A21_W90VN6-19-Q-0026-00001.pdf
PDF 1 MB Posted
- Solicitation number
- W90VN619Q0026
About this file
The purpose of this amendment is to revise PWS and Attachment in accordance with questions f rom vendor and to answer to the questions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A21_W90VN6-19-Q-0026.pdf | ||
| A21_Attachment.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W90VN619Q0026
F3J3CG9218AW01-1
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
A. The purpose of this amendment is to revise PWS and Attachment in accordance w ith questions from vendor and to answ er to the questions.
B. The closing date/time is extended to from 19 Sep 2019 1400hrs to 20 Sep 2019, 1500hrs.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 27
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Sep-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W90VN619Q0026
X 9B. DATED (SEE ITEM 11)
02-Sep-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Sep-2019
CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCO OSAN, UNIT #2039
APO AP 96278-2039
UNITED STATES
W90VN6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
Osan AB, Republic of Korea
Page | 2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS AND ANSWERS
Questions and Answers
1. On the page 17 tables, MH98-06 ~ BD1185 needs 5 lines (2 lines + 3 lines) x 4" PVC Conduit. Is that correct?
: No, 2 or 3 X 4” PVC ducts need to be installed. See the 2.2.2.14.1.1 Duct-bank/Inner-duct Infrastructure.
2. There is no regulation for installing inner ducts. Please provide us diameter, hydrothermal, etc., and more information.(4 1 in inner ducts per 1 4 inch)
: See the page “2.2.2.13.1 Composition”, We prefer the fabric type innerduct(Maxcell or equivalent) and put 3 x 3Cell fabric innerduct in one empty duct.
3. On the page 17 tables, where do we install NEMA 4X Pull Box?
: It will be installed outside wall of B1185 to install the ducts into inside comm room.
4. For the Construction Period, it says 90days on the page 19. It says 30 days on the page 50. Which one is correct?
: 90 days
5. From BD1185 to BD870, we need information on MH/HH. There is a section which has no captured pictures.
: Please see the updated sketch 1 &2
6. Do we have to install 288 core fiber cables for the whole sections?
: Yes
7. is the Sheet 2 of 3 and 4 of 4 missing on Attachment 1 in PWS. ?
: Please see the updated sketch 1 &2
8. is there no distances on last page from B1185 ITN through MH-870A in PWS ?
Page | 3
: Please see the updated “2.2.2.14.1.1 Duct-bank/Inner-duct Infrastructure” and “2.2.2.14.2 Fiber Optic Cable Installation”
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 19-Sep-2019 02:00 PM to 20-Sep-2019 03:00 PM.
The following have been added by full text:
REVISED PWS AND ATTACHMENTS
Performance Work Statement for
Installation of Fiber Optic Cable B949 to B1185/1185-870
Osan Air Base, Republic of Korea
17 Sep 19
Contents
1.0 SCOPE
2.0 REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.1.1 Safety Requirements
2.1.1.1 Site Coordination
2.1.1.2 Confined Space
2.1.1.3 Accident/Incident Reporting and Investigation
2.1.1.4 Airfield Driving
2.1.1.5 Work Area(s)
2.1.1.5.1 Flightline
2.1.1.6 Traffic control
2.1.2 Environmental Management
2.1.3 Permits
2.1.4 Cultural Resources (If Applicable)
2.1.5 Integrated Process Team (IPT)
2.1.6 Quality Assurance
2.1.7 Contractor Personnel
2.1.7.1 Project Management
Page | 4
2.1.7.2 Site Point of Contact (POC)
2.1.7.3 Personnel Requirements
2.1.8 Warranty
2.1.9 Manuals and Practices
2.1.10 Contractor Manpower Reporting Application (eCMRA)
2.2 SPECIFIC REQUIREMENTS
2.2.1 Site Survey
2.2.2 Outside Plant Requirements
2.2.2.1 Existing Maintenance Holes
2.2.2.2 Measurements
2.2.2.3 Underground Utilities Markings
2.2.2.4 Closures for Cable Splicing in Maintenance Holes
2.2.2.5 Splice Connectors
2.2.2.6 Labeling
2.2.2.7 Shield Bonding Connectors
2.2.2.8 Grounding
2.2.2.9 Cable Tags
2.2.2.10 Cable Terminations
2.2.2.10.1 Backboards
2.2.2.11 FOC Maintenance Loop
2.2.2.12 New Maintenance Holes/Hand-holes
2.2.2.12.1 Cable Racks and Cable Rack Supports
2.2.2.12.2 Grounding
2.2.2.13 Underground Conduit System
