RFPAttach7_Cross_Reference_Matrix_020113.docx

DOCX document 82 KB Posted

Attached to
ENGAGEMENT SKILLS TRAINER (EST II) - DRAFT RFP W900KK-13-R-0007
Solicitation number
W900KK13R0007
Issued by

About this file

RFPAttach7_Cross Reference Matrix_020113

View the file

Other files

File Type Posted
QAs-to-Draft-RFP_ESTII_9_May_13.xlsx XLSX spreadsheet
QAs-to-Draft-RFP_ESTII_17Apr13.xlsx XLSX spreadsheet
RFP_EST_II_Edited_041513.doc DOC document
RFPAttach9_PerfRiskContractMatrix__Edited_012213.xls XLS spreadsheet
RFPAttach5_GFI-Dist-Agreement.doc DOC document
RFPAttach4A_GFEtoAwardee_Edited_04012013.xlsx XLSX spreadsheet
RFPAttach8_PerfRiskAssessmentSurvey.doc DOC document
RFPAttach2A_ESTII_Demo_Plan_Edited_041013.docx DOCX document
RFPAttach11_PricingSpreadsheet_Edited_041013.xlsx XLSX spreadsheet
RFPAttach1_SRD_Final_Signed_040813.pdf PDF
RFPAttach10_DO1_ESTII_Edited_032513.docx DOCX document
RFPAttach2B_Ballistic_Data_Collection_rev_0.xlsx XLSX spreadsheet
RFPAttach4B_GFI-Partial_ARDEC_Ballistics_Table_for_M16A4.docx DOCX document
RFPAttach3_iWatch_Army_Brochure.ppt PPT presentation
RFPExhibitsA-C_CDRLs_Edited_031113.pdf PDF
RFPAttach6_RFP-Comment-Form.doc DOC document
QAs-to-Draft-RFP_ESTII_26Mar13.xlsx XLSX spreadsheet
QAs-to-Draft-RFP_ESTII_11Mar13.xlsx XLSX spreadsheet
QAs_to_Draft_RFP_EST_II_15_Feb_13.xlsx XLSX spreadsheet
NDA_Weapons_ICD_Meggitt_(1-14-13).doc DOC document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT

CROSS REFERENCE MATRIX

FOR THE U.S. ARMY ENGAGEMENT SKILLS TRAINER (EST) II

3 October 2012

Prepared by U.S. Army PEO Simulation, Training and Instrumentation (PEO STRI) 12350 Research Parkway Orlando, FL 32826-3276

System Requirements Document (SRD) Verification Methods of Verification The EST II shall be qualified by a series of verifications performed during the production, system integration, and acceptance test phases of the program. The applicable verification method for each requirement stated in Section 3 of the EST II System Requirements Document is specified in the EST II Requirements Traceability Matrix (RTM). The verification methods are defined as follows:

a. Analysis. An element of verification that uses established technical or mathematical models or simulations, algorithms, charts, graphs, circuit diagrams, or other scientific principles and procedures to provide evidence that stated requirements were met.

b. Demonstration. An element of verification that involves the actual operation of an item to provide evidence that the required functions were accomplished under specific scenarios. The items may be instrumented and performance monitored.

c. Examination. An element of verification that is generally nondestructive and typically includes the use of sight, hearing, smell, touch, and taste; simple physical manipulation; and mechanical and electrical gauging and measurement.

d. Test. An element of verification in which scientific principles and procedures are applied to determine the properties or functional capabilities of items.

e. Not Applicable (N/A). Verification methods do not apply.

