Amendment of Solicitation W90VN824R0046_0001.pdf
PDF 655 KB Posted
- Solicitation number
- W90VN824R0046
About this file
This document is an amendment to a solicitation for a federal contract opportunity to repair fire station building No. 277 at Warrior Base, Korea. The work includes architectural, mechanical, electrical, and structural repairs and new construction. The principal features of the work are described in detail, including items such as flooring, walls, ceilings, doors, windows, HVAC, plumbing, sprinklers, and electrical systems. The contract will be awarded to one of the existing General Construction Multiple Award IDIQ contract holders. The amendment incorporates revised drawings and statements of work into the requirement. All other terms and conditions of the solicitation remain the same.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Drawing files 184001 Civil AMENDMENT.pdf | ||
| Solicitation W90VN824R0046.pdf | ||
| 184001_DWG.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
411TH CSB, KOREA - RCO CASEY
POC: MAJ DUVALDADRIAN, ALEXANDER C.
DSN: 315-722-1380
E-MAIL: ALEXANDER.C.DUVALDADRIAN.MIL@ARMY.
APO AP 96205-5289
UNITED STATES
0012101879 184001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
A. The purpose of this amendment is to incorporate the revised draw ing & statement of w ork into this requirement.
B. All other terms and conditions of the solicitation remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 17
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Jun-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W90VN824R0046
X 9B. DATED (SEE ITEM 11)
04-Jun-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Jun-2024
CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCO CASEY
UNIT#15289
APO AP 96224-6224
UNITED STATES
W90VN8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W90VN8
FACILITY CODECODE
EMAIL:TEL:
W90VN824R0046
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
DESCRIPTIONS AND SPECIFICATION
DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, YONGSAN-CASEY
UNIT #15543
APO AP 96224-5543
AMIM-YNP-G 10 June 2024 (Amendment)
SPECIFICATIONS
FOR
PROJECT NO.: 184001
Repair fire station, building No. 277
Warrior Base, Korea
TABLE OF CONTENTS
1. Technical Provisions - I: Statement of Work
2. Technical Provisions - II: Technical Detail Specifications
3. Technical Provisions - III: Special Conditions
4. Appendix "A": List of Applicable Contract Drawings
TECHNICAL PROVISIONS - I
STATEMENT OF WORK
PROJECT NO TITLE LOCATION
184001 Repair fire station, building No. 277 Warrior Base
1. DESCRIPTION: The work to be performed to repair fire station, building No. 277 is described below and executed by one or more of the groups.
1.1. Work by Contractor: The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and in accordance with the specifications.
1.2. Work by In-House Labor: Not applicable to this project.
1.3. Work by Troop Labor: Not applicable to this project.
2. PRINCIPAL FEATURES: This project includes the following principal features:
2.1. Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.
2.1.1. Architectural Work
2.1.1.1. Floor work
2.1.1.1.1. Replace existing floor tile with new Polyvinyl Chloride Tile (PVCT) including Vinyl Cove Base (VCB) as shown on new floor plans and interior finish schedule. The existing concrete flooring shall be smooth, true, level plane with all defects such as rough or scaling concrete, low spots, high spots, painting, and uneven surface shall be corrected for new flooring. Provide leveling concrete for existing concrete slab if needed.
2.1.1.1.2. Replace existing rubber tiles including rubber tile base as shown on floor plans and interior finish schedule.
2.1.1.1.3. Replace existing conc stoops as shown on floor plan, existing/removal plan, floor plan, section, and interior finish schedule.
2.1.1.1.4. Apply hardener and epoxy coating with non-slip grits as shown on floor plan and interior finish schedule.
TP I-1
2.1.1.1.5. Replace existing Ceramic Floor Tile (CFT) with new including cement bond coat, waterproof membrane, and mortar bed as shown on floor plans and detail drawings.
2.1.1.2. Interior and exterior wall work
2.1.1.2.1. Replace existing all Gypsum Wall Board (GWB) wall board walls with new GWB wall (Normal, water resistant or 'X' type) including metal studs as shown on floor plans, sections and detail drawings.
2.1.1.2.2. Paint all interior/exterior wall surfaces including other components (Steel guardrail, guard post, fuel tank, and conc dike) as shown on interior finish schedule, elevations, and sections.
