MISTE_Pre-Solicitation_Conferences_Industry_Questions_and_Government_Res.docx
DOCX document 21 KB Posted
- Solicitation number
- W900KK-19-R-0006
About this file
This document contains details from a pre-solicitation conference for the Modernizing Instrumentation Solutions for Test and Evaluation (MISTE) contract opportunity. The conference provided responses to industry questions regarding requirements for two initial delivery orders. The first delivery order is for the System-of-Systems Controlled Environment Test Infrastructure (SCETI) project to develop snow, fog, and atmospheric measurement capabilities at Redstone Test Center on a firm fixed price basis. The second delivery order is for the Test Network Modernization (TNM) project to modernize the test network at Electronic Proving Ground in Fort Huachuca, Arizona on a cost plus fixed fee basis. Both delivery orders are expected to be awarded at the time of the MISTE contract award, with responses to the draft request for proposal due by December 3, 2018 and the solicitation planned for release in the second quarter of fiscal year 2019.
Responses to Pre Solicitation Conference questions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MISTE Pre-Solicitation Conference held 10 December 2018 The below are questions from industry, and the responses issued by the Government during the MISTE Pre-Solicitation Conference.
1. Questions asked from ACC Orlando Briefing, Slide 11:
1. Question: How will Past Performance be evaluated? Will it be evaluated on the Team as a whole?
Answer: The Government has not yet defined the evaluation criteria.
2. Question: Will Small Business be evaluated as a percentage?
Answer: Yes.
3. Question: Will the Draft Request for Proposal (RFP) be complete and contain Sections L (Instructions, notices, and conditions to bidders), and M (Evaluation factors for award)?
Answer: Yes.
2. Questions asked from the SCETI Delivery Order Briefing, Slides 15-18:
1. Question: Will the Contractor or the Government be responsible for SCETI facilities?
Answer: The Government will be responsible for SCETI facilities.
2. Question: What portion of SCETI is being developed, and who is the industry partner that others can coordinate with?
Answer: The Government will release any pertinent information pertaining to this topic with the draft RFP.
3. Question: Is an Associate Contracting Agreement (ACA) required?
Answer: The Government does not anticipate the need for an ACA with MISTE.
4. Question: Is the current Other Transaction Authority (OTA) fielding part of the overall SCETI requirement? Who is accountable to ensure all the pieces of SCETI operate together? OTA personnel? MISTE personnel?
Answer: The Government is responsible for any SCETI software integration within MISTE.
5. Question: When do you anticipate the OTA prototype to be complete? Before RFP? Before the award of MISTE?
Answer: The Government anticipates the OTA prototype to be complete no later than the MISTE contract award. However, any information the Government can release to provide fair and open competition will be included with the RFP.
3. Questions asked from the TNM Delivery Order Brief, Slides 19-24:
1. Question: Is there an unfair competitive advantage in regards to the vendor currently supporting TNM?
Answer: The Government has determined that there is not an unfair competitive advantage associated with the vendor currently supporting TNM. The Government will release the information (survey) completed at EPG in 201. The documents were delivered to the government by the current vendor supporting TNM. Industry was cautioned that this data is no longer current. MISTE.
2. Question: How does this network relate to Office of the Secretary of Defense (OSD) networks and/or the Test Resource Management Center (TRMC)? Are you (the Government) leveraging that?
Answer: This network is unrelated to OSD, TRMC, and other similar networks.
3. Question: Did the Government publish the "as known" network as it is today?
Answer: Yes.
4. Question: Is the Government considering any contract types other than Firm Fixed Price (FFP) or Cost Plus Fixed Fee (CPFF)?
Answer: The Government does not anticipate incentivizing the first 2 Delivery Orders.
5. Question: Are both SCETI and TNM awardable Delivery Orders?
Answer: Yes.
6. Question: Will both the SCETI and TNM Delivery Orders be submitted as part of the MISTE contract award?
Answer: The Government will award at least one Delivery Order at the time of the MISTE contract award, and the government anticipates awarding the second Delivery Order soon after.
4. Closing Remarks and Miscellaneous Questions:
1. Question: On TNM, the original had 5 bases on the upgrade. Is there a number now? Is it still 5 bases?
Answer: MISTE TNM DO-002 only applies to Electronic Proving Ground (EPG). The Government anticipates TNM upgrades for other Bases in the future.