Verification of EST II Requirements

SRD Paragraph
Item
Analysis
Demonstration
Examination
Test
N/A
3.1
Major Systems
X
X
X
X
3.1.1
Key Performance Parameters

X

3.1.2
Instructor Operator System (IOS)

X

3.1.2.1
Trainer Control

X

3.1.2.2
Built In Test (BIT)

X

3.1.2.2.1
Daily Operational Readiness for Training Requirements

X

3.1.2.2.2
Real-Time Performance Monitoring

X

X

3.1.2.2.3
Diagnostics
X
X
3.1.2.3
Storage and Transfer of Zero Data

X

X

3.1.2.4
System Utilization

X

3.1.2.5
Operational Status

X

X

3.1.3
Simulated Weapons
X
X
3.1.3.1
Simulated Weapon Safety
X
X
3.1.3.2
Legacy Simulated Weapons

X

3.1.3.3
EST II Simulated Weapons

X

3.1.3.4
Simulated Weapon System Mounts

X

3.1.3.5
Simulated Weapon System Accessory Capabilities
X
X
X
3.1.3.6
Boresighting and Zeroing
X
X

X

3.1.3.7
Simulated Weapon Recoil
X
X
X
3.1.3.8
Ballistic Simulation

X

3.1.3.9
Ammunition

X

X

3.1.3.10
EST II Ammunition Types

X

3.1.3.11
Parallax Error Compensation

X

X

3.1.3.12
Rifle and Pistol Cant

X

X

3.1.3.13
Simulated Weapon Diagnostics

X

3.1.3.14
Simulation of Shooting Positions

X

3.2
Major Subsystem

X

3.2.1
Visual Simulation

X

3.2.1.1
Targets
X

X

3.2.1.2
Simulation Fidelity

X

3.2.1.2.1
Friendly and Enemy Forces and their Doctrine, Tactics, Techniques and Procedures

X

X

3.2.1.2.2
Geo-Typical Terrains
X
3.2.1.2.2.1
Terrain Regions
X
X
3.2.1.2.2.2
Terrain Types
X
X
3.2.1.2.2.3
Marksmanship Terrains

X

3.2.1.2.3
Atmospheric, Lighting and Weather Conditions
X
X
3.2.1.2.4
Specific enemy, non-combatants, and friendly vehicles, personnel, and equipment

X

3.2.1.2.5
Dynamic, correlated terrain

X

3.2.1.2.6
The effects of munitions on personnel, vehicles and structures

X

X

3.2.1.2.6.1
Personnel
X
X
3.2.1.2.6.2
Vehicles
X
X
3.2.1.2.6.3
Structures

X

3.2.1.3
Visual System Image Quality
X
X

X

3.2.1.3.1
Visual System Interface
X
X
3.2.1.3.2
Marksmanship Criteria

X

X

3.2.1.3.3
Collective Criteria

X

3.2.1.3.4
EOF Criteria

X x

3.2.1.4
Shots, Hits and Misses

X

3.2.2
Audio
X
X
3.2.3
Authoring Capability

X

X

3.3
Training

X

X

3.3.1
Marksmanship Training

X

X

3.3.2
Collective Training

X

X

3.3.3
Escalation of Force (EOF) Training

X

X

3.3.4
Scenario Library
X
X

X

3.3.5
Multimedia Training

X

X

3.3.6
After Action Review (AAR)

X

3.3.6.1
Marksmanship Capabilities

X

X

3.3.6.2
Collective/EOF Capabilities

X

X

3.4
General Systems

X

3.4.1
Safety
X
3.4.1.1
Eye Safe Laser
X
3.4.1.2
System Safety
X
3.4.1.3
Health Hazards
X
3.4.2
Human Engineering
X
3.4.3
Quality Construction

X

3.4.3.1
Parts
X
3.4.3.1.1
Plug-in Assemblies and Subassemblies

X

3.4.3.1.1.1
Flammable Materials
X
3.4.3.1.1.2
Fungus-Inert Materials
X
3.4.3.1.1.3
Hazardous Materials
X
3.4.3.1.1.4
Corrosion Resistance
X
3.4.3.1.1.5
Wood Products
X
3.4.3.1.1.6
Radioactive Material
X
3.4.3.1.1.7
Electrostatic Discharge (ESD) Sensitive Assemblies and Equipment