2.1.1.2.3. Replace existing Glazed Ceramic Wall Tile (GCWT) with new including cement bond coats, waterproof membrane, and plastering with metal lath as shown on floor plans and sections.
2.1.1.2.4. Replace existing pipe chases/pipe cover with waterproof or ‘X’ type of GWB for mechanical piping system and duct as per floor plans, sections, and detail drawings.
2.1.1.2.5. Replace/block up existing protected wall siding including insulations with vapor barrier and paint on existing protected metal wall liner as shown on floor plans, elevations, sections and detail drawings.
2.1.1.3. Interior and exterior ceiling and roof work
2.1.1.3.1. Replace existing ceiling with new acoustical ceiling tiles including metal suspension systems as shown on floor plans and interior finish schedule.
2.1.1.3.2. Replace existing ceiling with new GWB (Normal, water resistant or 'X' type) ceiling including ceiling suspension system as shown on floor plans and finish schedule.
2.1.1.3.3. Paint all interior ceiling surfaces as shown on interior finish schedule and sections.
2.1.1.3.4. Replace existing rain gutters and downspouts with new including conc splash blocks as shown on floor plans and elevations.
2.1.1.3.5. Replace existing standing seam metal canopies with new including rain gutter as shown on roof plan, elevation, and detail.
2.1.1.4. Miscellaneous work
2.1.1.4.1. Replace existing doors and door frames with new including hardware sets as shown on new floor plan and door schedule.
2.1.1.4.2. Replace existing windows including insect screen with new aluminum thermal breaker type windows including glass as shown on floor plans, elevations, and window schedule.
2.1.1.4.3. Replace existing window horizontal mini blinds with new, fireproof type.
TP I-2
2.1.1.4.4. Replace existing exterior steel stair with new including guardrail, handrail, and rubber safety corner guards as shown on floor plan, elevation, section, picture, and structure drawings.
2.1.1.4.5. Replace existing aluminum louver with new as shown on floor plans and louver schedule.
2.1.1.4.6. Replace existing Fire Extinguisher Cabinets (FEC) and Fire Extinguisher Brackets (FEB) with new as shown on floor plans and detail drawing.
2.1.1.4.7. Replace existing all toilet accessories and shower benches with new as shown on floor plans and detail drawings.
2.1.1.4.8. Replace interior and exterior signages with new as shown on floor plans, elevations, and signage schedule.
2.1.1.4.9. Replace existing metal shelf with mop rack with new.
2.1.1.4.10. Replace existing roll up doors including manual hand chain and wire remote controller as shown on floor plans and door schedule.
2.1.1.4.11. Replace existing Stainless Steel (SST) laundry shelf as shown on floor plans, elevations, and detail drawing.
2.1.1.4.12. Replace existing access doors on wall and ceiling as required.
2.1.1.4.13. Replace existing counter table as shown on floor plan, elevation, and detail drawing.
2.1.1.4.14. Replace existing kitchenette including base cabinet and upper cabinet as shown on floor plan, elevation, and detail drawings.
2.1.1.4.15. Replace existing bulletin boards as shown on floor plans and detail drawings.
2.1.1.4.16. Block up duct chase hall on concrete slab with concrete including re-bar, metal deck, and support steel structure as shown on floor plan.
2.1.2. Mechanical Work
2.1.2.1. Repair the heating and cooling system with new Variable Refrigerant Flow (VRF) duct-free split heat pump indoor and outdoor units, hot water boiler, hot water circulation pump, electric wall mounted heaters, electric ceiling heater, electric unit heater, unit heaters, air separator, expansion tank, air compressor, ducts, pipes, valves, insulations, controls, access doors, equipment support (concrete pad), and all associated accessories for Heating, Ventilating, and Air Conditioning (HVAC) system as shown on drawings.
2.1.2.2. Repair ventilation system with new exhaust fans, range hood, energy recovery ventilators, sliding balancer track system for removal disel exhaust, heat destratification fan, CO2 sensor, controls, diffusers, grilles, louvers, dampers, ducts, insulations, access doors, equipment support (concrete pad), and all associated accessories for HVAC system as shown on drawings.
