Text version

F3J3CE9241AW03

" REPAINT BASE ROADS AND PARKING LOT MARKINGS, OSAN AIR BASE"

THIS IS GENERAL REPAIR IDIQ RFP FOR THE FOLLOWING CONTRACTORS ONLY:

CONTRACT NO.:W91QVN-19-D-0002, -0006, -0008, -0010, -0012.

OFFERORS MUST COMPLY WITH THE FOLLOWING:

A. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit clause in Section

L for the schedule.

B. Submission of Proposals

(1) Proposal Packet: It shall be submitted by 1300 hours on the closing date of RFP throuth FBO.

(2) Pricing & Technical proposal

a. Price and Bidding Schedule w ith Sub-CLINs

b. Completion of Section K, 5152.204-4032(Representations and Certif ications)

C. If the contractor is unable to submit the proposal in response to this RFP, the contractor shall submit a "No-Offer Letter" by the date and time specif ied in this solicitation.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

11-Sep-2019

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

X

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______0 calendar days and complete it w ithin ________120 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________23 Sep 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO OSAN, UNIT #2039

APO AP 96278-2039

UNITED STATES

W90VN6

PAGE OF PAGES

1 OF

CODE W90VN6

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

411TH CSB, KOREA - RCO OSAN

POC: MR.PAK, SIN NAM

0503-357-6013

SINNAM.PAK2.LN@MAIL.MIL

APO AP 96278-2039

UNITED STATES

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: 0503-357-6013 FAX:

W90VN619R0039 17

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued)

(Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Repaint Base Roads and Markings

FFP

SMYU 19-1002 : REPAINT BASE ROADS AND PARKING LOT MARKINGS

FOB: Destination

PURCHASE REQUEST NUMBER: F3J3CE9241AW03

PSC CD: Z2JZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job Estimated cost for War Hazard Losses

FFP

is zero (0)

FOB: Destination

PSC CD: Z2JZ

NET AMT

BID SCHEDULE

ITEM NO. DESCRIPTION QTY U/T UNIT

PRICE

AMOUNT

0002 AH Dispose of and haul all construction debris to off-base designated area permitted by ROKFC Government in accordance with appropriate laws and regulations

15 CY ₩ ₩

0005 AB Remove thermoplastic pavement marking 39,300 SF ₩ ₩

0006 AH Thermoplastic pavement marking 39,300 SF ₩ ₩

TOTAL AMOUNT (W) ₩

Section C - Descriptions and Specifications

SOW

PROJECT NUMBER: SMYU 19‐1002

DESCRIPTION: REPAINT BASE ROADS AND PARKING LOT MARKINGS,

FY19

1. GENERAL: The work to be performed for completion of this project shall be in general as described below and executed by the contractor.

1.1. Work by Contractor: The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as listed below and in accordance with the drawings, sketches and specifications.

1.2. Work by In‐House Forces: N/A

1.3. Work by Troop labor: N/A

2. TECHNICAL SPECIFICATIONS: Above project shall comply with specifications in awarded original contract package.

3. SCOPE OF WORKS (SOW):

3.1. Civil Works:

3.1.1 Remove existing center lines, crosswalk lines, and stop lines on the base road. (Approx. 39,300 SF)

3.1.2 Repaint center lines, crosswalk lines, and stop lines on the base road. (Approx. 39,300 SF)

3.1.3 Dispose existing marking paints.

3.1.4 Submit the phasing plan as part of AF Form 3000 submittal.

4. KEY INFORMATION FOR CONSTRUCTION SCHEDULE

Project Site Base Area Base Wide

Contract Type General IDIQ

Performance of Period (PoP)

120 Days after Task Order issued

PoP includes offshore material procurement, digging permit, AF Form 3000 approval & contractor mobilization

Temporary Airfield Construction Waiver Required (TACW)

N/A

Risk Assessment (RA) Required

N/A

Phasing Work Required Yes If yes, please see the “5.2. Remark”

Military Training Event Anticipated

N/A

Restricted Area Escort Required

N/A

5. REMARKS: All documents for drawings, construction schedule and, phasing plan shall be approved before construction start.

