Att4-BSDC-CDRLs.pdf

PDF 499 KB Posted

Attached to
Blowing Sand & Dust Chambers Federal contract opportunity
Solicitation number
W900KK17R0074
Issued by
Department of the Army Materiel Command Contracting Command Orlando Contracting Center

About this file

Attachment 4 - BSDC - Contract Data Requirements Lists

View the file

Other files for this federal contract opportunity

Other files attached to Blowing Sand & Dust Chambers, newest first.
File Type Posted
CombinedSynSol-BSDC.pdf PDF
Att1-BSDC-SOW.pdf PDF
Att3-BSDC-Spec-YTC.pdf PDF
Att2-BSDC-Spec-ATC.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SFAE-STRI-ITTS

6. REQUIRING OFFICE

SOW Paragraph 3.2.1

5. CONTRACT REFERENCE

DI-MGMT-81861

4. AUTHORITY (Data Acquisition Document No.)

3. SUBTITLE

Integrated Master Schedule (IMS)

Integrated Program Management Report (IPMR)

2. TITLE OF THE DATA ITEM

A001

1. DATA ITEM NO.

F. CONTRACTOR

W900KK-C-17-Sand and Dust

E. CONTRACT/PR NO.

Sand and Dust

D. SYSTEM/ITEM

TDP

C. CATEGORY

TM OTHER MGMT

A

B. EXHIBIT

A. CONTRACT LINE ITEM NO.

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Form Approved

OMB No. 0704-0188

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

N/A

8. APP CODE

LT

7. DD 250 REQ

D

9. DIST STATEMENT

REQUIRED

13. DATE OF SUBSEQUENT

SUBMISSION

See Block 16

11. AS OF DATE

12. DATE OF FIRST

MNTHLY

10. FREQUENCY

Repro Reg

Final

Draft

b. COPIES

a. ADDRESSEE

14. DISTRIBUTION

05-JUN-2017

J. DATE

Vick, Derek

I. APPROVED BY

H. DATE

G. PREPARED BY

Primas, Mitchell

1. BLOCK 9: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND

U.S. DEPARTMENT OF DEFENSE CONTRACTORS ONLY DUE TO CRITICAL

TECHNOLOGY EFFECTIVE 1 JUNE 2015. OTHER REQUEST FOR THIS DOCUMENT

SHALL BE REFERRED TO U.S. ARMY PEO STRI/SFAE-STRI-ITTS.

2. BLOCK 12: INITIAL SUBMISSION IS DUE NO LATER THAN 60 CALENDAR

DAYS AFTER CONTRACT AWARD.

3. BLOCK 13: SUBSEQUENT SUBMISSIONS SHALL BE DUE THE 7TH CALENDAR

DAY OF EACH MONTH AND CONTINUE MONTHLY THROUGH CONTRACT PERIOD OF PERFORMANCE.

4. BLOCK 14: CONTRACTOR SHALL SUBMIT THE DATA, IN THE FORM OF

ATTACHMENTS, VIA EMAIL TO

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

ACCEPTED BY THE PEO STRI FIREWALL. FOR SUBMISSION OF THESE FILE

TYPES, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS.

5. GOVERNMENT WILL HAVE 10 WORK DAYS FOR REVIEW AND ACCEPTANCE OR

REJECTION OF EACH SUBMISSION.

6. CONTRACTOR SHALL HAVE 5 WORK DAYS TO INCORPORATE GOVERNMENT COMMENTS.

16. REMARKS

1 SFAE-STRI-ITTS-I

0 1 0 15. TOTAL

18. ESTIMATED

TOTAL PRICE

17. PRICE GROUP

Page 1 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SFAE-STRI-ITTS-I

SOW Paragraph 3.2.3

DI-MISC-80711A

Cybersecurity Artifacts

Scientific and Technical Reports

A002

TM OTHER MISC

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

N/A

SEE BLOCK 16

1TIME

27-JUN-2017

U.S. DEPARTMENT OF DEFENSE CONTRACTORS DUE TO CRITICAL TECHNOLOGY 1

JUNE 2015. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO

U.S. ARMY PEO STRI/SFAE-STRI-ITTS.

