US Army Corps of Engineers Mississippi Valley Division

Fema le Po l i c e Town, Phase I – 15 JUN 17 Amendment 0004

Summary of Changes

Drawings:

1. Revised Site Drawing – G-001 Added new sheet C-108 to index

2. Revised Site Drawing – C-102 Added location of Water Storage Tank and Fire Pump House

3. Added Site Drawing – C-108 Added Fire Protection Site Plan

4. Revised Site Drawing – E-101 Added new service to Fire Pump House

5. Revised Site Drawing – E-102 Edit text

6. Revised Site Drawing – E-103 Added new service to Fire Pump House

7. Revised Site Drawing – E-504 Added note to Detail A1

8. Revised Site Drawing – E-601 Detail A1

9. Revised Site Drawing – E-602 Edit electrical schedules

10. Revised – Building A G-001 Added and revised sheets to index

11. Revised – Building A A-002 Added sprinkler room, reserved stairs, and edit Code Analysis

12. Revised – Building A A-003 Added sprinkler room

13. Revised – Building A A-101 Added sprinkler room, removed window, and reversed stairs

14. Revised – Building A A-201 Removed stairwell window

15. Revised – Building A A-203 Added sprinkler room door

16. Revised – Building A A-403 Added sprinkler room, removed window and reversed stairs

17. Revised – Building A A-601 Added sprinkler room to schedule and new hardware for sprinkler room door

18. Added – Building A FP-001 - Sprinkler Coverage Plan

19. Added - Building A FP-002 - Fire Alarm Riser Schematic

20. Added - Building A FP-003 - Combined Sprinkler Standpipe Riser Schematic

21. Revised – Building A M-101 Added heater to sprinkler room and modified first floor stairwell AC location

22. Revised – Building A E-101 Added/revised lighting in sprinkler room and stair

23. Revised - Building A E-103 Added receptacle in sprinkler room

24. Revised - Building A E-601 Revised electrical panel schedule

Specifications:

25. Project Table of Contents – Deleted old, replaced with new

26. Added – CLIN 0024 “Site Fire Sprinkler System” to 00 11 00.00 45

27. Added – Paragraph 2.8.6 “Site Fire Sprinkler System” to 01 10 00

28. Submittal Register - Remove old and replaced with new

29. Changed – Paragraph 3.2.1.9 “Features” changed List Item (d.) and deleted List Item (e.) to 01

35 13.

30. Added - 21 12 00 Standpipe System

31. Added - 21 13 13.00 10 - Wet Pipe Sprinkler System

32. Added - 21 30 00 - Fire Pumps

33. Revised - 28 31 64.00 10 - Fire Detection and Alarm System

34. Added – 33 16 15 – Water Storage Steel Tanks