W90VN619R0023_repair_AF_tech_B320.pdf

PDF 542 KB Posted

Attached to
SMYU 19-1049 Reapir AF Tech B320
Solicitation number
W90VN619R0023
Issued by

About this file

W90VN619R0023

View the file

Other files

File Type Posted
Bidding_Schedule__(SMYU_19-1049).xls XLS spreadsheet
DWG_(SMYU_19-1049).pdf PDF
W90VN619R0023_repair_AF_tech_B320.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F3J3CE9095AW01

"REPAIR AF TECH APPLICATIONS CENTER, B320, OSAN AIR BASE"

THIS IS BUILDING GENERAL REPAIR IDIQ RFP FOR THE FOLLOWING CONTRACTORS ONLY:

CONTRACT NO.:W91QVN-19-D-0002, -0006, -0008, -0010, -0012.

OFFERORS MUST COMPLY WITH THE FOLLOWING:

A. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit clause in Section L for the schedule.

B. Submission of Proposals

(1) Proposal Packet: It shall be submitted by 1300 hours on the closing date of RFP throuth FBO.

a. Bidding Schedule

b. Completion of Section K

C. If the contractor is unable to submit the proposal in response to this RFP, the contractor shall submit a "No-Offer Letter" by the date and time specif ied in this solicitation.

CPT BOOKWALTER, RANDY 315-757-6020

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

29-Apr-2019

(RFP)

(IFB)

X

CALL:

Repair AF tech applications center B320

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

X

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO OSAN, UNIT #2039

APO AP 96278-2039

W90VN6

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

SMYU 19-1049

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W90VN619R0023 15

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W90VN619R0023

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot Repair AF Tech Applications Center, B320

FFP

SMYU 19-1049 REPAIR AF TECH APPLICATIONS CENTER, B320 See SOW FOB: Destination MFR PART NR: Null

PURCHASE REQUEST NUMBER: F3J3CE9095AW01

PSC CD: Z2JZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Lot Estimated Cost for War Hazard

FFP

FOB: Destination

NET AMT

Section C - Descriptions and Specifications

STAETMENT OF WORK

Statement of Work

1. GENERAL: The work to be performed for completion of this project shall be in general as described below and executed by the contractor.

1.1 Work by Contractor: The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as listed below and in accordance with the drawings, sketches and specifications.

1.2 Work by In‐House Forces: N/A

1.3 Work by Troop labor: N/A

2. TECHNICAL SPECIFICATIONS: Above project shall comply with specifications in awarded original contract package and attached particular specification, if any.

3. SCOPE OF WORKS (SOW):

a. Architectural Works:

Floor (Interior)

1. Replace existing carpet flooring with new incl. cove base in R‐101.

2. Apply epoxy coating on existing floors in R‐104 & R‐105 Floor (Exterior)

3. Remove existing asphalt pavement partially and install new concrete stoop incl. floor door holder at the R‐101 entrance door.

4. Replace existing concrete stoop with new incl. floor door holder at the R‐103 entrance door.

5. Cut the existing ground/asphalt pavement and restore it when electrical LAN work done (Approx. 40LF).

Wall (Interior)

6. Replace existing interior gypsum board walls with new incl. wall frames and batt insulations in R‐101.

7. Install new interior gypsum board walls incl. wall frames and batt insulations in R‐104 & R‐ 105.

8. Remove existing walls partially to provide door openings and passages for a single door between R‐101 & R‐103 and a double door between R‐104 & R‐105. The job shall include all relevant finish works.

9. Apply paint/coating on entire interior gypsum board walls and exposed steel frames on wall & ceiling.

Wall (Exterior)

10. Remove existing wooden panels, window, A/C unit, heating stuff and block up the openings with metal sheets incl. insulation on the exterior wall of R‐101.

11. Repair all damaged exterior walls and apply paint/coatings on the entire exterior walls of the building.

Ceiling

12. Replace existing acoustical tile ceiling system with new in R‐101 & R‐103.

Door

13. Replace existing doors and frames with new hollow metal ones incl. all relevant hardware as shown on the drawing A‐01 and the door/hardware schedule below.

14. Replace existing sliding door and frame in R‐104 with new electric power operated roll up door (Approx. 10’w x 8’h) incl. outside locking device, wall frames for support, 2 sets of steel pipe guard post and all relevant hardware as shown on the drawing A‐01 and the door/hardware schedule below.

15. Install a new single hollow metal door between R‐101 & R‐103 and a new double hollow metal door between R‐104 and R‐105 incl. wall frames for support and all relevant hardware as shown on the drawing A‐01 and door/hardware schedule below.