2.1.2.3. Perform Duct Air Leakage Test (DALT) and Testing, Adjusting, and Balancing (T.A.B) after construction to verify that the HVAC system works properly.
TP I-3
2.1.2.4. Repair plumbing system with new domestic cold and hot water piping system, sewer and vent piping system including plumbing fixtures, washer box, domestic hot water heater, domestic hot water recirculation pump, valves, water hammer arresters, emergency eyewash and shower station, control, access doors, and all associated accessories as shown on drawings.
2.1.2.5. Repair sprinkler system with new automatic fire protection wet sprinkler system, spare sprinkler head cabinet with spare sprinkler head (6ea), and fire suppression system (for range hood) as shown on drawings.
2.1.2.6. The contractor shall inspect and test the fire protection system. The work inspection and test shall be performed by the Fire Protection Professional Engineer (FPE).
2.1.3. Electrical Work
2.1.3.1. Replace existing lighting fixtures, exit lights, exterior lights, emergency alarm lights, toggle switches, 3-way switches, photocell, lighting contactor, remote roll-up doors and emergency alarm lights controller, wires and conduits with new.
2.1.3.2. Replace panelboards, receptacles and cover plates, and wires and conduits with new.
2.1.3.3. Replace existing safety switches, combination motor starters, magnetic motor starters, junction boxes, control system, wires and conduits for HVAC system with new.
2.1.3.4. Replace existing fire alarm control system with new addressable fire alarm control and mass notification system panel, building transmitter, antenna, lighting arrester, manual pull stations, smoke detectors and relay modules, visual signal strobes, microphone, speaker devices, and associated wiring and conduit.
2.1.3.5. Replace existing Telephone Terminal Board (TTB), equipment rack, telephone/data outlets, and associated wire and conduit with new.
2.1.3.6. Replace existing cable TV distribution system, CATV outlets and associated wiring and conduit with new.
2.1.3.7. Replace existing Public Address (PA) system, speakers, and associated wiring and conduit with new.
2.1.3.8. Replace existing lightning protection system with new.
2.1.3.9. Replace existing underground exterior telecommunication line with new.
2.1.3.10. Remove and reinstall existing communication devices and cables, radio antenna.
2.1.3.11. Replace existing underground exterior power distribution system including pad mounted transformer and manholes with new.
2.1.3.12. Replace existing emergency backup generator sets and Automatic Transfer Switch (ATS) with associated wiring and conduit with new.
TP I-4
2.2. Schedule #II, New Construction (L): All work shall be in accordance with the attached drawings and specifications.
2.2.1. Civil Work
2.2.1.1. Install 150mm diameter Polyvinyl Chloride (PVC) fire water line with two (2) 150mm gate valve.
2.2.1.2. Install 80mm diameter PVC service water line with one (1) 80mm gate valve.
2.2.1.3. Replace 2.0m width concrete step with handrail and concrete stoop.
2.2.1.4. Restore Portland Cement Concrete (PCC) pavement.
2.2.1.5. Replace all necessary fuel tank parts including 20mm two (2) supply and 20mm one (1) return double wall pipes, except fuel tank and concrete pad with cleaning the fuel tank.
2.2.1.6. Restore solid sodding.
2.2.1.7. Construct trash bin.
2.2.1.8. Construct one (1) oil water separator and three (3) sewer manhole and connect to existing sewer manhole with 150mm diameter PVC pipe.
2.2.1.9. Construct concrete encasement.
2.2.1.10. Connect to existing 20mm diameter supply and return fuel line with flexible double wall pipes.
2.2.1.11. Reroute 200mm diameter PVC water line with one (1) air vacuum valve.
2.2.1.12. Construct one (1) hydrant with 150mm diameter gate valve.
2.2.1.13. Install 100mm diameter service water line with 100mm diameter gate valve.
2.2.1.14. Install 150mm diameter fire water line with 150mm diameter gate valve.
2.2.1.15. Construct eight (8) bollards around generator and transformer.
2.2.1.16. Replace exist chain link fence with new (FE-10) and block with rebar where gap between bottom rail and ground is bigger than 100MM and remove trees and vegetation 2.0M in and out of chain link fence.