X

3.4.3.1.2
Date Related Data
X
3.4.3.1.3
Workmanship

X

3.4.3.1.3.1
Threaded Fasteners

X

3.4.3.1.3.2
Wiring

X

3.4.3.1.3.3
Shielding

X

3.4.3.2
Power
X

X

3.4.3.3
Power Line Monitoring/Protection

X

3.4.3.4
Under/Over Voltage
X

X

3.4.3.5
Power Loss/Interruption

X

3.4.4
Information Assurance
X

X

3.4.5
System Environment Requirements
X
3.4.6
Transportability

X

3.5
System Configuration

X

3.5.1
Standard Configuration
X

X

3.5.2
Post Deployment Software Support
X

X

3.5.3
Authoring Configuration
X

X

3.6
Logistics

X

3.6.1
Nameplates and Markings

X

3.6.1.1
EST II Nameplate

X

3.6.1.2
Unique Identification

X

3.6.1.3
Marking of Units, Assemblies, Subassemblies and Parts

X

3.6.1.3.1
Lowest Replaceable Units (LRU)

X

3.6.1.3.1.1
Fuse Markings

X

3.6.1.3.1.2
Printed Circuit Boards (PCB)

X

3.6.1.3.2
Terminals, Terminal Blocks, and Strips

X

3.6.1.4
ESD Marking

X

3.6.2
Maintenance

X

3.6.2.1
Maintenance Concept

X

3.6.2.2
Reliability, Availability, and Maintainability (RAM)
X
3.6.2.2.1
Reliability
X
3.6.3.2.2
Operational Availability (AO)
X

X

3.6.3.2.3
Maintainability
X
3.6.2.3
Special Tools

X

3.7
Pre-Planned Product Improvements
X

Performance Work Statement (PWS) Verification Performance Work Statement (PWS) to proposal paragraph number Cross Reference Matrix

PWS Paragraph
Proposal Paragraph

1 SCOPE

1.1 Mission Objective

2 APPLICABLE DOCUMENTS

2.1 Government Documents

2.2 Availability of Government Documents

2.3 Order of Precedence

3 REQUIREMENTS

3.1 Program Management

3.1.1 Integrated Master Plan (IMP) and Contract Work Breakdown Structure (CWBS)

3.1.2 Integrated Master Schedule (IMS)

3.1.3 Contractor’s Progress, Status and Management Report

3.1.4 Contract Invoice and Payment Report

3.1.5 Configuration Management (CM)

3.1.6 Risk Management

3.1.7 Management Reviews, Meetings and other Events

3.1.8 Visitor Support

3.1.9 Integrated Digital Environment (IDE)

3.1.10 Integrated Product Team (IPT)

3.1.11 Associate Contractor Agreements

3.2 Systems Engineering

3.2.1 System Design

3.2.2 Requirements Traceability

3.2.3 Software (SW) Engineering

3.2.4 Hardware (HW) and Software (SW) Integration

3.2.5 Specialty Engineering

3.2.6 Design Reviews

3.2.7 Product Definition Data (PDD)

3.3 EST II System

3.4 System Test and Evaluation

3.4.1 Test and Evaluation Plan

3.4.2 Test Discrepancies

3.4.3 First Article Test (FAT)

3.4.4 System Verification Test (SVT)

3.4.5 System Operational Test (SOT)

3.4.6 Inspection and Acceptance Testing

3.4.7 Test Support

3.4.8 Test and Inspection Report

3.5 Logistics

3.5.1 Maintenance Concept

3.5.2 Logistics Support Analysis

3.5.3 Supportability Analysis and Logistics Management Information (LMI)

3.5.4 Technical Publications

3.5.5 Item Unique Identification (IUID)

3.5.6 Training Products

3.6 Interim Contractor Support

3.7 Site Activation

3.8 System Technical Support

3.8.1 Post Deployment Software Support (PDSS)

3.8.2 Establishment of item supportability with the designated Life Cycle Software Engineering Environment (LCSEE)

3.8.3 Engineering Services

3.8.4 Foreign Military Sales (FMS)

3.8.5 New Weapon Developments

3.9 Government Furnished Property (GFP) and Resources

image1.png

File details come from the government source that posted it. Updated .