Bathroom

16. Replace existing toilet partition and toilet accessories such as toilet paper holder (1EA), paper towel dispenser (1EA), shower curtain/rod (1EA), liquid soap dispenser (1EA), soap dish (1EA) for shower, robe hook (2EA), SST shelf (1EA), mirror glass (1EA), towel bar (1EA), medicine cabinet (1EA) with new in R‐102.

17. Remove existing wall mounted lavatory and install a new marble topped vanity cabinet in R‐ 102.

18. Repair/patch the existing wall & floor ceramic tiles including perfect cleaning and paint/coating existing gypsum board ceiling in R‐102 (Do not touch the existing water heater).

MISC

19. Move existing furniture, equipment and any stuff according to the user’s request and move them back where they were when all works done.

20. Provide any support works for mechanical & electrical works.

21. Remove all construction debris originated from the project and clean up the job site.

22. The contractor shall be responsible to repair all damages to existing areas caused by the project and to match condition to adjacent areas.

Door & Hardware Schedule

b. Mechanical Works:

1. Remove the exiting HVAC units such as split type wall mounted air conditioning indoor and outdoor unit, space hot air blower, and thru the wall type air conditioner. A/C units for RM No. 103 remain.

2. Replace the existing side wall exhaust fan, 100 CFM@ 0.125 in SP with new including backdraft damper and insect screen. Exhaust fan switch on/off shall be interlocked to the light switch.

3. Remove the fuel oil pipe from the fuel oil tank. Cap and abandon the existing fuel oil tank.

4. Replace insulation of existing water heater with new.

5. Replace the existing lavatory and water closet including piping with new ones.

6. Provide new floor standing heat pump indoor and outdoor unit, cooling 12,000 btu/h, heating 16,000 btu/h, Cooling Range: ‐4° F to 110° F, Heating Range: ‐13° F to 70° F, including wall mounted temperature controller and piping. Concrete pad for equipment shall be included.

7. Provide new ceiling concealed energy recovery ventilator 150 CFM with wall mounted wire remote controller including air diffuser and duct work.

8. Provide new exterior wall mounted heat pump unit including duct and register work.

Bard Model No. W18H2 (1‐1/2 ton) including 3.75 kW electric heat, low ambient control and relay, outdoor thermostat, wall mounted temperature controller, 208V/60A/1PH or approved equal.

9. Provide new pendent type sprinkler head, associate accessories and piping. Inspection, test, report under NICET supervision shall be performed.

c. Electrical Works:

1. Removal work

General; Remove existing conduit/wire for lighting, power, and comm. system.

1) Room #101 (Office)

Remove existing cable from distribution panelboard “MDPU” to subpanel in B320.

Remove existing conduits and wires on the ceiling for lighting system.

Remove existing power and comm. outlet in this room.

Remove existing lighting fixtures TYPE 206 on the ceiling in room #101 (Fluorescent 2’x4’) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐3EA

Remove existing toggle switch on the wall ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐2EA

Remove existing distribution panelboard on the wall(18 circuit breakers)‐‐‐‐‐‐‐‐1EA

Remove existing TEL outlets ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐4EA

Remove existing power receptacles ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐4EA

2) Room #102 (Toilet)

Remove existing lightings include the mirror light.

Remove existing toggle switch

3) Room #104 (Storage)

Remove existing lighting fixtures TYPE 302 Low Bay on the ceiling ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐4EA

Remove existing toggle switches for ceiling lights ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐2EA

Remove existing telephone terminal block on the wall ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐1EA

4) Room #105 (Storage)

Remove existing conduit and wires on the ceiling for lighting system.

Remove existing fluorescent lighting fixtures(1’x4’, surface Mtd.) on the ceiling.‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐2EA

5) Room #103 Remove existing lightings fixtures.

Remove existing toggle switches.

6) Exterior.

Remove existing lighting fixture on the exterior wall above room #105, and #103 entrance door

2. Installation work

1) Room #101 (Office)

Install new cable 600V “THW” 4‐1C #2 AWG, 1C #6 (G) in existing conduit from B321 “MPDU” to B320 main panelboard.

Install new distribution panelboard 3ph, 4W, 60Hz, 208/120V, flush mount in the wall as follow.

Main CB; 3P, 208V, 100AF/70AT, 22KAIC Branch CB;

2P, 100AF/20AT‐‐‐‐‐‐‐‐‐‐‐8EA

1P, 100AF/20AT‐‐‐‐‐‐‐‐‐‐‐12EA

Install new LED dimmable lighting fixtures type RF8 (FED STD 40‐06‐04‐52) recessed mounted, size 2’x2’, with conduits and wires from new panelboard .‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐5EA (SLG‐ TV600‐49‐WDM‐120‐40K or approved equal) ‐ With EM 1EA, without EM 4EA ‐ Illumination level is 30fc

Install dimmer switch for above LED lights.