2.2.1.17. Replace trees (3) double swing gate.
2.2.1.18. Replace warning sign plate on outer chain link fence every 50M.
2.2.1.19. Put weed control mat and coconut mat 1.0M each both in and out of chain link fence.
2.2.2. Architectural Work
2.2.2.1. Floor work
2.2.2.1.1. Install Vinyl Composition Tile (VCT) including VCB as shown on floor plan and interior finish schedule.
2.2.2.1.2. Install rubber tiles including rubber tile base as shown on floor plans and interior finish schedule.
2.2.2.1.3. Install concrete slab and stoops as shown on floor plans, sections, and structure drawings.
TP I-5
2.2.2.1.4. Apply epoxy coating with non-slip grits as shown on floor plan and interior finish schedule.
2.2.2.1.5. Install CFT with new including cement bond coat, waterproof membrane, and mortar bed as shown on floor plans and detail drawings.
2.2.2.1.6. Install trenches including trench covers in apparatus as shown on floor plans, sections, and detail drawings.
2.2.2.2. Interior and exterior wall work
2.2.2.2.1. Install all GWB walls including metal studs and insulation as shown on floor plans, sections, and detail drawings.
2.2.2.2.2. Paint all interior/exterior wall surfaces including other components (Guard post and trash bin) as shown on interior finish schedule, elevations and sections.
2.2.2.2.3. Install Glazed Ceramic Wall Tile (GCWT, full height) including cement bond coats, waterproof membrane, and plastering with metal lath as shown on floor plans and sections.
2.2.2.2.4. Install pipe chases/pipe cover waterproof or ‘X’ type of GWB for mechanical piping system and duct as per floor plans, sections, and detail drawings.
2.2.2.2.5. Install protected metal wall siding and protected metal wall liner panel including insulations with vapor barriers as shown on floor plans, elevations, sections, and detail drawings.
2.2.2.3. Interior and exterior ceiling and roof work
2.2.2.3.1. Install ceiling acoustical ceiling tile including metal suspension systems as shown on floor plan and interior finish schedule.
2.2.2.3.2. Install ceiling GWB (Normal, water resistant or 'X' type) ceiling including ceiling suspension system as shown on floor plans and finish schedule.
2.2.2.3.3. Paint all interior ceiling surfaces as shown on floor plans, sections, interior finish schedule, and section.
2.2.2.3.4. Paint all exterior exposed metal, woods, fascia, soffit, and metal flashing as shown on floor plan and elevations.
2.2.2.3.5. Install standing seam metal roof and protected metal roof liner panels including insulations with vapor barriers as shown on floorplans, elevations, sections, and detail drawings.
2.2.2.3.6. Install metal canopies including rain gutters and downspouts as shown on floor plans, elevations, and detail drawings.
2.2.2.3.7. Install protected metal rain gutters and downspouts including concrete splash blocks as shown on floor plans and elevations.
2.2.2.4. Miscellaneous work
TP I-6
2.2.2.4.1. Install doors and door frames including new hardware sets as shown on new floor plan and door schedule.
2.2.2.4.2. Install windows including insect screen with new aluminum thermal breaker type windows including glass as shown on floor plans, elevations, and window schedule.
2.2.2.4.3. Install aluminum louver as shown on floor plans and louver schedule.
2.2.2.4.4. Install metal shelf with mop rack in janitor room as shown on floor plans and detail drawing.
2.2.2.4.5. Install window horizontal mini blinds, fireproof type.
2.2.2.4.6. Install FECs and FEBs as shown on new floor plans and detail drawing.
2.2.2.4.7. Install all toilet accessories and wooden shower benches as shown on floor plans and detail drawings.
2.2.2.4.8. Install storage shelves with plastic laminates as shown on floor plan, elevation, and detail drawings.
2.2.2.4.9. Install interior and exterior signages with new for all rooms as shown on floor plan, elevations, and signage schedule.
2.2.2.4.10. Install roll up doors including manual hand chain and wire remote controller as shown on floor plans and door schedule.