2.2.2.13.1 Composition
2.2.2.13.2 Installation
2.2.2.13.3 Bends and Sealing
2.2.2.13.4 Utility Separation
2.2.2.13.5 Spacers and Tracer Wire
2.2.2.13.6 Warning Tape
2.2.2.13.7 Entrance Conduits into Existing Maintenance Holes
2.2.2.13.8 Excavation/Building Penetrations
2.2.2.13.9 Conduit Bends or Sweeps
2.2.2.13.10 Mule Tape
Page | 5
2.2.2.14 Outside Plant Installation
2.2.2.14.1 Infrastructure Installation
2.2.2.14.1.1 Duct-bank/Inner-duct Infrastructure
2.2.2.14.2 Fiber Optic Cable Installation
2.2.3 Project Residue
2.2.4 Site Restoration
2.2.5 Service Outages
2.2.6 Configuration Management. N/A
2.2.7 Identification/Marking
2.2.8 Installation Schedules
2.2.9 Weekly Status Reports
2.2.10 Drawings
Page | 6
2.2.10.1 As-Built Drawings
2.2.10.2 Butterfly Drawings
2.2.10.3 Geospatial Deliverables
2.2.11 Test and Acceptance/Installation Test Plan
2.2.11.1 Testing
2.2.11.2 In-progress Testing
2.2.11.2.1 Excavations
2.2.11.2.2 Splices
2.2.11.2.3 Fiber Optic Tests
2.2.11.2.4 Optical Attenuation
2.2.11.2.5 Distance
2.2.12 Acceptance/Installation Test Report
2.2.13 Final Acceptance
2.2.14 Training Plan. N/A
3.0 GENERAL INFORMATION
3.1 Period of Performance
3.2 Place of Performance
3.3 Hours of Operation
3.4 Holidays/Down Days
3.5 Base Support
4.0 APPENDICES
4.1 Appendix A. APPLICABLE STANDARDS
4.2 Appendix B. LIST OF DELIVERABLES
5.0 Attachment 1. Proposed Fiber Route
Page | 7
1.0 SCOPE.
This Performance Work Statement (PWS) defines the requirements for the Contractor to engineer, furnish, install and test (EFI&T) new 2-way, 4” manhole/duct-bank infrastructure and 288 strands of single mode fiber optic cable from B949 to Critical Node (CN) B1185 then from (CN) B1185 to (CN) B870 at Osan Air Base, Republic of Korea.
2.0 REQUIREMENTS.
This requirement requires a minor adjustment for B1185 fiber expansion which will allow redundant CN support and eliminate the bottleneck bandwidth currently supported from this CN.
Currently the CN at B1185 supports 31 buildings and over 1400 (1488) users and is unable to support the CDNs and CANs that rely on the CN residing at B1185 due to saturation of current
OSP.
ITN Fiber Expansion B1185 – 870 3Q2019 1 Gig pipe coming in and out
31 Buildings
1400 + users
2.00 Mbps Download Speed mean (3 tests)
1.19 Mbps Upload Speed mean (3 tests)
213 Ms Ping Speed Average (3 tests)
If ½ of the users are logged in at one time and are utilizing the internet and downloading an attachment or opening up a webpage or new tab, they would surpass the existing infrastructure’s backbone capacity by 400 Mbps (or 400%) resulting in a perceived “throttled” internet connection and degraded connectivity impacting their mission.
2.1 GENERAL REQUIREMENTS.
2.1.1 Safety Requirements.
The contractor shall remain in compliance with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.
2.1.1.1 Site Coordination.
The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.
2.1.1.2 Confined Space.
The Contractors and Sub-contractors entering spaces on Osan AB are responsible for the safety of their personnel and for their own permit space program as outlined in AFI 91-203. All confined space operations must be coordinated with the Base Safety Office prior to start of work. The contractor shall allow 5 work days for initial coordination. The primary Contractor is responsible for all Sub-contractor confined space operations.
Page | 8
2.1.1.3 Accident/Incident Reporting and Investigation.
The Contractor shall record and report all available facts relating to each instance of injury to either
Contractor or Government personnel to the 51 CS/SCX Project Manager and the Base Safety
Office unless otherwise stated in the PWS. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the
Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
2.1.1.4 Airfield Driving.
Any person operating a motor vehicle inside the airfield fence on Osan shall attend airfield driving familiarization training. The contractor shall coordinate with the 51 CS/SCX and the 51
OSS/OSAA to obtain the required training.
2.1.1.5 Work Area(s).
At day’s end, the Contractor shall remove all debris and surplus materials from the work place.
Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the work day. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard. The contractor shall ensure that any locking manhole covers are put back in place at the end of each workday.
2.1.1.5.1 Flightline.
In the event of a need to have a safety barrier in/around the flight line, the contractor shall coordinate with Airfield Management for approval. In addition, if approved, these items will need to be weighed-down/secured to avoid causing a FOD hazard. All FOD (screws, trash, etc) shall be controlled/secured until properly disposed of.
2.1.1.6 Traffic control.
In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall notify the 51 CS/SCX PM NLT 10 calendar days in advance to inform base
Security Forces and Emergency Services personnel of the planned disruptions.
2.1.2 Security Requirements.
The Contractor shall process and provide a Site Visit Request Letter to 51 CS/SCX within 5 calendar days after contract award. This letter shall identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this PWS. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All
Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.
2.1.3 Environmental Management.
The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations; and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The Contractors are responsible to know
Page | 9 and follow all applicable Federal, State, Local and Air Force regulations for environmental protection, including waste disposal, sewer discharge, air emissions, and storm water requirements. The contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Osan AB. The Prime Contractor shall ensure that their sub-contractors (if any) comply with these specifications.
2.1.4 Permits.
The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation. For example:
Digging permit, AF Form 103 shall be submitted through Base Civil Engineering
(BCE) 14 calendar days in advance of digging activities.
Confine space entry permit, AF Form 1024 shall be coordinated through base safety office. The Contractor shall be prepared to provide proof of their Confined Space
Training Program along with the AF Form 1024 to base safety.
BCE Work Clearance Request, AF Form 332 shall be drafted upon the approval of the installation plan. Submit the drafted AF Form 332 to 51 CS/SCX Project Manager at least 21 calendar days in advance of the construction activities. BCE must complete coordination of the 332 before installation can begin.
2.1.5 Integrated Process Team (IPT).
The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the
Government Contracting Officer (CO), the CSI-B, the System Engineer (if any), the 38 ES Project
Manager (if any), the 51 CS Project Manager, and other base personnel as required. The Contractor shall provide an agenda and a worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute in accordance with (CDRL A004).
2.1.6 Quality Assurance.
The Contractor shall provide Quality Assurance Support for the entire life of the project. The
Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) shall be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them (CDRL A003). Government personnel reserve the right to perform inspections of the Contractor’s work during any and all phases of the installation.
2.1.7 Contractor Personnel.
2.1.7.1 Project Management.
The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.
Page | 10
2.1.7.2 Site Point of Contact (POC).
The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours for the duration of the project, up to and until final acceptance by the
Government PM and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.
2.1.7.3 Personnel Requirements.
The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English and shall be on site to coordinate permits, clearances, and receive shipments/material related to the task order.
2.1.8 Warranty.
The Contractor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one year workmanship warranty. The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.
2.1.9 Manuals and Practices.
The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment.
2.1.10 Contractor Manpower Reporting Application (eCMRA).
The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site.
The contractor is required to completely fill in all required data fields using the following web address http://www.ecmra.mil.
Reporting inputs will be for the labor executed during the period of performance during each
Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the ECMRA help desk.
2.2 SPECIFIC REQUIREMENTS.
This section describes the underground cables, inner-ducts and MH conduit system installation requirements. The Contractor shall design and install Customer-Owned Outside Plant
Telecommunications Infrastructure in according with ANSI/TIA-758-A. Each cable installation shall be coordinated with the 51 CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion. See Attachment 1, Sketch 1, 2 & 3 for reference and estimated distances of existing and proposed infrastructure and cables routes. This is only a proposed solution. The Contractor is free to make any recommendations pertaining to the accomplishment of this requirement in their proposal.
The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, http://www.ecmra.mil/
Page | 11 supervision, management, and other incidentals necessary to meet the requirements as stated in this PWS. The Contractor shall comply with the current ANSI/TIA telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided shall be new and not refurbished.
2.2.1 Site Survey.
The contractor may utilize Cyberspace Infrastructure Planning System (CIPS) Visualization
Component (CVC) to perform a desktop survey to estimate Fiber distances, duct availability, and new MHDS required. These findings must be verified through a site survey prior to installation. A snapshot of CVC’s current facility and MHDS layout is provided in Attachment 1, Sketch 1 & 2.
2.2.2 Outside Plant Requirements.
As indicated in this PWS and attached sketches, the Contractor shall EFI&T the 288 strands single mode fiber optic cable and additional 4” duct system infrastructure required from ITN 949 to ITN
1185 then ITN 1185 to ITN 870.