5.1. Military Training Events are anticipated to occur during the construction period as indicated in Table above. During Training Event, contractor will not be allowed to access the project site. Contractor shall consider these conditions in their proposal. Contractors will be given 72hours notice of work stoppage without incurring penalty to the Government.

5.2. Road marking schedule shall be determined based on circumstances of partial/full closure of road. Government will not release all sites for marking at once. Detail phasing plan shall be discussed and established with COR. Contractor shall prepare/submit road closure request to COR two weeks in advance at the minimum.

6. SECURITY REQUIRMENTS:

The training IWATCH/EAGLE EYES/AT Level I shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 45 calendar days after contract award.

ALERTS: During military alerts or special operations, the contractor may not be authorized on base or in the work site. When the contractor is prohibited from access to the base or work site for one (1) day or less per month, no adjustment in the contract time shall be made. When the contractor is prohibited access for more than one (1) day per month, adjustments shall be made in accordance with applicable clauses of the General Provisions.

BASE PASSES: The contractor shall be required to obtain base passes to Osan Air Base to perform the requirements of this contract. The contractor shall be responsible to submit a base pass request no later than five (5) calendar days after award of this contract. It should be noted that it can take up to 30 days or more to process base pass paperwork. It shall be the responsibility of the contractor to prepare the necessary base pass paperwork to include USFK Form 82‐E, USFK Form 225EK‐E, family history register, local register, etc. for each individual requiring access to Osan Air Base. The contractor shall also be authorized to receive vehicle passes for each of the contractor’s vehicles used in the performance of the requirements of this contract. It shall be the responsibility of the contractor to prepare the necessary paperwork to include USFK Form 195EK‐E, vehicle registration, vehicle insurance, certificate of safety inspection and a copy of driver’s license for each vehicle requiring access to Osan Air Base. The contractor shall prepare a cover letter listing each individual, skill, escort privileges, vehicle type, vehicle registration number, etc. The contractor shall also provide the COR with two (2) copies of this request letter, with carbons, to include the top copy with original signatures.

Escort privileges will be justified and limited to specific needs for contract completion and at the discretion and approval of the sponsor and requesting authorities identified in Block 13 and

W90VN619R0039

Section III of the USFK Form 82‐E, Application for Installation/Base Access. The contractor shall not be authorized to perform any portion of the contract requirements until such time that the contractor has processed the necessary base pass paperwork for entry onto Osan Air Base. The COR shall not provide or be responsible to provide the contractor with escorts during performance of any part of this contract. All of the above documents shall be turned in to the COR for processing with the 51st Security Forces.

The contractor and all associated sub‐contractors shall practice Operations Security. The contractor shall not talk about work outside of the work area nor discuss the work being performed on social media. Unless absolutely necessary to perform the duties stated in the contract, the contractor shall not take pictures of or inside sensitive locations as determined by the contracting officer representative. It shall be the responsibility of the contractor to safeguard all documents provided. Documents shall be stored away from view when not being used. Documents that are no longer needed shall be shredded in an approved government shredder.

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY REFERENCE

52.211-10 Commencement, Prosecution, and Completion of Work APR 1984

Section I - Contract Clauses

CLAUSES INCORPORATED BY FULL TEXT

52.232-18 AVAILABILITY OF FUNDS (APR 1984)

Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting

Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

(End of clause)

Section J - List of Documents, Exhibits and Other Attachments

DRAWINGS

LIST OF DRAWINGS

1. GENERAL: The work shall conform to the following contract drawings, all of which form a part of the specifications. Additional sets will be furnished to the contractor. Drawings are available at the 51 Civil Engineer Squadron, Osan AB.