2.2.2.4.11. Install SST laundry shelves room as shown on floor plan and detail drawing.
2.2.2.4.12. Install access doors on wall and ceiling as required.
2.2.2.4.13. Install guard posts as shown on floor plans and detail drawing.
2.2.2.4.14. Install bulletin boards as shown on floor plans and detail drawings.
2.2.3. Mechanical Work
2.2.3.1. Install new VRF duct-free split heat pump indoor and outdoor units, hot water boiler, hot water circulation pump, electric wall mounted heaters, electric ceiling heater, electric unit heater, unit heaters, air separator, expansion tank, air compressor, ducts, pipes, valves, insulations, controls, access doors, equipment support (concrete pad), and all associated accessories for the heating and cooling system as shown on drawings.
2.2.3.2. Install new exhaust fans, energy recovery ventilators, sliding balancer track system for removal disel exhaust, heat destratification fan, CO2 sensor, controls, diffusers, grilles, louvers, dampers, ducts, insulations, access doors, equipment support (concrete pad), and all associated accessories for the ventilation system as shown on drawings.
2.2.3.3. Perform DALT and T.A.B after construction to verify that the HVAC system works properly.
2.2.3.4. Install new domestic cold and hot water piping system, sewer and vent piping system including plumbing fixtures, washer box, domestic hot water heater, domestic hot water recirculation pump, valves, water hammer arresters, emergency eyewash and shower station, electric water cooler, control, access doors, and all associated accessories for the plumbing system as shown on drawings.
2.2.3.5. Install new automatic fire protection wet sprinkler system, spare sprinkler head cabinet with spare sprinkler head (6ea), and all associated accessories for the sprinkler
TP I-7
system as shown on drawings.
2.2.3.6. The contractor shall inspect and test the fire protection system. The work inspection and test shall be performed by the FPE (Fire Protection Professional Engineer).
2.2.4. Electrical Work
2.2.4.1. Install new lighting fixtures, exit lights, exterior lights, emergency alarm lights, toggle switches, 3-way switches, photocell, lighting contactor, remote roll-up doors and emergency alarm lights controller, wires and conduits.
2.2.4.2. Install new watt hour meter, Current Transformers (CT), panelboards, receptacles and cover plates, and wires and conduits.
2.2.4.3. Install new safety switches, combination motor starters, magnetic motor starters, junction boxes, control system, wires and conduits for HVAC system.
2.2.4.4. Replace existing fire alarm control system with new addressable fire alarm control and mass notification system panel, manual pull stations, smoke detectors and relay modules, visual signal strobes, microphone, speaker devices, and associated wiring and conduit.
2.2.4.5. Install new Telephone Terminal Board (TTB), equipment rack, telephone/data outlets, and associated wire and conduit.
2.2.4.6. Install new cable TV distribution system, CATV outlets, and associated wiring and conduit.
2.2.4.7. Install new Public Address (PA) speakers and connect to new PA system with associated wiring and conduit.
2.2.4.8. Install new underground exterior telecommunication line including manhole.
2.2.4.9. Replace existing lightning protection system with new.
2.2.5. Structural Work
2.2.5.1. Construct concrete slab.
2.2.5.2. Construct concrete stoop with step.
2.2.5.3. Construct 200mm thickness concrete stem and foundation.
2.2.5.4. Construct roof with steel column, beam, and standing seam metal roofing.
2.2.5.5. Construct interior/exterior stairs.
2.2.5.6. Construct 250mm thickness concrete ramp.
2.2.5.7. Submit structure design analysis and shop drawing.
TP I-8
TECHNICAL PROVISIONS - II
TECHNICAL DETAIL SPECIFICATIONS
GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/2014-OMA-SPECS_REVISION- 1.pdf. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.
The Standard Technical Detail Specifications:
The work shall conform to the most current version of the listed standards/specifications below.
