This document is a Contract Data Requirements List (CDRL) outlining test and inspection reporting requirements for a transparent armor First Article Test (FAT). The FAT must be completed within 45 days of award according to the attached Statement of Work (SOW). The contractor must submit a FAT Report to the Procuring Contracting Officer (PCO) within 10 days of completing the FAT, and the government requires 30 days for review. FAT approval is required before production can begin. Production delivery is to start 60 days after FAT approval. The report is to be provided under Contract W9098S20Q0009 for transparent window armor issued by the Department of the Army Materiel Command Contracting Command Rock Island Arsenal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1423-1 FEB 2001

PREVIOUS EDITIONS MAY BE USED. Page 8 of 14 Pages

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for information Operations and reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project, (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER X

D. SYSTEM/ITEM

M915A5 B-KIT

E. CONTRACT / PR NO. F. CONTRACTOR

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

TEST/INSPECTION REPORT

3. SUBTITLE

FIRST ARTICLE TEST REPORT

4. AUTHORITY (Data Acquisition Documentation No.)

DI-NDTI-80809B

5. CONTRACT REFERENCE

SECTION E

6. REQUIRING OFFICE

AMSJM-QAP

7. DD 250 REQ.

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ONE/R

12. DATE OF FIRST SUBMISSION

ASREQ

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION

ASREQ

Draft

Final Reg Repro

PCO

0 1

16. REMARKS:

The First Article Test (FAT) shall be completed within 45 days from award.

The FAT shall be conducted in accordance with Attachment 002 Statement of Work (SOW).

The FAT Report shall be submitted to the PCO within 10 days after completion of FAT. The Government requires 30 days for review. Disposition of the FAT Report will be provided through the PCO. FAT must be approved prior to production.

Delivery for production shall begin 60 days from FAT approval.