HQCWJ980612465
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Th follow ing items are applicable to this amendment. (SEE SECTION SF 30 BLOCK 14 CONTINUATION PAGE).
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Mar-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W90VN918R0011
X 9B. DATED (SEE ITEM 11)
20-Mar-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Mar-2018
CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCO DAEGU, UNIT #15682
APO AP 96218-5682
UNITED STATES OF AMERICA (THE)
W90VN9 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W90VN918R0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
ANSWER TO VENDOR'S QUESTION
A. The purpose of this amendment is to provide answers for vendor’s questions submitted as shown below:
Question Answer According to PWS 3.3 Replacement Parts, there is NO amount limitation for parts of high valuable parts such as batteries, controllers and etc. which cost exceeding KRW 2,000,000.
Should the contractor replace every high valuable parts by contractor’s cost without any additional cost or those items will be required to use a different contract such as a separate purchase order?
Performance Work Statement (PWS), paragraph 3.3 as described in RFQ remains unchanged.
According to the Sub-factor A- Contractor’s Personnel Qualification:
The Contractor(s) shall provide Electronic License(전자기능사
자격증) and Vehicle Machine Maintenance Technician
Licenses(자동차기관정비기능사 자격증) issued by ROK Government.
In respect of PWS 8: Schedule of Items, those items are classified as heavy equipment. Especially the electric forklift consists of electrical equipment.
We therefore inquire of you whether not only Electronic
License(전자기능사 자격증) but also Electric license(전기기능사
자격증) are acceptable.
And the items are classified as heavy equipment, Construction
Equipment Maintenance Technician Licenses(건설기계정비기능사
자격증) should be qualified as well.
Therefore We are asking if these licenses can be added to Electronic
License(전자기능사 자격증) or also Electric license(전기기능사
자격증) and to Vehicle Machine Maintenance Technician
Licenses(자동차기관정비기능사 자격증) or Construction
Equipment Maintenance Technician Licenses(건설기계정비기능사
자격증) to enhance the range of competitive bids that may be
Technical Evaluation Sub-Factor A and B as required in RFQ remains unchanged.
W90VN918R0011
submitted Do you intend to conduct site visit to let the bidders to check the current equipment status?
Site Visit date/time: 3 April 2018, 14:00 pm Location: In front of Gate 6 at Camp Walker (Daegu city) POC: Mr. Hwang at (010) 8740-
B. All other terms and conditions of the solicitation remain the same.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting: See below.
-Description: MATERIAL HANDLING EQUIPMENTS (MHE), SWEEPERS, SCRUBBERS AND DOORS
AT DEAGU COMMISSARY
- Date / Time: 3 April 2018 / 14;00 hours
- Location: In front of Gate 6 at Camp Walker
- DeCA POC: Mr. Hwang at (010) 8740-0008
NOTE:
1. Any participants who need to be escorted MAY contact POC above a day prior to the date of site visit.
2. The Attendee must bring a photo identification card (Korean ID Card: Ju-min-deng-rok-jung) when attending the site visit orientation.
(End of provision)
(End of Summary of Changes)