DIVISION 01 – GENERAL REQUIREMENTS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED
MATERIAL
02 65 00 UNDERGROUND STORAGE TANK REMOVAL
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS
MATERIALS
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
TP II-1
02 83 19.00 10 LEAD BASED PAINT HAZARD ABATEMENT, TARGET
HOUSING & CHILD OCCUPIED FACILITIES
DIVISION 03 – CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 05 23 WELDING, STRUCTURAL
05 12 00 STRUCTURAL STEEL
05 21 23 STEEL JOIST GIRDER FRAMING
05 30 00 STEEL DECKS
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 50 14 STRUCTURAL METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 22 00 ROOF AND DECK INSULATION
07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS
07 41 13 METAL ROOF PANELS
07 42 13 METAL WALL PANELS
07 60 00 FLASHING AND SHEET METAL
07 92 00 JOINT SEALANTS
DIVISION 08 – OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 33 23 OVERHEAD COILING DOORS
08 51 13 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
TP II-2
08 81 00 GLAZING
08 87 16 FRAGMENT RETENTION FILM FOR GLASS
08 91 00 METAL WALL AND DOOR LOUVERS
DIVISION 09 – FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 22 36 LATH
09 29 00 GYPSUM BOARD
09 30 00 CERAMIC TILE, QUARRY TILE, AND PAVER TILE
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 90 00 PAINTS AND COATINGS
DIVISION 10 – SPECIALTIES
10 14 01 EXTERIOR SIGNAGE
10 14 02 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 28 13 TOILET ACCESSORIES
DIVISION 12 – FURNISHINGS
12 21 00 WINDOW BLINDS
12 32 00 MANUFACTURED WOOD CASEWORK
12 36 00 COUNTERTOPS
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 – PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
TP II-3
23 09 53.00 20 SPACE TEMPERATURE CONTROL SYSTEMS
23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT
DIVISION 26 – ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 32 14.00 10 DIESEL-GENERATOR SET, STATIONARY 15-300 KW, STANDBY
APPLICATIONS
26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 – COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 33.00 10 FIRE ALARM REPORTING SYSTEM, RADIO TYPE
28 31 49 CARBON MONOXIDE DETECTORS
28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 – EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.17 COLD MILLING OF BITUMINOUS PAVEMENTS
32 11 16 SUBBASES FOR FLEXIBLE PAVING
32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE
32 11 24 GRADED CRUSHED AGGREGATE BASE COURSE FOR PERVIOUS
PAVEMENT
32 12 10 BITUMINOUS TACK AND PRIME COATS
32 12 11 BITUMINOUS SURFACE TREATMENT
32 12 15.13 HOT-MIX ASPHALT AIRFIELD PAVING
TP II-4
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 17 24.00 10 PAVEMENT MARKINGS
32 92 23 SODDING
DIVISION 33 – UTILITIES
33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
TP II-5
TECHNICAL PROVISIONS - III
SPECIAL CONDITIONS
1. Material Approval Submittal:
(1) The contractor shall submit a shop drawing submittal schedule and the material approval request with all supporting documents to the COR within 14 days after receipt of NTP.
(2) The Contractor shall process submittals in accordance with Section 013300 – SUBMITTAL
PROCEDURES.
2. Extended warranty - FAR 52.246-21
2.1. Extended warranty list
2.2. Contractor shall submit to COR the Warranty Certification with 4025 for the listed items.
2.3. Contractor shall submit to COR Warranty management plan and approve it before 30 days of pre-warranty conference. (OMA Sec 01 78 00)
2.4. Contractor shall have the Pre-Warranty Conference before Contract Close Date. (OMA Sec 01 78)
2.5. Warranty Information and Data
TP III-1
2.5.1. Contractor shall submit Warranty tag design, COR shall review and approve it for the listed and shall install it for the listed items. (OMA Sec 01 78 00)
2.5.2. Submit the O&M Manual with Manufacture’s instruction for DPW training. (OMA Sec 01 78 00)
3. The contractor shall have personnel on site for the sprinkler work and the fire alarm work upon Government's direction, who are certified by the National Institute for Certification in Engineering
L/N Warranty Item Description Warranty
Period (Yrs) Certification
(Yes / No) Warranty Tag
(Yes / No) Repair Time after call
1 Metal roof panel Installer 10 N N 24hrs
2 Acrylic fluid-applied proofing. Installer 2 N N 24hrs
3 Leak Detection Module panel TMS-2000 Installer 10
4 Float Level S/W Assm'y MP 450 Installer 10
5 Leak Sensor Installer 10
6 Leak Detection Module panel progrem Fee Installer 10
7 Oil Water Separator Installer 10
8 VRF Heat Pump, Outdoor Unit Product 3 Y Y 24 Hrs
9 VRF Heat Pump, Indoor Unit Product 3 Y Y 24 Hrs
10 Energy Recovery Ventilator Product 3 Y Y 24 Hrs
11 Split Type Heat Pump, Indoor & Outdoor Unit Product 3 Y Y 24 Hrs
12 LED Light Product 10 Y Y 7 Days
Technologies (NICET) Level III or equivalent. Equivalent Certificates in Korea are the followings which are issued by the Human Resource Development Service of Korea. If the contractor doesn’t have personnel who are certified by NICET, the contractor shall have two personnel that one is certified for (1) and the other for (2) below.
