Egypt AVIONICS BEECHCRAFT UPGRADE PWS 08April2026.pdf
PDF 250 KB Posted
- Attached to
- W58RGZ26 EGYPT
- Solicitation number
- W58RGZ26EGYPT
About this file
This is a Performance Work Statement (PWS) for the modification of two Beechcraft King Air B1900C aircraft for the Egyptian Air Force (EAF), prepared by the U.S. Army Fixed Wing Project Office (FWPO).
The Contractor shall modify two aircraft with an upgraded cockpit avionics system in Cairo, Egypt, using FAA or EASA-approved Supplemental Type Certificates (STC). The upgraded avionics suite must include dual EHS/ADS-B transponders, dual GNSS with SBAS capability, TCAS II Version 7.1, dual ADAHRS systems, weather radar, multifunction displays (MFD), dual flight management systems (FMS), a new autopilot, and inertial reference systems (IRS) for mission equipment. The upgrades shall enable the EAF to operate in civil airspace under instrument flight rules (IFR) in Europe, Africa, southwest Asia, and overwater airspace controlled under ICAO regulations, with no requirement for operations above flight level 290. The Contractor must preserve existing post-production modifications including the Aero Data Flight Inspection System (AD-AFIS-113) and Leica Electro Optical System (ADS-80). The contract period of performance is 12 months after contract award, with aircraft induction required by day 60. The Contractor shall provide two years of avionics spares including two spare international variant non-COMSEC AR-1500 radios, cockpit pilot training in Cairo for up to six pilots, six technicians, and three navigators, weight and balance documentation, technical publications, and an acceptance test procedure demonstrating full functionality with no degradation of existing systems. Final acceptance will be performed by EAF and FWPO personnel via DD-250/WAWF process. The EAF provides the two aircraft and all ground support equipment, while the Contractor furnishes all tools, equipment, and materials required for installation. The Contractor shall implement ISO 9001 AS9100 quality management systems, comply with ITAR FMS exemption (EG-B-VGT LOA), and adhere to security requirements including anti-terrorism awareness training, operations security (OPSEC) Level I training, and threat awareness reporting (TARP) for personnel traveling to Cairo.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FAQ - Egypt.xlsx | XLSX spreadsheet | |
| EGYPT RFI 2April26- Final SAM.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Army Fixed Wing Project Office
(FWPO) Egyptian Air Force (EAF)
Performance Work Statement (PWS)
Prepared by:
Fixed Wing Project Office SFAE-AV-FW
5304 Martin Road Redstone Arsenal, AL 35898
NOTE: Procuring Contracting Officer’s (PCO) Authority. The PCO is the only person authorized to approve changes in any of the requirements under this PWS and any provisions contained elsewhere in this contract. In the event the Contractor implements any such change at the direction of any person other than the PCO, the change will be considered to have been made without Government authority.
REVISION DESCRIPTION PARAGRAPHS
AFFECTED DATE
Base Initial Release All 04-03-2026
Contents
1.0 SCOPE
2.0 APPLICABLE DOCUMENTS
3.0 PROGRAM MANAGEMENT
3.1 PROGRAM KICK-OFF MEETING
3.2 INTEGRATED PRODUCT TEAM (IPT) COORDINATION
3.3 INTEGRATED MASTER SCHEDULE (IMS)
3.4 TESTING
4.0 PERFORMANCE REQUIREMENTS
4.1 COCKPIT MODIFICATION UPGRADE
4.2 MAINTENANCE AND REPAIR
4.3 OVER AND ABOVE (O&A) FOR MAINTENANCE AND REPAIR DELAY
4.4 RECOMMENDED SPARES
5.0 COCKPIT PILOT TRAINING
6.0 PRODUCT REQUIREMENTS
6.1 EGYPTIAN AIR FORCE (EAF) FURNISHED PROPERTY
6.2 GOVERNMENT FURNISHED INFORMATION
6.3 CONTRACTOR FURNISHED PROPERTY
7.0 WEIGHT AND BALANCE DOCUMENTATION
8.0 FORMS, RECORDS, AND PUBLICATIONS
9.0 QUALITY CONTROL
10.0 AIRCRAFT INDUCTION AND ACCEPTANCE
11.0 WARRANTIES
12.0 AIRCRAFT ACCEPTANCE / FINAL INSPECTION
13.0 SECURITY REQUIREMENTS
13.1 ANTI-TERRORISM (AT) REQUIREMENTS FOR CONTRACTOR
PERSONNEL TRAVELLING OVERSEAS
13.2 OPERATIONS SECURITY (OPSEC) REQUIREMENTS
13.3 THREAT AWARENESS REPORTING PROGRAM (TARP)
14.0 INTERNATIONAL TRAFFIC IN ARMS REGULATIONS (ITAR)
REQUIREMENTS
15.0 PERIOD OF PERFORMANCE (PoP)
APPENDIX A - LIST OF ACRONYMS
APPENDIX B - DOCUMENT SUMMARY LIST (DSL)
Performance Work Statement (PWS)
Modification of B1900C Cockpit Upgrade
1.0 SCOPE
The Fixed Wing Project Office (FWPO) has a requirement to modify two (2) each Beechcraft King Air B1900C aircraft for the Egyptian Air Force (EAF).
An upgraded cockpit avionics system shall be integrated with the existing post-production modifications that include Aero Data Flight Inspection System (AD-AFIS-113) and the Leica Electro Optical System (ADS-80).
The post-production modifications shall be preserved through integration.