2.2.2.1 Existing Maintenance Holes.
The Contractor shall pump out water as required into the storm drain system. Water may be drained through the pavement or grass area where a storm drain is not available. If necessary, the Contractor shall be responsible for removing mud, debris, etc. from maintenance holes/hand-holes to the extent necessary for the Contractor to perform work in the space. All mud, debris, etc. that is removed shall be disposed of off-base in accordance with 51CE guidance.
2.2.2.2 Measurements.
Any distances provided in this PWS or obtained through CVC are approximations and should NOT be used for ordering materials or determining duct lengths. Material purchasing will be determined by actual field survey.
2.2.2.3 Underground Utilities Markings.
The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or horizontal directional boring and shall take precautions to protect existing infrastructure. The Contractor is responsible for repair of any damage caused during installation when the infrastructure is clearly marked. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 (Dig Permit) remains current.
2.2.2.4 Closures for Cable Splicing in Maintenance Holes.
Intermediate cable splices shall be minimized and consist of fusion splices in a high quality re-enterable splice case. Only splice closures intended for underground applications shall be used in the underground system. The Contractor shall use standard re-enterable fiber splice closures. The closures shall have adequate strength to protect the splice and maintain cable shield electrical continuity in the below ground environment. The Government quality inspector shall have the opportunity to inspect the inside of the splice case before closure pressure testing and encapsulation is performed.
2.2.2.5 Splice Connectors.
Page | 12
All fiber splicing shall be performed in accordance with RUS Bulletin 1735F-401, Standards for
Splicing Copper and Fiber Cable. The fusion splice method shall be used for fiber optic cable.
2.2.2.6 Labeling.
The Contractor shall label all equipment and cables they install and cables identified for re-use in accordance with ANSI/TIA-606-A-2002 and as directed by the 51CS/SCXP. New ducts shall be permanently labeled on the wall of each building/manhole indicating the connecting building/maintenance hole at the other end of the duct (for example, “To MH-200”). The cover of all new fiber optic distributions (FODPs) shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the FODP manufacturer has not identified the sequence in which the ports are counted, the Contractor shall provide designation labels/strips to identify the sequence in which the ports are counted.
FODP Label Example: FODP 1622
FO B949-B1185, 1-12
Note: The same information shall appear on the Contractor’s completed As-Built-Drawings.
2.2.2.7 Shield Bonding Connectors.
If new installed cable is copper cable, shield bonding connectors, bond bars, braids, ribbons, clamps, etc., shall be provided to maintain cable shield continuity at splices and at ground connections. Bonding connectors shall be provided IAW RUS Bulletin 345-65 (PE-33). Cable shields shall be bonded and continuous throughout the cable distribution system.
2.2.2.8 Grounding.
If new installed cable is copper cable, The contractor shall ground new cable shields to the
Telecommunication Main Ground Bus-Bar (TMGB), in or near the new service entrance box located on the outside of each building. The contractor is required to provide one 6’’ x 4’’ copper ground bar and ground it to the existing ground point in accordance with ANSI/TIA-607B, Generic
Telecommunications Bonding and Grounding (Earthing) for Customer Premise, unless a TMGB already exists.
2.2.2.9 Cable Tags.
All tags shall be permanently labeled, easily visible and corrosion resistant. Install cable tags in all maintenance holes/hand-holes, cable vaults, pull boxes and building entrance terminal locations.
When cables pass through a maintenance-hole, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. Tagging and labeling of new cables shall be IAW the following:
A288L8.3F
FO B699-B871, 1-12
FO B699-B872, 13-24
FO B699-HH21, 25-288 Dark
Page | 13
Line One: A = Armored Sheath (otherwise leave blank) 288 = Fiber Count. L = Loose Tube
Buffer or (T) Tight Tube Buffer. 8.3 = Single Mode. F = Filled core (otherwise leave blank).
Lines Two, Three, Four: 699-871 = From-To Building numbers. 1-12 = Cable/strand Count.
2.2.2.10 Cable Terminations.
Newly installed fiber optic cables shall be terminated on new fiber optic distribution panels using fusion spliced pigtails with LC connectors or LC fusion splice direct connectors.
2.2.2.10.1 Backboards.
Newly installed backboards shall be AF-standard 0.75”-thick plywood, with two coats of white, fire-resistant paint.
2.2.2.11 FOC Maintenance Loop.
The Contractor shall install a minimum of a 50 foot fiber optic cable maintenance loop at the first
MH from the building, at each splice point MH location and at every third manhole. The maintenance loop shall be properly labeled and securely supported by two cable hooks. Cable hooks are to be positioned so the highest one supports the underside of the top of the coil and the bottom hook supports the underside of the bottom of the coil.