2. BLOCK 12: SHALL BE DUE NO LATER THAN 90 CALENDAR DAYS PRIOR TO FAT TRR.

3. GOVERNMENT WILL HAVE 7 CALENDAR DAYS FOR REVIEW AND ACCEPTANCE OR REJECTION.

4. CONTRACTOR SHALL HAVE 7 CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS.

3. BLOCK 14: CONTRACTOR SHALL SUBMIT THE DATA, IN THE FORM OF

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL. AND THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-12-D-0003, CLIN 0002, CDRL A001, 1 MAY 2013). SUBMISSIONS

REQUIREMENTS TO BE DETERMINED BASED ON ATC/YTC RMF REQUIREMENTS.

Page 2 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SFAE-STRI-ITTS-IMO

SOW Paragraph 3.4.1.1

DI-MISC-80711A

Site Survey Report

Scientific and Technical Reports

A003

TM OTHER MISC

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

2. BLOCK 12: SHALL BE DUE NO LATER THAN 5 CALENDAR DAYS AFTER SITE SURVEY.

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

6. GOVERNMENT WILL HAVE 7 CALENDAR DAYS FOR REVIEW AND ACCEPTANCE OR REJECTION.

7. CONTRACTOR SHALL HAVE 7 CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS.

8. CONTRACTOR FORMAT IS ACCEPTABLE.

Page 3 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW Paragraph 3.5.1

DI-NDTI-80566A

Test Plan

A004

TM OTHER NDTI

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

2. BLOCK 12: SHALL BE DUE NO LATER THAN 45 CALENDAR DAYS PRIOR TO FAT TRR.

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

4. GOVERNMENT WILL HAVE 10 CALENDAR DAYS FOR REVIEW.

5. CONTRACTOR SHALL HAVE 10 CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS.

6. CONTRACTOR FORMAT IS ACCEPTABLE.

Page 4 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.5.4 AND 3.5.5

DI-NDTI-80603A

Test Procedure

A005

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

2TIME

1. BLOCK 12: FIRST SUBMISSION DUE 21 CALENDAR DAYS PRIOR TO FAT TRR.

2. BLOCK 13: FINAL SUBMISSION DUE 21 CALENDAR DAYS PRIOR TO SAT TRR.

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-12-D-0003, CLIN 0002, CDRL A001, 1 MAY 2013). SUBMISSIONS SHALL

BE IN MICROSOFT OFFICE 2013 OR SEARCHABLE ADOBE ACROBAT READER

(*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES, TABLES,

AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013. FOR DATA

SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB OR IF

THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER THAN

10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN THE

FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

TYPES, CONTACT THE CONTRACTING SPECIALIST FOR SUBMISSION INSTRUCTIONS.

4. GOVERNMENT WILL HAVE 7 CALENDAR DAYS FOR REVIEW AND ACCEPTANCE

OR REJECTION OF EACH SUBMISSION.

5. CONTRACTOR SHALL HAVE 7 CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS.

6. REVISIONS TO THE DOCUMENT SHALL CLEARLY INDICATE CHANGES FROM

PREVIOUS VERSIONS THROUGH VERSION/REVISION NUMBER/LETTER,

HIGHLIGHTS, CHANGE BARS, ETC.

7. GOVERNMENT RESERVES THE RIGHT TO WITNESS ANY CONTRACTOR/SUBCONTRACTOR TEST.

8. CONTRACTOR FORMAT IS ACCEPTABLE.

Page 5 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPHS 3.5.4 and 3.5.5

DI-NDTI-80809B

Test/Inspection Report

A006

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

2TIME

2. BLOCK 12: FIRST SUBMISSION SHALL BE DUE NO LATER THAN 7 CALENDAR

DAYS AFTER FAT.

3. BLOCK 13: FINAL SUBMISSION SHALL BE DUE NO LATER THAN 7 CALENDAR

DAYS AFTER SAT.

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

5. GOVERNMENT WILL HAVE 7 CALENDAR DAYS FOR REVIEW AND ACCEPTANCE OR REJECTION.

6. CONTRACTOR SHALL HAVE 7 CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS.

7. CONTRACTOR FORMAT IS ACCEPTABLE.

Page 6 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.6.1

DI-SAFT-80102C

SAFETY ASSESSMENT REPORT

A007

TM OTHER SAFT

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

DATE 16

BLOCK 16

1TIME/R

1. BLOCK 9: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE

AND U.S. DEPARTMENT OF DEFENSE CONTRACTORS DUE TO CRITICAL

TECHNOLOGY 1 JUNE 2015. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE

REFERRED TO U.S. ARMY PEO STRI/SFAE-STRI-ITTS.

2. BLOCK 12: FIRST SUBMISSION SHALL BE DUE NO LATER THAN 45 CALENDAR

DAYS PRIOR TO FAT TRR.

