulation in locker room and main office in accordance with attached drawing #7/11.

44. The contractor shall replace 7ea aluminum sliding windows & aluminum frames (0.98 W x 0.98 L), minimum AT/FP blast windows (9.52mm clear laminated glass + 12mm air space + 6mm tinted low-e tempered glass) incl. insect screens & window latch in locker room and main office in accordance with attached drawing #7/11.

45. The contractor shall replace 7ea horizontal blinds (0.98 W x 0.98 L) in locker room and main office in accordance with attached drawing #7/11.

46. The contractor shall replace 7ea window security bars (1.20 W x 1.20 L) in locker room and main office in accordance with attached drawing #7/11.

47. The contractor shall replace a steel flush single door with steel door frame (900mm x 2,150mm, 45mm thick), hinge butts 4-1/2" x 4-1/2" A8111, kick plate, aluminum weather strip (Door sweep, ANSI/BHMA.R5G165 type, UL Listed), door lockset (mortise lockset, F-08, UL Listed), door closer (UL Listed), door stopper with hook, aluminum threshold (150mm W x 1000mm L, UL Listed) in main office entrance door in accordance with attached drawing #7/11.

48. The contractor shall replace a wood flush solid core single door (UL Listed) with steel door frame (900mm x 2,150mm, 45mm thick), hinge butts 4-1/2" x 4-1/2" A8111, kick plates, door holder and bored type lockset F-82 (UL Listed) and aluminum threshold (150mm W x 1000mm L, UL Listed) in locker room entrance door in accordance with attached drawing #7/11.

49. The contractor shall install caulking for painting area (included doors, windows, base board, wall, ceiling, etc.) in locker room and main office in accordance with attached drawing #7/11.

50. The contractor shall remove and reinstall various furniture incl. 2ea refrigerators, 6ea steel or wooden cabinets, 8ea desks, 6ea shelves, 5ea bookcases, 10ea chairs, 1ea microwave oven, 1ea table, etc. at main office and leader’s office in accordance with attached drawing #7/11.

51. The contractor shall install & remove plastic sheets outdoors to cover various pieces of furniture in accordance with attached drawing #7/11.

52. The contractor shall paint 2 coats on entire interior wall with doors/frames, base board and etc in locker room and main office in accordance with attached drawing #7/11.

53. The contractor shall replace wood soffit board (trim & nailed with 12mm thick plywood), wood fascia board & nailed (250mm high x 25mm) at B1911 in accordance with attached drawing #8/11.

54. The contractor shall replace sheet metal rain gutters (#24 gauge, 150mm wide), 6ea basket strainers, sheet metal downspouts & strap and hanger incl. painting at B1911 in accordance with attached drawing #8/11.

55. The contractor shall replace galvanized sheet metal flashing (#24 gauge) incl. painting for fascia board at B1911 in accordance with attached drawing #8/11.

56. The contractor shall replace 2 SM asphalt shingle roof canopy above main entrance door at B1911 in accordance with attached drawing #8/11.

57. The contractor shall paint 2 coats on entire exterior wall, wood soffit board, wood soffit board, etc. at B1911 in accordance with attached drawing #8/11.

F. Electrical Work (B1911)

58. The contractor shall replace 3ea 1'x4' LED lighting fixture (Recessed type, UL Listed), toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate, UL Listed), power line and conduits at locker room in accordance with attached drawing #9/11.

59. The contractor shall replace 1ea 1'x4' LED lighting fixture (EM battery pack type, Recessed type, UL Listed), toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate, UL Listed), power line and conduits at locker room in accordance with attached drawing #9/11.

60. The contractor shall replace 6ea 1'x4' LED lighting fixture (Recessed type, UL Listed) and toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate, UL Listed), power line and conduits at main office in accordance with attached drawing #9/11.

61. The contractor shall replace 4ea 1'x4' LED lighting fixture (EM battery pack type, Recessed type, UL Listed), toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate, UL Listed), power line and conduits at main office in accordance with attached drawing #9/11.

62. The contractor shall install 2ea EXIT signs (LED type, 120/277V, aluminum housing material, single type, w/battery charger, UL Listed), power line and conduits at main office in accordance with attached drawing #9/11.

63. The contractor shall replace a LED exterior lighting fixture (exterior wall, wall packs weatherproof type, 100 Watt, 120V, UL Listed), toggle switch (Flush mounted, 1P-20A-120/277VAC, w/cover plate), power line and conduits at above the main entrance door in accordance with attached drawing #9/11.

64. The contractor shall extend power line (3-#10 in 16mm C) w/conduits from existing outlet (220V) to new safety switch for heat pump at locker room in accordance with attached drawing #10/11.

65. The contractor shall install an outlet (220V) with power line and conduits for water purifier in main office in accordance with attached drawing #10/11.

66. The contractor shall install 2ea safety switches (3P-30A, fusible type, UL Listed) w/power line (3-#10 in 16mm C) in locker room and main office in accordance with attached drawing #10/11.

67. The contractor shall install 8ea electric conduits (22mm dia) with 8ea LAN outlets (Dual modular type, CAT6 RJ-45 W/wall plate 2 port, UL Listed) and LAN cables (The LAN cable is provided by the user) in main office in accordance with attached drawing #10/11.

68. The contractor shall replace 11ea outlets (110V, UL Listed), 3ea outlets (220V), power line and conduits in locker room and main office in accordance with attached drawing #10/11.