2.2.2.12 New Maintenance Holes/Hand-holes.
Maintenance holes installed under this Task Order shall have an American Association of State
Highway and Transportation Officials (AASHTO) rating of H-20 or equivalent. Unless otherwise stated, HHs shall have a minimum interior dimension of 4’W x 4’L x 4’H or 3’W x 5’L x 4’H.
HHs shall be furnished with cable racks and a grounding system. It is understood that some
Maintenance Holes are precast with bonding ribbons or some similar connection, to the manhole rebar and therefore do not require a ground rod. This method of grounding in lieu of a ground rod is satisfactory just as long as the achieved impedance to ground is twenty five (25) ohms or less.
HHs shall meet the requirements of TIA -758B, paragraph 5.2.2. Prefabricated HHs are preferred.
HH shall be installed so that they are reasonably level on a gravel bed of 6 inches to allow drainage of water from the walls. The gravel bed should extend 8 inches to 12 inches beyond the outer edges of the MH/HH. MH/HH covers shall be labeled with 1/8” raised letters stating
“COMMUNICATIONS”.
2.2.2.12.1 Cable Racks and Cable Rack Supports.
Cable racks shall be installed in maintenance holes as required. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case. Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips. All cables shall be supported using racking clips, cable racks, and cable hooks.
2.2.2.12.2 Grounding.
Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc.
necessary to properly bond/ground the cable in MHs/HHs shall be provided.
2.2.2.13 Underground Conduit System.
Page | 14
The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Provide a minimum of 12" cover of clean fill above the conduit. Backfill material shall be clean and free from all organic material, clay, marl or unstable materials, debris, lumps, or broken paving. No rocks or stones larger than 3 inches in diameter shall be allowed in backfill. Material for backfill may be material resulting from excavation, if it meets the above requirements. Directional drilling will be used for major road crossings. Otherwise, crossing of paved surfaces may be performed by pavement cuts and resurfacing with appropriate matching road material. This does not prevent the Contractor from using directional drilling if it is more cost effective. Ducts will be appropriately protected when placed under paved surfaces.
2.2.2.13.1 Composition.
The ducts shall be corrosion resistant and 4-inch inside diameter (I.D.) round or metric equivalent.
The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2;
or EPC-80-PVC (Schedule 80) IAW NEMA TC-2; or high density polyethylene (HDPE) SIDR
13.5 Schedule 80 PVC shall be limited to risers all above ground conduit and under the roadway/parking pavement. High density polyethylene (HDPE) SIDR 13.5 shall be used when directional boring is used. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell end type coupling and shall be watertight when assembled.
Flexible fabric innerduct(Maxcell or equivalent) will be used for base communication duct system to enables it to take the shape of the cables, allowing more cables to be placed within a conduit. If fabric innerduct will be installed on new duct system, 3 X 3Cell must be installed in one duct space.
2.2.2.13.2 Installation.
Installation of underground conduits/ducts shall be IAW RUS Bulletin 1751F-643 and RUS
Bulletin 1753F-151. All ducts not installed across roads, sidewalks, parking areas, or areas to be paved, etc. shall have a minimum of 36 inches ground cover, where possible. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. shall be installed with protective measures such as concrete incase, and etc. All ducts installed beneath airfield paved surfaces shall be installed by means of horizontal directional boring beneath the paved surface so as not to damage the existing pavement, unless not physically possible due to geographical or man-made obstructions.
2.2.2.13.3 Bends and Sealing.
All bends between MHs shall be a minimum 40-foot radius with the sum of bends in all directions not exceeding a total of 90 degrees. Ducts shall have bell ends and enter a MH perpendicular to the surface of the wall through which it is entering. All ducts/inner-ducts entering MH shall be sealed. Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a rigid test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit shall be pulled through two diagonally opposite ducts to ensure proper alignment. In addition, all ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc.
Page | 15
2.2.2.13.4 Utility Separation.
When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.
2.2.2.13.5 Spacers and Tracer Wire.
Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at an interval of four (4) spacers per 20 feet. At least one duct or roll pipe shall have tracer wire or be otherwise locatable from the surface.
2.2.2.13.6 Warning Tape.
Cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route.
The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message.
2.2.2.13.7 Entrance Conduits into Existing Maintenance Holes.
When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if knockout doesn’t exist. Penetration shall not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts will be a minimum of 18 inches from either the maintenance hole floor or ceiling, if practical.