3. BLOCK 13: REVISIONS AS REQUIRED.

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-12-D-0003, CLIN 0002, CDRL A001, 1 MAY 2013). SUBMISSIONS SHALL

BE IN MICROSOFT OFFICE 2013 OR SEARCHABLE ADOBE ACROBAT READER

(*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES, TABLES,

AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013. FOR

DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB OR

IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

5. GOVERNMENT WILL HAVE 7 CALENDAR DAYS FOR REVIEW AND ACCEPTANCE

6. CONTRACTOR SHALL HAVE 7 CALENDAR WORK DAYS TO INCORPORATE

GOVERNMENT COMMENTS.

Page 7 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3..6.2

DI-SAFT-80106C

HEALTH HAZARD ASSESSMENT REPORT (HHAR)

A008

TM OTHER SAFT

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

2. BLOCK 12: SUBMISSION SHALL BE DUE NO LATER THAN 45 CALENDAR DAYS

PRIOR TO FAT TRR.

3. BLOCK 13: REVISIONS AS REQUIRED

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-12-D-0003, CLIN 0002, CDRL A001, 1 MAY 2013). SUBMISSIONS SHALL

BE IN MICROSOFT OFFICE 2013 OR SEARCHABLE ADOBE ACROBAT READER

(*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES, TABLES,

AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013. FOR

DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB OR

IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

5. GOVERNMENT WILL HAVE 7 CALENDAR DAYS FOR REVIEW AND ACCEPTANCE

6. CONTRACTOR SHALL HAVE 7 CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS.

1 SFAE=STRI-ITTS-I

LEN

Page 8 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.6.3

DI-ILSS-80872

Operator & Maintainer Training Course

Training Materials

A009

TM OTHER ILSS

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

DD

08-JUN-2017

Kinsman, David

06-JUN-2017

Daens, Glenn

OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO U.S. ARMY PEO

STRI/SFAE-STRI-ITTS.

1. BLOCK 8: Government approval is required prior to system acceptance.

2. BLOCK 12: SHALL BE DUE NO LATER THAN 5 CALENDAR DAYS AFTER SAT.

3. BLOCK 13: REVISIONS AS REQUIRED

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

5. GOVERNMENT WILL HAVE 5 CALENDAR DAYS FOR REVIEW AND ACCEPTANCE OR REJECTION.

6. CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE GOVERNMENT COMMENTS.

9. APPROPRIATE TECHNICAL MANUALS SHALL BE DELIVERED AT TIME OF TRAINING.

Page 9 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.6.4

DI-SESS-81758A

LOGISTICS PRODUCT DATA

A010

TM OTHER SESS

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

SEE BLOCK

ONE/R

1. BLOCK 3: SPECIFIC DELIVERABLES UNDER THIS CONTRACT ARE:

A. MATERIEL COMPONENT LIST (MCL)

B. RECOMMENDED INITIAL SPARE/REPAIR PARTS LIST

C. TOOLS AND TEST EQUIPMENT LIST (TTE)

2. BLOCK 4: CONTRACTOR SHALL DEVELOP LPD USING GEIA-STD 0007 AS GUIDANCE.

3. BLOCK 8: GOVERNMENT APPROVAL WILL BE REQUIRED PRIOR TO SIGNING DD250.

4. BLOCK 9: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND

TECHNOLOGY. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO

U.S. ARMY PEO STRI, SFAE-STRI-ITTS. WARNING - THIS DOCUMENT

CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY ARMS-EXPORT

CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE EXPORT

ADMINISTRATION ACT OF 1979, AS AMENDED, TITLE 50, U.S.C., APP. 240 ET SEQ.

5. BLOCK 12: THE CONTRACTOR SHALL SUBMIT INITIAL SUBMITTAL 30

WORKING DAYS PRIOR TO PHYSICAL CONFIGURATION AUDIT (PCA). THE

GOVERNMENT WILL HAVE 10 WORKING DAYS FOR REVIEW AND ACCEPTANCE OR

REJECTION AND PROVIDE COMMENTS. THE CONTRACTOR SHALL HAVE 5

WORKING DAYS TO INCORPORATE GOVERNMENT COMMENTS.

6. BLOCK 13: REVISIONS AS REQUIRED THROUGH THE LIFE OF THE CONTRACT.

7. BLOCK 14: BLOCK 14: CONTRACTOR SHALL SUBMIT THE DATA, IN THE FORM

OF ATTACHMENTS, VIA EMAIL TO

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

8. CONTRACTOR FORMAT IS NOT ACCEPTABLE. DELIVERABLES SHALL CONSIST

OF THE ENTIRE GEIA-STD 0007 DATABASE.