PROJECT NUMBER: SMYU 19-1002

DESCRIPTION: REPAINT BASE ROADS AND PARKING LOT MARKINGS

DWG NO. SHT NO. REF NO. DESCRIPTION

1 TO 6 T-01 Cover Sheet

2 TO 6 C-01 Location Plan

3 TO 6 C-02 SITE PLAN-1

4 TO 6 C-03 SITE PLAN-2

5 TO 6 C-04 SITE PLAN-3

6 TO 6 C-05 SITE PLAN-4

Section K - Representations, Certifications and Other Statements of Offerors

5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS

(a) SUBCONTRACTING:

If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or

ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.

(b) AFFILIATED OFFERORS:

(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.

(2) Each offeror shall furnish, below, the following information:

(i) Whether the offeror has any affiliates;

(ii) The names and addresses of all affiliates of the offeror; and

(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.

AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)

(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):

Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.

(d) STANDARDS OF CONDUCT CERTIFICATION:

This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.

(i) Name ______________________________________________

Former rank/grade ____________________________________

Last US Government position ___________________________

(ii) Name ______________________________________________

(iii) Name ______________________________________________

Firm ____________________________________________________

Name _____________________________________________________

Signature __________________________________________________

Title _____________________________________________________

Date of Execution ____________________________________________

(e) TAXES:

(1) References:

(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."

(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.

(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.

(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.

(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

This item will be imported specifically for this contract? Yes _____ No _____

(ii) Special Excise Tax:

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

Name of item manufacturer

(iii) Value Added Tax (VAT):

Input VAT on materials purchased for this contract. 10% _____

Input VAT on transportation leased/rented for this contract.10% _____

Input VAT on equipment leased/rented for this contract. 10% _____

Input VAT on services purchased for this contract. 10% _____

Output VAT on total contract amount. 10% _____

(iv) Special Excise (Petroleum) Tax:

No. of U/P

Liters w/o Tax Tax/Unit Total Tax Amount

Regular Gasoline ________ (L) ________ w________ w_____________

Premium Gasoline ________ (L) ________ w________ w_____________

Diesel ________ (L) ________ w________ w_____________

Other ________ (L) ________ w________ w_____________

(v) Education Tax.

(3) Name of the oil company from which POL products will be purchased:

Oil Company: _________________________________________ (Name only)

(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.

Signed (Chop)

(f) CERTIFICATIONS AND REPRESENTATIONS

By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation.

The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.

Section L - Instructions, Conditions and Notices to Bidders

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for—

Date & Time: 18 Sep 2019, 1000 hrs

(c) Participants will meet at—

Bldg #142 at Morin Gate, Osan Air Base

POC: Mr. Pak, Sin Nam at sinnam.pak2.ln@mail.mil or 0503-357-6013

(End of provision)

5152.236-4011 CONSTRUCTION PRICE RANGE

Pursuant to FAR 36.204 the estimated price range is between $ 100,000.00 and $250,000.00.

INSTRUCTIONS TO OFFEROR

INSTRUCTIONS TO OFFEROR

1. GENERAL INSTRUCTIONS

a. The Government intends to award without discussion, but reserves the right to conduct discussions if deemed necessary and to establish a competitive range for efficiency in accordance with FAR 52.215- 1(f)(4).

b. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.

2. SUBMISSION OF PROPOSAL:

a. FBO SUBMISSION REQUIRED: Offers shall be submitted to the Federal Business Opportunities (FBO) website (https://www.fbo.gov/), or if FBO is not available, email to sinnam.pak2.ln@mail.mil and anthony.s.mosley.civ@mail.mil with the evidence document such as screen shot. The FBO unavailability is limited to only FBO server problem not individual failure/problem. All questions should be emailed to sinnam.pak2.ln@mail and anthony.s.mosley.civ@mail.mil within five (5) days by 1300 hours (Korea Standard Time) after the solicitation is issued.

mailto:sinnam.pak2.ln@mail.mil mailto:sinnam.pak2.ln@mail.mil mailto:anthony.s.mosley.civ@mail.mil mailto:sinnam.pak2.ln@mail mailto:anthony.s.mosley.civ@mail.mil

b. CLOSING DATE: The electronic offer shall be submitted by 1300 hours (Korea Standard Time) on the closing date of RFP.