The minimum bending radius for entry conduit/ducts shall be no less than 10 times the inside diameter of the conduit. Ducts and openings around ducts shall be sealed to prevent moisture from entering the maintenance holes.
2.2.2.13.8 Excavation/Building Penetrations.
All wall penetrations, including inside buildings, shall be restored to meet required base fire ratings.
2.2.2.13.9 Conduit Bends or Sweeps.
Where a bend or sweep is placed in PVC nonmetallic duct bank between maintenance holes, the duct bank must be encased in concrete with a minimum compressive strength of 17,225 kilopascal
(kPa) [2500 pounds per square inch (psi)].
2.2.2.13.10 Mule Tape.
All new vacant ducts shall be provided with a waterproof corrosion resistant mule tape for future cable installation. The mule tape shall extend into the MH and be secured to the cable rack or pulling iron, etc.
2.2.2.14 Outside Plant Installation.
See Attachment 1, Project Sketches for reference and estimated distances of existing and proposed infrastructure requirements.
The Contractor shall install underground outside plant infrastructure as described below.
This is only a proposed solution. The Contractor is free to make any recommendations pertaining
Page | 16 to the accomplishment of this requirement in their proposal and the sequence of installation is at the Contractor’s discretion.
Install FODPs in the communications rooms in B1185 (2), B949 (1) and B870 (1) to receive each 288- stand FOCs.
Use existing vacant innerduct or Geotextile Innerduct to install new cable.
If no innerducts are available, use existing vacant duct to install new Innerducts/geotextile and FOC.
If no ducts are available, install the new ducts, Innerducts/geotextile and FOC.
For more detailed installation route, refer to the map diagram sketches under attachment 1.
2.2.2.14.1 Infrastructure Installation.
Install the following new infrastructure. All new locations and distances are approximate. (See
Sketches 1- 3)
Page | 15
2.2.2.14.1.1 Duct-bank/Inner-duct Infrastructure
Install the following 4” PVC duct-banks
From Location To Location New Duct
Quantity
New Innerduct Distance
(Feet)
Sketch Comment
B1185 MH98-06 2 3 X 3Cell in one duct
250’ 1&2 Install NEMA
4X pull box.
MH98-8 MH98-9 3 X 3Cell in one duct
410’ 1&2
MH98-9 MH98-10 3 X 3Cell in one duct
320’ 1&2
MH98-11 MH98-12 3 X 3Cell in one duct
360’ 1&2
MH98-11 MH1101 3 3 X 3Cell in one duct
230’ 1&2 Concrete
Incase required
MH1121 MH1122 3 3 X 3Cell in one duct
280’ 1&2
MH1122 MH1119 3 3 X 3Cell in one duct
50’ 1&2 Concrete
Incase required
MH1119 MH1118 3 3 X 3Cell in one duct
125’ 1&2
MH1118 MH1117A 3 3 X 3Cell in one duct
130’ 1&2
MH1117A HH1117 3 3 X 3Cell in one duct
65’ 1&2
HH1117 MH1116 3 3 X 3Cell in one duct
60’ 1&2 Concrete
Incase required
HH1116 HH1142 3 X 3Cell in one duct
450’ 1&2
HH1142 MH894B 3 X 3Cell in one duct
230’ 1&2
Page | 16
2.2.2.14.2 Fiber Optic Cable Installation.
All fiber optic cables shall be installed in new ducts.
Install the Following Single Mode Fiber Optic Cables.
From To Via Maintenance
Holes / Handholes
Stra nd
Cou nt
Appr ox.
Dista nce
(Feet
Sketc h
Comment
B1185 B870 B1185, MH98-6,
MH98-7, MH98-8,
MH98-9, MH98-10,
MH98-11, HH1101,
HH1121, MH1122,
HH1119, HH1118,
HH1117A, HH1117,
MH1116, HH1116,
HH1142, MH894B,
MH870A, MH870B,
B870
288 4,005’ 1 & 2 In B1185 and B870 ITN, terminate the new 288 strands fiber optic cable on a new Fiber
Optic Distribution Panel (FODP) using fusion splice pigtails with
LC connectors. Mount the
FODP in an existing equipment rack/cabinet.
B949 B1185 B949, MH85A,
MH98-13, MH98-12,
MH98-11, MH98-10,
MH98-9, MH98-8,
MH98-7, MH98-6,
B1185
288 3,120’ 1 & 2 In B949 and B1185 ITN, terminate the new 288 strands fiber optic cable on a new Fiber
Optic Distribution Panel (FODP) using fusion splice pigtails with
LC connectors. Mount the
FODP in an existing equipment rack/cabinet.