Page 10 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.6.4

DI-SESS-81759A

LOGISTICS PRODUCT DATA SUMMARIES

A011

TM OTHER SESS

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

ONE/R

Block 3: Maintenance Planning and Repair Analysis Summaries

1. BLOCK 4. DATA PRODUCTS ARE REQUIRED FOR DEVELOPMENT OF

MAINTENANCE PLANS, PROCEDURES, AND MANUALS. THE CONTRACTOR SHALL

PREPARE SUPPORTABILITY SUMMARIES USING THE DATA DICTIONARY AND

DATA PRODUCTS OUTLINED IN GEIA-STD-0007 AND THE TAILORED WORKSHEETS

FOR DATA PRODUCTS PROVIDED AS AN ANNEX TO THIS CDRL. SPECIFIC

DELIVERABLES UNDER THIS CONTRACT ARE:

A. MAINTENANCE PLANNING

B. REPAIR ANALYSIS

2. BLOCK 8: GOVERNMENT APPROVAL WILL BE REQUIRED PRIOR TO SIGNING DD250.

3. BLOCK 9: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE

AND U.S. DEPARTMENT OF DEFENSE CONTRACTORS ONLY DUE TO CRITICAL

TECHNOLOGY. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO

U.S. ARMY PEO STRI, SFAE-STRI-ITTS. WARNING - THIS DOCUMENT

CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY ARMS-EXPORT

4. BLOCK 12: THE CONTRACTOR SHALL SUBMIT INITIAL SUBMITTAL 30

WORKING DAYS PRIOR TO GOVERNMENT ACCEPTANCE TESTING (GAT). THE

GOVERNMENT WILL HAVE 10 WORKING DAYS FOR REVIEW AND ACCEPTANCE OR

REJECTION AND PROVIDE COMMENTS. THE CONTRACTOR SHALL HAVE 5

WORKING DAYS TO INCORPORATE GOVERNMENT COMMENTS.

5. BLOCK 13: LISTS SHALL BE UPDATED AFTER TECHNICAL MANUAL

VERIFICATION AND RESUBMITTED 15 WORKING DAYS PRIOR TO THE SITE

ACCEPTANCE DEMONSTRATION.

6. BLOCK 14: CONTRACTOR SHALL SUBMIT THE DATA, IN THE FORM OF

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

7. CONTRACTOR FORMAT IS ACCEPTABLE USING GEIA-STD 0007 AS GUIDANCE.

1 STRI-STRI-ITTS-I

Page 11 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.6.6

DI-TMSS-80527C

A012

TM OTHER TMSS

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

Block 2: COMMERCIAL OFF-THE-SHELF (COTS) MANUALS AND ASSOCIATED

SUPPLEMENTAL DATA

Block 3: COTS MANUALS AND ASSOCIATED SUPPLEMENTAL DATA

1. BLOCK 4: ALL PAGED BASED COTS DOCUMENTATION SHALL BE INDEXED,

TABBED AND PLACED IN A BINDER. THE INDEXED BINDER SHALL INCLUDE A

TABLE OF CONTENTS.

2. BLOCK 8: FINAL GOVERNMENT APPROVAL IS REQUIRED PRIOR TO

ACCEPTANCE OF THE SYSTEM.

3. BLOCK 9: DISTRIBUTION STATEMENT A APPROVED FOR PUBLIC RELEASE;

DISTRIBUTION IS UNLIMITED.

4. BLOCK 12 AND 13: DRAFT OUTLINES SHALL BE DUE AT ALL PROGRAM

REVIEWS. FINAL DRAFT SUBMISSION SHALL BE DUE 45 DAYS PRIOR TO

GOVERNMENT ACCEPTANCE TESTING (GAT). THE GOVERNMENT WILL HAVE 20

WORKING DAYS TO ACCEPT/REJECT AND PROVIDE COMMENTS. THE CONTRACTOR

SHALL HAVE 10 WORKING DAYS TO INCORPORATE CHANGES. REVISIONS AS

REQUIRED THROUGH THE LIFE OF THE CONTRACT.