69. The contractor shall relocate an existing heat pump unit (23 pyong), power lines and conduits located in main office to locker room.in accordance with attached drawing #10/11.

70. The contractor shall install a heat pump unit, 23 pyong, 220V, 60Hz, heating capacity: 9,300W/49.7m2, cooling capacity: 8,300W/75.5m2, power consuming: 2.80 kw, freon gas type: R410A (UL Listed), power line and conduits in accordance with attached drawing #10/11

G. Safety

1. The contractor shall assign safety guard around working area.

H. Construction Debris

1. The contractor shall remove and dispose construction debris to outside compound in accordance with local laws and regulations.

I. General Work

1. The COR shall coordinate work performance schedule between the contractor and using agency and phase work might be required to be coordinated with using agency.

2. The contractor should coordinate any salvageable and recyclable materials within project limit with COR carefully to determine proper material handing methods.

3. The contractor shall perform painting works in accordance with the O&MA regulations.

4. The contractor shall install and remove the scaffolding (single and double) with temporary stair or slope and other scaffolding accessories for this project.

TECHNICAL PROVISIONS - II

TECHNICAL DETAIL SPECIFICATIONS

PROJECT NO TITLE LOCATION

K9-00001-3J REPAIR B1910 & B1911 (AMMO DEPOT #2) YOUNG CHEON

GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications are Acrobat® PDF format and can be read with the Acrobat Reader® software.

TECHNICAL PROVISIONS - III

SPECIAL CONDITIONS

PROJECT NO TITLE LOCATION

K9-00001-3J REPAIR B1910 & B1911 (AMMO DEPOT #2) YOUNG CHEON

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which is incorporated in-to the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through Saturday) except for Korean Legal Holidays. Any proposed change in working hours must be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). Please note that there will be an exception for night shift when working on the fire alarm system.

3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days’ notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed by the Government to require inspection.

4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.

5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten (10) working days prior to the starting of work. The request shall be submitted to the COR for approval.

6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.

7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, and other equipment necessary for proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, and any other items, as required by law.

8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the COR.

Equipment not completely safe or functional shall be repaired and accepted by the government before work is initiated.

9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings any changes in such work which constitute any change from the original contract drawings per government’s approval. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.

10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after Notice to Proceed dependent on Government’s direction if such material is not yet determined.

11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.

12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.

13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting Officer approval. Make request fourteen (14) calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, associated level of work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.

14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor additional cost. These additional incurred costs are contractor’s responsibility. The Contractor shall reflect these costs in the preparation of their proposal.

15. SAFETY: The safety plan must be approved before any work can be performed on this contract. Hard hats, suitable work boots and other necessary personnel protective gear per safety regulations are mandatory. Contractors are required to get a written permission from safety office and Fire and Emergency Service prior to entering confined spaces (i.e., manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.

16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the Base Security Office. It is the prime contractor’s responsibility to provide information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.

17. WARRANTY: The contractor shall be responsible for resolution on any defect/ failure on the contract during the one (1) year warranty period. The contractor shall provide services or/and repair and replacement to the satisfaction of the government. The one (1) year warranty starts the day after final inspection approval from the authorized government personnel.

18. ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.

18.1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

18.2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area.

Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

18.3. For contractors that do not require CAC but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

18.4. iWATCH TRAINING. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility, or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

19. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;

Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;

Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;

Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;

20. CONTAMINATION FIND CLAUSE: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.

21. INADVERDENT FIND CLAUSE: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch.

12, Para 12-3 J)

22. FUEL TANK AND LINES: If applicable, underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 9, Para 9-3.b. (5))

23. Non-PCB TRANSFORMER CERTIFICATION: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB (Polychlorinated Biphenyl) transformer certification to COR for each installed transformer. New transformer will be installed after COR's approval for non-PCB transformer certification for each to be installed transformer.

24. DUST REDUCTION REQUIREMENTS: Contractor shall perform the works in accordance with the USFK Regulation 201-1, Table 2-7.

25. HAZARDOUS MATERIAL HAZARDOUS WASTE: All hazardous material and hazardous waste used/created during the project must be stored in accordance with the Code Of Regulation 1910 Subpart H and USFK Reg 201-1, Environmental Governing Standard (EGS) Chapter 5 and Chapter 6.

TECHNICAL EXHIBIT I: DELIVERABLE SCHEDULE

DELIVERABLE FREQUENCY FORMAT

OF

COPIES

SUBMIT TO

Final Project Schedule

Within 30 calendar days after NTP Electronic copy.

COR

Preconstruction Submittals

Within 15 days after NTP Electronic copy.

COR

Quality control plan (QCP)

Within 15 days after NTP Electronic copy.

COR

Safety Plan Para. TPIII. 15

Within 15 days after NTP Electronic copy.

COR

Construction permission Para. TPIII. 5

10 working days prior to the starting of work

Electronic copy.

COR

Notification of need for inspection Para. TPIII. 3

7 working days prior to any work deemed by the Government to require inspection

Electronic copy.

COR

DD Form 1354, Transfer and acceptance of DoD real property

Prior to final inspection Electronic copy.

COR

As-built drawings Para. TPIII. 9

Prior to final inspection Electronic copy.

COR

AT Level I Training Certificate Para. TPIII.

18.1

NLT 30 calendar days after contract award

All Training Certificates

COR

iWATCH Training Certificate Para. TPIII.

18.4

NLT 30 calendar days after contract award

All Training Certificates

COR

(End of Summary of Changes)