Page | 17
2.2.3 Project Residue.
All residues from this project shall be disposed of off base and in accordance with Federal, State, local and base environmental laws and regulations. All residue produced by horizontal directional boring operations (i.e., slurry) shall be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal and state environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on Osan AB.
2.2.4 Site Restoration.
The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. The Contractor shall comply with all base grounds restoration requirements. Common use areas shall be restored with sod.
2.2.5 Service Outages.
The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).
2.2.6 Configuration Management. N/A
2.2.7 Identification/Marking.
The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign (minimum
8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the
Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers.
2.2.8 Installation Schedules.
The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system IAW CDRL A002.
2.2.9 Weekly Status Reports.
The Contractor shall prepare a Weekly Status Report and distribute IAW CDRL A003. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.
2.2.10 Drawings.
2.2.10.1 As-Built Drawings.
The Contractor shall submit red line drawings showing the “as-built” configuration in format specified by 51CS/SCX project manager. The 51CS/SCX will provide baseline drawings. The
Page | 18
Contractor shall provide As-Built Rack Elevation, Inside Cable Plant and Outside Cable Plant drawings and distribute IAW CDRL A001.
2.2.10.2 Butterfly Drawings.
The Contractor shall record and submit butterfly, cable path and building penetration drawing information for all new installations including butterfly drawings for all Maintenance Holes, hand-hole and pull-boxes that contain new or reused FOC. Drawings shall record the path and arrangement of new and reused fiber optic cables, splices, and the arrangement duct-banks, ducts, and inner-duct. Drawings shall be submitted in an easily read electronic format such as pdf. Scanned data sheets or legible sketches are acceptable if the listed information is provided IAW CDRL A001.
2.2.10.3 Geospatial Deliverables.
The Contractor shall collect and record geospatial data and provide as-built documentation (shape files) of all new installed MHDS components and new cable components (including metadata) compatible with the Cyberspace Infrastructure Planning System (CIPS) Visualization Component
(CVC) drawing system. Data points shall be recorded at the center of each manhole/hand hole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points shall be recorded to capture any change in direction along the route. The government will review the shape files in
CVC and transcribe the information to the CVC system. Shape files shall be delivered within 30 days of project completion IAW CDRL A001.
2.2.11 Test and Acceptance/Installation Test Plan.
The Contractor shall provide a test plan as to how the system shall be pre-tested, in-progress-tested and post-tested to demonstrate to the Government that the system is fully operational and meets or exceeds the specified requirements and that the system is fully ready to be placed into service
(CDRL A005). The Contractor shall test the system to demonstrate to the Government quality assurance evaluation of the system. These tests shall be accomplished prior to the system being placed into service.
2.2.11.1 Testing.
The Contractor shall conduct on-site testing IAW OEM’s installation manuals, practices and the appropriate vendor’s test procedures. The Contractor shall furnish all test equipment and personnel required to conduct all required testing. During any testing phase, the Government reserves the right to perform any of the contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing. The Contractor shall participate with the Government in testing the complete communications system. When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment will be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction. After appropriate corrective action has been taken, all tests including those previously completed, related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance. The contractor will provide tests of data loss within 10 calendar days of acceptance.
Page | 19
2.2.11.2 In-progress Testing.
2.2.11.2.1 Excavations.
All excavations shall be inspected for compliance with applicable installation and safety directives, and installation plan procedures. After material is placed, the contractor shall inspect and document the installation prior to backfilling.
The backfill task shall be coordinated with the 51 CS/SCX Project Manager 24 hours prior for each backfill. In addition, the designated government representative shall be allowed to inspect the installation prior to backfilling.
2.2.11.2.2 Splices.
All splices shall be tested for cable faults and splicing errors as they are completed. All cable faults and/or splicing errors detected shall be corrected after the completion of each splice point test and prior to sealing the closure. The contractor's QCM and the designated government representative shall inspect all splices prior to sealing the closure.
If, for any reason, moisture contaminates a splice, all modules and/or connectors shall be replaced and the entire splice retested.
2.2.11.2.3 Fiber Optic Tests.
All strands of all fiber optic cables shall be tested in accordance with TIA 526-7-(2002) Measurement of Optical
Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent. As a minimum, the following tests shall be performed. Both Optical Time Domain Reflectometer (OTDR) and Optical Power Meter tests will be used for all end-to-end circuits. For incomplete circuits that end in Maintenance Holes, only OTDR testing is required.
2.2.11.2.4 Optical Attenuation.
End to end attenuation tests shall be conducted on all fiber optic cable strands. Tests shall be accomplished to ensure the installed cable is within the specified parameters.