5. BLOCK 14: CONTRACTOR SHALL SUBMIT THE DATA, IN THE FORM OF

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

6. CONTRACTOR FORMAT IS ACCEPTABLE.

Page 12 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.6.8

DI-MGMT-81804A

Item Unique Identification Report

A013

TM OTHER MGMT

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

ASREQ

Block 2: Item Unique Identification (IUID) Marking Activity, Validation and

Verification Report

1. BLOCK 4: IUID REPORT IS REQUIRED TO IDENTIFY MANDATED IUID

REQUIREMENTS IN ACCORDANCE WITH MIL-STD-130N. AT A MINIMUM, THE

FOLLOWING IUD DATA ELEMENTS ARE REQUIRED:

A. IUID TYPE ITEM DESCRIPTION

B. UNIQUE ITEM IDENTIFIER

C. UNIT OF MEASURE

D. ISSUING AGENCY

E. ENTERPRISE IDENTIFICATION NUMBER

F. CONTRACT NUMBER

G. PART NUMBER

H. SERIAL NUMBER

I. SHIPMENT/ACCEPTANCE DATE

J. SHIP TO DODAAC CODE

2. BLOCK 8: GOVERNMENT APPROVAL IS REQUIRED.

3. BLOCK 9: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND

TECHNOLOGY. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO

U.S. ARMY PEO STRI, SFAE-STRI-ITTS. WARNING - THIS DOCUMENT

CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY ARMS-EXPORT

4. BLOCK 12 AND 13: INITIAL SUBMISSION SHALL BE DUE 60 DAYS PRIOR TO

GOVERNMENT ACCEPTANCE TESTING (GAT). THE GOVERNMENT WILL HAVE 15

WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION. THE CONTRACTOR

SHALL HAVE TEN (10) WORKING DAYS FOR CORRECTION AND RESUBMISSION OF

THIS CDRL. FINAL ACCEPTANCE WILL OCCUR AT FINAL INSPECTION.

REVISIONS THROUGHOUT THE LIFE OF THE CONTRACT.

5. BLOCK 14: REPRODUCIBLE SHALL BE DELIVERED VIA WIDE AREA WORKFLOW

(WAWF), IAW CONTRACT CLAUSES SET FORTH IN SECTION G CONTRACT

ADMINISTRATION DATA; AND SHALL BE DELIVERED VIA ELECTRONIC MAIL IN

THE FORM OF ATTACHMENTS TO DOROTHY BRYANT AT

DOROTHY.A.BRYANT6.CIV@MAIL.MIL. THE EMAIL SUBJECT LINE SHALL

INCLUDE THE CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING

PERIOD (E.G., W900KK-16-C-0056, CLIN 0002, CDRL A001, 1 MAY 2013).

SUBMISSIONS SHALL BE IN MICROSOFT OFFICE 2013. GRAPHIC PACKAGES

USED TO CREATE FIGURES, TABLES, AND CHARTS SHALL BE COMPATIBLE

WITH MICROSOFT WORD 2013. REPRODUCIBLE FOR SOURCE CODE AND

EXECUTABLE FILES SHALL BE DELIVERED ON A CD-ROM TO PEO STRI, ATTN:

DOROTHY BRYANT, SFAE-STRI-KOT, 12350 RESEARCH PARKWAY, ORLANDO, FL

32826. AFTER FINAL ACCEPTANCE OF THIS DOCUMENT A REPORDUCIBLE COPY

SHALL BE DELIVERED TO DOROTHY BRYANT AT

DOROTHY.A.BRYANT6.CIV@MAIL.MIL. FOR DATA SUBMISSION WITH AN

ELECTRONIC FILE SIZE GREATER THAN 10 MB OR IF THE COMBINED SIZE OF

THE ATTACHMENTS TO THE EMAIL IS GREATER THAN 10 MB, CONTACT THE COR

FOR SUBMISSION INSTRUCTIONS. EMAIL IN THE FORM OF COMPRESSED OR

ZIP FILES AND EXECUTABLE FILES ARE NOT ACCEPTED BY THE PEO STRI

FIREWALL. FOR SUBMISSION OF THESE FILE TYPES, CONTACT THE COR FOR

SUBMISSION INSTRUCTIONS.

6. CONTRACTOR FORMAT IS NOT ACCEPTABLE.

1 SFAE-STRI-ITTS

Page 13 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.5.14

DI-SESS-81000E

Product Drawings/Models and Associated Lists

B001

X TM OTHER

B

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

U.S. DEPARTMENT OF DEFENSE CONTRACTORS ONLY DUE TO OPERATIONAL USE,

EFFECTIVE 3 MAR 2012. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE

REFERRED TO U.S. ARMY PEO STRI, SFAE-STRI-PS-G4.