Install conduit and wire thru ceiling from new distribution panelboard.

Install the power receptacles with wire as shown on the drawing.

Install the LAN/Tel outlet with FO cable as shown on the drawing.

Install wall mount type LAN switch (Catalyst 2960‐XR 24 GigE PoE 370W, 4 x 1G SFP, IP Lite (Model # WS‐C2960XR‐24PS‐1)

Install power source for existing Water Heater from new panelboard to WH include safety switch.

2) Room #102 (Toilet) Install LED lighting fixture on the ceiling as shown on the drawing. (TYPE RF1)

Install mirror lighting type WF 3 with LED.

Install GFCI receptacle on the wall above 30cm from washbasin.

3) Room #103 (Equipment)

Install new LED dimmable lighting fixtures type RF8 (FED STD 40‐06‐04‐52) recessed mounted, size 2’x2’, with conduits and wires from new panelboard .‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐4EA (SLG‐ TV600‐49‐WDM‐120‐40K or approved equal) ‐ With EM 1EA, without EM 3EA ‐ Illumination level is 30fc

Install dimmer switch for above LED lights.

Install receptacles as shown on the drawing.

4) Room #104 (Maintenance Shop 1)

Install TYPE SF4 (FED STD 40‐06‐04‐78) on the ceiling lights, surface mount, size 1’x4’ dimmable with LED lamp as shown on the drawing. (Lighting Model No. SLGTV600‐ 38‐WDM120‐40K‐WEM or approved equal) ‐ Without EM battery 5EA, with EM 1EA.

Install dimmer switch on the wall.

‐ Illumination level: 50fc

Install power outlet as shown on the drawing.

Install LAN/TEL outlet as shown on the drawing.

Install safety switch 1P, 30A, 240V for roll up door as shown on the drawing. And power source from new distribution panelboard in room #101.

5) Room #105 (Maintenance Shop 2) Install TYPE SF4 (FED STD 40‐06‐04‐78) on the ceiling lights dimmable with LED lamp as shown on the drawing.

‐ With EM 1EA, without EM 3EA.

‐ Surface mounted type.

‐ Size, 1’x 4’

‐ SLG‐TV600‐49‐WDM‐120‐40K or approved equal.

‐ Illumination level: 50fc

Install power outlets (receptacles) as shown on the sketch.

6) Power source for Mechanical Equipment

Install safety switch 600V, 30A, with fuse, NEMA 3R enclosure near the new wall mounted HEAT PUMP on the exterior wall, see mechanical drawing for location of heat pumps.

The power source from new installed panelboard in room #101.

7) Exterior

Install security lights on the exterior wall as shown on the drawing.

o ‐ Type EH5 (FED STD 40‐06‐04‐12) but lamp will be LED.

Install FO cable 12 Strand from ITN in B355 thru existing inner duct to FO wall mounted cabinet switch in room #101 as shown on the drawing. (splicing in the manhole is not allowed)‐ Approximate 1.2km

Install new duct from MH318 to B320 room #101 as shown on the drawing.

Excavation and backfill for ductbank is included on the Arch.4. ATTACHED DRAWING OR SKETCH OR PICTURES: Yes

5. CONTRACT PERFORMANCE PERIOD: 180 calendar days ARO and it includes off‐shore materials procurement + base pass authorization + military exercise (90 days) and construction period (90 days).

6. ATTACHED CLIN ITEMS INCL. COST (IGCE): Yes

7. REMARKS:

7‐1. Site Orientation will be strongly recommended. The contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the works, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost IAW FAR 52.236‐3.

7‐2. Time on target of the site release date will be discussed with user & BCE at the pre‐con meeting after award.

8. SECURITY REQUIRMENTS (AT/OPSEC):

8.1 Contractor’s personnel or any representative of the contractor entering installation/base shall abide by all security regulations imposed by Installation Commander or Base Commander at all times and shall be subject to security checks. Contractor’s personnel and property shall be subject to search and seizure upon entering the confines of the installation/base, while on, and upon leaving confines of the installation/base.

8.2 The training IWATCH/EAGLE EYES/AT Level I shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 45 calendar days after contract award.

8.3 ALERTS: During military alerts or special operations, the contractor may not be authorized on base or in the work site. When the contractor is prohibited from access to the base or work site for one (1) day or less per month, no adjustment in the contract time shall be made. When the contractor is prohibited access for more than one (1) day per month, adjustments shall be made in accordance with applicable clauses of the General Provisions.