3. SUBMISSION REQUIREMENTS

a. PRICING PROPOSAL: The pricing proposal must clearly indicate prices for each Contract Line Item Number in Section B - Supplies or Services and Prices.

b. BIDDING SCHEDULE WITH SUB-CLINs: The bidding schedule with Sub-CLINs must clearly identify all costs that can materially impact the statement of work.

c. SECTION K - Representations, Certifications and Other Statements of Offerors

d. SECTION K-TAXES: Offerors must complete all tax portions of SECTION K. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, offerors shall propose exemptions of specific ROK taxes that are legitimate, attributable to the contract, and authorized by the applicable stated references.

e. SECTION K-OTHER: Offerors must complete all Non-Tax related portions of SECTION K.

f. COMPLIANCE WITH SOLICITATION: Failure to submit the above requirements under SECTION L may be grounds for determining the proposal to be non-compliant. For example, if a detailed offer breakdown is not submitted, the contracting officer will be unable to find the offeror's pricing proposal acceptable and the offeror's proposal will be ineligible for award. Non-compliance will only be cured if the government holds discussions as detailed in SECTION L.

4. NO OFFER LETTER: If MA IDIQ Contractor is unable to submit the proposal in response to this RFP, the Contractor shall submit a 'No-Offer Letter' by date and time specified in this RFP.

5. SITE VISIT

a. Offerors who intend to propose on this solicitation are strongly encouraged to attend site visit. See site visit Clause, FAR 52.236-27 Alt I. Offerors are required to have a valid Korean Identification card or driver license when attending the site visit orientation

b. Offeror shall submit the following information to Mr. Pak, Sin Nam at sinnam.pak2.ln@mail.mil by 01:00 PM, 17 September 2019 for temporary access. After sending E-mail, offerors may confirm with Mr. Pak, Sin Nam at (0503) 357-6013 (Commercial) if the e-mail is delivered to his e-mail account.

- Individual(s) Name per offeror (Maximum 2 person may be escorted per company)

c. The attendee must bring a valid identification card with clean photo (주민등록증) or driver license.

6. Requirements

a. This Solicitation is for requirements CLIN 0001, Repaint Base Roads and Parking Lots with Statement of Works.

b. This requirement is below the $250,000 threshold.

c. This solicitation is “Subject to the Availibility of Funds”.

Section M - Evaluation Factors for Award

BASIS OF AWARD

Evaluation Factors for Award Electronic offers submitted by 1300 hours (Korea standard Time) on the closing date of RFP shall be considered timely.

1. EVALUATION CRITERIA

a. The pricing proposal shall be evaluated to determine whether it is complete and reasonable. A complete and reasonable pricing proposal will be deemed acceptable.

b. The bidding schedule with Sub-CLINs will be used by the contracting officer to determine whether proposed prices are complete and reasonable. A bidding schedule with Sub-CLINs may be used by the contracting officer to determine whether an offeror is able to complete the requirements under the contract, and/or whether discussions will be conducted pursuant to instructions to the offerors.

c. SECTION K - Representations, Certifications and Other Statements of Offerors

d. SECTION K-TAXES will be evaluated to determine whether it is complete. In addition, propose exemptions of specific ROK taxes will be evaluated to determine whether they are legitimate, attributable to the contract, authorized, and reasonable. A complete SECTION-K that only proposes exemptions of specific ROK taxes that are legitimate, attributable to the contract, necessary to complete the Task Order, do not improperly overstate any proposed tax exemption, authorized, and reasonable will be deemed acceptable.

e. SECTION K-OTHER will be evaluated to determine whether it is complete. A complete SECTION K-OTHER will be deemed acceptable.

2. BASIS FOR AWARD: Award shall be made to the responsible offeror submitting the lowest priced offer that is evaluated as acceptable for all evaluation criteria.