4. THE GOVERNMENT SHALL HAVE 5 CALENDAR DAYS TO REVIEW AND

ACCEPTANCE OR REJECTION.

5. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

ACCEPTED BY THE PEO STRI FIREWALL. FOR SUBMISSION OF THESE FILE

Page 14 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SFAE-STRI-PMITTS

SOW PARAGRAPH 3.6.7

DI-SESS-81003E

COMMERCIAL DRAWINGS/MODELS AND ASSOCIATED LISTS

B002

X TM OTHER

B

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

U.S. DEPARTMENT OF DEFENSE CONTRACTORS ONLY DUE TO OPERATIONAL USE,

EFFECTIVE 3 MAR 2012. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE

REFERRED TO U.S. ARMY PEO STRI, SFAE-STRI-PS-G4.

4. THE GOVERNMENT SHALL HAVE 5 CALENDAR DAYS TO REVIEW AND

ACCEPTANCE OR REJECTION.

5. THE CONTRACTOR SHALL HAVE 5 CALENDAR DAYS TO INCORPORATE

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

ACCEPTED BY THE PEO STRI FIREWALL. FOR SUBMISSION OF THESE FILE

Page 15 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

SOW PARAGRAPH 3.6.5

MIL-STD-40051-2C

Page-Based Technical Manuals

C001

TM X OTHER

C

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services and Communications Directorate (07040188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.

Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the

1. BLOCK 4: MANUAL CONTENT SHALL USE GUIDANCE FROM MIL-STD-40051-2C

BUT CONTRACTOR FORMAT IS ACCEPTABLE.

2. BLOCK 8: GOVERNMENT APPROVAL WILL BE REQUIRED PRIOR TO SIGNING DD250.

3. BLOCK 9: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE

AND U.S. DEPARTMENT OF DEFENSE CONTRACTORS ONLY DUE TO CRITICAL

TECHNOLOGY. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO

U.S. ARMY PEO STRI, SFAE-STRI-ITTS. WARNING - THIS DOCUMENT

CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY ARMS-EXPORT

4. BLOCK 12 AND 13: DRAFT OUTLINES SHALL BE DUE AT ALL PROGRAM

REVIEWS. FINAL DRAFT SUBMISSION SHALL BE DUE 45 DAYS PRIOR TO

GOVERNMENT ACCEPTANCE TESTING (GAT). THE GOVERNMENT WILL HAVE 20

WORKING DAYS TO ACCEPT/REJECT AND PROVIDE COMMENTS. THE CONTRACTOR

SHALL HAVE 10 WORKING DAYS TO INCORPORATE CHANGES. REVISIONS AS

REQUIRED THROUGH THE LIFE OF THE CONTRACT.

5. BLOCK 14: CONTRACTOR SHALL SUBMIT DRAFT AND REPRODUCIBLE PRODUCTS,

IN THE FORM OF ATTACHMENTS, VIA EMAIL TO

USARMY.ORLANDO.PEO-STRI.LIST.PM-ITTS-AEM-CDRLS@MAIL.MIL AND TO THE

CONTRACT SPECIALIST. THE EMAIL SUBJECT LINE SHALL INCLUDE THE

CONTRACT NUMBER, CDRL DATA ITEM NUMBER, AND REPORTING PERIOD (E.G.,

W900KK-15-D-0001/004, CLIN 0002, CDRL A001, 1 MAY 2015). SUBMISSIONS

SHALL BE IN MICROSOFT OFFICE 2013 AND SEARCHABLE ADOBE ACROBAT

READER (*.PDF) FORMATS. GRAPHIC PACKAGES USED TO CREATE FIGURES,

TABLES, AND CHARTS SHALL BE COMPATIBLE WITH MICROSOFT OFFICE 2013.

FOR DATA SUBMISSION WITH AN ELECTRONIC FILE SIZE GREATER THAN 10 MB

OR IF THE COMBINED SIZE OF THE ATTACHMENTS TO THE EMAIL IS GREATER

THAN 10 MB, CONTACT THE COR FOR SUBMISSION INSTRUCTIONS. EMAIL IN

THE FORM OF COMPRESSED OR ZIP FILES AND EXECUTABLE FILES ARE NOT

ACCEPTED BY THE PEO STRI FIREWALL. FOR SUBMISSION OF THESE FILE

Page 16 of 16 Pages PREVIOUS EDITION MAY BE USED. DD FORM 1423-1, FEB 2001

File details come from the government source that posted it. Updated .