8.4 BASE PASSES: The contractor shall be required to obtain base passes to Osan Air Base to perform the requirements of this contract. The contractor shall be responsible to submit a base pass request no later than five (5) calendar days after award of this contract. It should be noted that it can take up to 30 days or more to process base pass paperwork. It shall be the responsibility of the contractor to prepare the necessary base pass paperwork to include USFK Form 82, USFK Form 225 EK, family history register, local register, etc. for each individual requiring access to Osan Air Base. The contractor shall also be authorized to receive vehicle passes for each of the contractor’s vehicles used in the performance of the requirements of this contract. It shall be the responsibility of the contractor to prepare the necessary paperwork to include USFK Form 195, vehicle registration, vehicle insurance, copy of driver’s license, etc. for each vehicle requiring access to Osan Air Base. The contractor shall prepare a cover letter listing each individual, skill, escort privileges, vehicle type, vehicle registration number, etc. The contractor shall also provide the COR with two (2) copies of this request letter, with carbons, to include the top copy with original signatures. Escort privileges will only be authorized to company officials and the site superintendent and the Site Foreman. No other individual will be authorized escort privileges. The contractor shall not be authorized to perform any portion of the contract requirements until such time that the contractor has processed the necessary base pass paperwork for entry onto Osan Air Base. The COR shall not provide or be responsible to provide the contractor with escorts during performance of any part of this contract. All of the above documents shall be turned in to the COR for processing with the 51st Security Forces.

8.5 Return Post/Base Passes: On the contract completion date, the contractor shall turn in all passes to the sponsor that were issued for the contract and final payment will not be made until such items are returned.

8.6 The contractor and all associated sub‐contractors shall practice Operations Security. The contractor shall not talk about work outside of the work area nor discuss the work being performed on social media. Unless absolutely necessary to perform the duties stated in the contract, the contractor shall not take pictures of or inside sensitive locations as determined by the contracting officer representative. It shall be the responsibility of the contractor to safeguard all documents provided.

Documents shall be stored away from view when not being used. Documents that are no longer needed shall be shredded in an approved government shredder.

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY REFERENCE

52.211-10 Commencement, Prosecution, and Completion of Work APR 1984

Section G - Contract Administration Data

Section K - Representations, Certifications and Other Statements of Offerors

CLAUSES INCORPORATED BY FULL TEXT

5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS

(a) SUBCONTRACTING:

If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.

(b) AFFILIATED OFFERORS:

(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.

(2) Each offeror shall furnish, below, the following information:

(i) Whether the offeror has any affiliates;

(ii) The names and addresses of all affiliates of the offeror; and

(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.

AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)

(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):

Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.

(d) STANDARDS OF CONDUCT CERTIFICATION:

This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.

(i) Name ______________________________________________ Former rank/grade ____________________________________

Last US Government position ___________________________

(ii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________

(iii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________

Firm ____________________________________________________ Name _____________________________________________________ Signature __________________________________________________

Title _____________________________________________________ Date of Execution ____________________________________________

(e) TAXES:

(1) References:

(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."

(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.

(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.

(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.

(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

This item will be imported specifically for this contract? Yes _____ No _____

(ii) Special Excise Tax:

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

Name of item manufacturer

(iii) Value Added Tax (VAT):

Input VAT on materials purchased for this contract. 10% _____ Input VAT on transportation leased/rented for this contract.10% _____ Input VAT on equipment leased/rented for this contract. 10% _____ Input VAT on services purchased for this contract. 10% _____ Output VAT on total contract amount. 10% _____

(iv) Special Excise (Petroleum) Tax:

No. of U/P Liters w/o Tax Tax/Unit Total Tax Amount Regular Gasoline ________ (L) ________ w________ w_____________ Premium Gasoline ________ (L) ________ w________ w_____________ Diesel ________ (L) ________ w________ w_____________ Other ________ (L) ________ w________ w_____________

(v) Education Tax.

(3) Name of the oil company from which POL products will be purchased:

Oil Company: _________________________________________ (Name only)

(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.

Signed (Chop)

(f) CERTIFICATIONS AND REPRESENTATIONS

By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation.

The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.

Section L - Instructions, Conditions and Notices to Bidders

CLAUSES INCORPORATED BY FULL TEXT

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for—

2 May 2019 at 0930

(c) Participants will meet at –

Morin Gate, Osan AB

(End of provision)

5152.236-4011 CONSTRUCTION PRICE RANGE

Pursuant to FAR 36.204 the estimated price range is between $ 100,000 and $250,000