2.2.11.2.5 Distance.
Test to determine the installed cable length between optical patch panels. All strands of all fiber optic cables shall be tested.
2.2.12 Acceptance/Installation Test Report.
The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan IAW CDRL A006.
2.2.13 Final Acceptance.
The Contractor shall schedule a final project walk-through with the Base POC. This should be scheduled 5 calendar days prior to acceptance. AFTO 747, Cyberspace Infrastructure System
Acceptance will be certified by signature on block 12.a prior to acceptance
2.2.14 Training Plan. N/A
3.0 GENERAL INFORMATION.
3.1 Period of Performance.
The period of performance, completion of project shall be three (3) months after the start date for a total of 90 days.
Page | 20
3.2 Place of Performance.
The place of performance is Osan AB, Republic of Korea.
3.3 Hours of Operation.
The Contractor shall routinely work during normal duty hours of the site between the hours of
0730-1630. However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the 51
CS/SCX PM at least 10 calendar days in advance.
3.4 Holidays/Down Days.
The Contractor shall not perform under this contract on federal holidays or site-unique down-days unless expressly authorized by the CO and coordinated with the base POC.
3.5 Base Support.
The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project in their proposal. The contractor shall return all government furnished lay-down and storage areas to their original condition upon completion of the project.
Page | 21
4.0 APPENDICES.
4.1 Appendix A. APPLICABLE STANDARDS.
The following list is not all-exclusive. The Contractor shall comply with applicable commercial code and standards
AFI 91-203 – Air Force Consolidated Occupational Safety Instruction
OSHA CFR 29 Part 1910-268 – Telecommunications
NEMA TC 2- Electrical Polyvinyl Chloride (PVC) Tubing and Conduit
ANSI/TIA-606-B Administration Standard for Telecommunications Infrastructure
ANSI/ TIA-568-C Commercial Building Telecommunications (568C.1, 568C.2, 568C.3)
Cabling Standard
ANSI/TIA-607-B Commercial Building Grounding (Earthing) and Bonding Requirements for
Telecommunications
TIA-526-7- Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant
TIA-569-B - Commercial Building Standard for Telecommunications Pathways and Spaces
TIA-570-B –Residential Telecommunications Infrastructure Standard
TIA-758 Customer-owned Outside Plant Telecommunication Infrastructure Standard
BICSI TDM Manual - Building Industries Consulting Services International
Telecommunications Distribution Methods (TDM) Manual
BICSI – Outside Plan Design Reference Manual
RUS Bulletin 345-65 (PE-33) – Specification for Shield Bonding Connectors
RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable
RUS Bulletin 1751F-643 - Underground Plant Design
RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications Engineering
Shield Continuity and Construction Manual (TE&CM) 451.2
RUS Bulletin 1751F-801 – Electrical Protection Fundamentals
RUS Bulletin 1753F-151 (515b) - Specifications and Drawings for Underground Cable
Installation
RUS Bulletin 1753F-201 (PC-4) – RUS Standard for Acceptance Tests and Measurements of
Telecommunications Plant
RUS Bulletin 1753F-207 (PE-87) – REA Specification for Terminating Cables
NFPA 70 - National Electric Code
FGDC-STD-007.3-1998 - Geospatial Positioning Accuracy Standards Part 3: National Standard for Spatial Data Accuracy
Unified Facilities Criteria 3-260-01
Page | 22
4.2 Appendix B. LIST OF DELIVERABLES.
All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this PWS. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The
Contractor shall submit the following deliverables:
CDRL Data Item Title Data Item Title
A001 As Built DI-DRPR-80151A/T
A002 Work Schedule DI-MISC-81382/T
A003 Status Report DI-MGMT-80368A
A004 Meeting Minutes DI-ADMIN-81505/T
A005 Test Plan DI-NDTI-80566A/T
A006 Test Report DI-QCIC-80512
4.3 ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
4.3.1 Access and General Protection/Security Policy and Procedures:
This standard language text is for contractor employees with an area of performance within an
Army controlled installation, facility, or area. The contractor and all associated sub-contractors’ employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshall
Office, Director of Emergency Services, or Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
4.3.2 For contractors that do not require CAC, but require access to a DoD facility or installation.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index
(NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
Page | 23
4.4 ADMINISTRATIVE CONSIDERATIONS
4.4.1 Points of Contact:
Primary POC: TSgt Patrick White
Project Manager
51 CS/SCXP
Bldg 949, Room 203
011-82-31-661-5520
Osan AB, Pyeongtaek city Republic…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.