ATTACHEMENT_002_QASP.docx
DOCX document 16 KB Posted
- Attached to
- INDUCTION HARDENING
- Solicitation number
- W9098S-15-T-0226
About this file
ATTACHMENT 002 - QASP
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATTACHMENT_001_SOW_8_OCT_2015.docx | DOCX document | |
| 15-T-0226-0002.pdf | ||
| 15-T-0226-0001.pdf | ||
| ADDITIONAL_DRAWINGS_15-T-0226.pdf | ||
| ATTACHMENT_001_SOW.docx | DOCX document | |
| DRAWINGS_15_T_0226.pdf | ||
| W9098S-15-T-0226.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP) Induction Harden P/N‘s 7070851 and 7070704
1. CONTRACT REQUIREMENT:
The contractor will induction harden the areas called out on drawings 7070851 and 7070704 and meet all specifications listed on said drawings. An initial Test Part will be provided by the Government to validate the contractor’s process adheres to all requirements prior to releasing the contractor for production. The Test Part will be tested at a certified government laboratory for all requirements noted herein.
2. PRIMARY METHOD OF SURVEILLANCE:
The contractor’s performance will be inspected by TARA-QA personnel to ensure all requirements are followed IAW QASP. Specific instructions are outline below.
3. ANALYSIS OF RESULTS:
Inspection will be performed before parts are received. The Government will not accept hardened parts with cracks, or out of round conditions exceeding 0.040”.
| Service |
| Standards |
| Success |
| Method of Surveillance |
| Contractor will manage the contract in accordance drawing # 7070851 |
| 7070851 Rev J, Note 3 |
MIL-M-11472 or Dye Penetrate Inspect, MIL-1-6866.
| 100% |
| QA inspection and COC and CTR. The CTR will include Rockwell results, Magnetic Particle or Dye Penetrant test results. |
| Contractor will manage the contract in accordance drawing # 7070704 |
| 7070704 Rev G, Note 5 |
MIL-M-11472 or Dye Penetrate Inspect, MIL-1-6866.
| 100% |
| QA inspection and COC and CTR. The CTR will include Rockwell results, Magnetic Particle or Dye Penetrant test results. |