(1) Engineer Fire Fighting Facilities - Electrical (소방설비기사 -전기)
(2) Engineer Fire Fighting Facilities - Mechanical (소방설비기사 -기계)
4. Environmental Requirements in Contract
The Contractor shall perform work consistent with the relevant policy and objectives identified in Installation’s Environmental Management System (EMS). The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by Installation’s EMS, including pollution prevention, waste reduction, energy use, and natural resource protection. The Contractor shall provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In addition, the Contractor shall advise their employees of their roles and responsibilities identified by the EMS and how these requirements affect their work performed under this contract. The Contractor is responsible for ensuring that the Contractor and any persons involved in the supervision or performance of the contract complete all required Environmental training.
In the event of any environmental nonconformance or noncompliance associated with the contracted services, the contractor shall take corrective and/or preventative actions. In the event of any noncompliance with any federal, state, or local environmental law, regulation or requirement, the Contractor shall immediately respond by taking all appropriate corrective actions and notifying the Contracting Officer’s Representative (COR) and the Environmental Office. For any nonconformance with the EMS, the Contractor shall take corrective action and initiate further preventative action, as required by the Environmental Office.
All on-site contractor personnel shall complete necessary safety and environmental training specified for the type of work conducted on-site. Upon contract award, the COR will notify the EMS Manager to arrange Environmental training for appropriate staff.
Additionally, when ordering supplies for use on Installation, all contractor personnel must favor energy-efficient, recycled or reclaimed material whenever practicable.
The responsibilities of all contractor personnel include:
TP III-2
(1) Comply with all applicable environmental laws, regulations and installation environmental policies.
(2) Control and prevent spills or hazardous substances releases IAW installation Spill Prevention
Plan.
(3) Ensure dust, debris, materials, trash, etc., do not become air borne and travel off the project site.
(4) Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, topsoil and landforms without approval, except in areas indicated on the drawings or specified to be cleared.
(5) Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated.
(6) Open burning is prohibited on the Government premises IAW installation environmental policy.
(7) Participate in installation’s recycling program.
(8) Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content. Spills of hazardous or toxic materials must be immediately reported to the Contracting Officer and the Environmental Office.
Storage, describing, packaging, labeling, marking and placarding of hazardous waste and hazardous material IAW applicable environmental laws, regulations and local environmental policies. Transport hazardous waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.
(9) Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling. Handling, storage, and disposal of solid waste must be conducted to prevent contamination. Transport solid waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.
(10) Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must.
(11) When potential cultural or historic items are inadvertently found during construction activities, immediately cease activities in the vicinity of the discovery and report the findings to the Environmental Office.
(12) Participate in installation’s Integrated Pest Management (IPM) program whenever practicable.
TP III-3
(13) Minimize interference with disturbance to, and damage to fish, wildlife, and plants including their habitat.
5. CONTRACT REQUIREMENTS PACKAGE ANTITERRORISM/OPERATIONS SECURITY REVIEW
COVER SHEET
After Notice to process is issued, COR shall take following action, Section IV. Standard Contract Language/Contract Clause Applicability and/or Additional SOW Language.
A. AT Level I training. This standard language is for contractor employees with an area of performance within as Army controlled installation, facility or area. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas shall complete AT Level I awareness training within 30 calendar days after the contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil
B. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
B-a. For contractors that do not require CAC but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014- 05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
C. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to
TP III-4
watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
D. For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
(End of Summary of Changes)