Airworthiness approval for this modification effort shall be accomplished using Federal Aviation Administration (FAA) or European Aviation Safety Agency (EASA) approved Supplemental Type Certificate (STC). The Contractor shall provide technical specifications for all upgraded systems and subsystems. The Contractor shall provide Outside the Continental United States (OCONUS) training for pilots, technicians, and navigators.
The Contractor shall provide spares to support the requirement. The integration of the upgraded cockpit avionics system shall be performed in Cairo, Egypt.
2.0 APPLICABLE DOCUMENTS
Applicable Top-Level documents to be used in the performance of this PWS are listed by number, title, contract reference, category, and date in the Document Summary List (DSL), Appendix B of this document. Tailored individual data requirements are identified in the DSL. The document versions in the DSL take precedence over the generic references (those without revision letters) cited in this
PWS.
3.0 PROGRAM MANAGEMENT
The Contractor shall implement and perform all program management functions to ensure successful completion of this effort, to include the Integrated Product Team (IPT) process, in accordance with (IAW) the Contractor’s established program management processes and procedures. The Contractor shall provide the United States Government (USG) with a weekly report by email.
3.1 PROGRAM KICK-OFF MEETING
The Contractor shall conduct a kick-off meeting at the Contractor’s facility within thirty (30) business days after contract award (ACA). The Contractor shall coordinate a detailed agenda with the Government Project Lead and deliver the agenda and attendant briefing IAW DI-ADMN-81249, CDRL A001. The Contractor shall prepare meeting minutes IAW DI-ADMN-81250, CDRL A002.
All briefings shall include, as a minimum:
a. All corrections made during the meeting.
b. Contractor-identified Project Lead for this effort at the kick-off meeting.
c. All Contractor personnel responsible for aspects of the requirements within the scope of the PWS shall be present to discuss their approach to successful completion of this task.
d. The Contractor shall provide their program plan and schedule, to include:
i. Technical and management controls and approaches for the labor force.
ii. Program organization.
iii. Roles and responsibilities of IPTs.
iv. Program execution risk.
v. Quality.
vi. Configuration management approaches.
vii. Personnel resources.
viii. Development and testing that shall satisfy the requirements of this PWS.
ix.
3.2 INTEGRATED PRODUCT TEAM (IPT) COORDINATION
The Contractor shall implement an IPT process with defined membership roles and responsibilities to conduct bi-weekly IPT meetings. The Contractor’s Project Lead shall be empowered to make decisions for the Contractor in all matters related to the conduct of this PWS. Contractor (and sub-Contractor, if applicable) Project Leads or Subject Matter Experts (SME) shall participate. The Contractor shall coordinate and lead a project status teleconference specific to this effort. The Contractor shall be prepared to provide status on the modifications including issues, planned solutions, schedule, and other relevant topics. The Contractor shall report the status of risks, schedule variances, technical performance, logistic or part impact and support, and all related issues with recommendations for resolution.
The Contractor shall coordinate a standard agenda with the Government Project Lead and deliver the agenda IAW DI-ADMN-81249, CDRL A001. The Contractor shall prepare conference minutes and any presented material and deliver IAW DI-
ADMN-81250, CDRL A002.
3.3 INTEGRATED MASTER SCHEDULE (IMS)
The Contractor shall implement and maintain an IMS. The IMS shall be an integrated schedule of detailed program tasks and shall be delivered IAW DI-MGMT-81861, CDRL A005.
3.4 TESTING
The Contractor shall develop an Acceptance Test Procedure (ATP) to demonstrate full functionality and operation of all modified systems and ensure no degradation of existing systems. Acceptance of the cockpit avionics upgrade shall be performed post modification and shall include flight test performed by EAF pilot in command and Contractor mentor co-pilot to validate performance and shall include a FWPO Technical representative in the cabin area to accept that the upgrades are fully operational. The ATP shall be delivered IAW DI-NDTI-80603, CDRL A006.
4.0 PERFORMANCE REQUIREMENTS
The integration of the upgraded cockpit will be performed in Cairo, Egypt.
4.1 COCKPIT MODIFICATION UPGRADE
The Contractor shall use FAA or EASA approved STC to modify an EAF provided B1900C aircraft with an upgraded cockpit avionics system. The upgrade shall allow EAF to fly in civil airspace under instrument flight rules (IFR) without a requirement for country waiver due to lack of avionics capabilities required for entry into specified airspace. The Contractor shall consider the intended aircraft operations to include Europe, Africa, southwest Asia, and overwater airspace controlled under International Civil Aviation Organization (ICAO) regulations. There is no requirement for the Contractor to provide requirements for the EAF aircraft to fly above flight level 290 (29,000’). The Contractor shall provide all tools, equipment, and material required to complete installation of the modification. The Contractor shall provide an avionics suite that includes the threshold requirements listed below:
• Transponder with Enhanced Surveillance (EHS) and ADS-B (Out):
Dual EHS and Automatic Dependent Surveillance – Broadcast (ADS- B): ADS-B (Out) transponders shall be integrated to meet the European Commission Implementing Regulation (EU) 1207/2011, which calls out the detailed performance requirements of the data transponders are required to transmit to Air Traffic Control.
• Global Navigation Satellite Systems (GNSS) enabled with Space Based Augmentation System (SBAS) – Dual GNSS, such as the American Global Positioning System (GPS) or the European Galileo System, to determine the aircraft’s position and velocity around the world to a high degree of accuracy utilizing signals broadcast from a constellation of medium earth orbit satellites.
• Traffic and Collision Avoidance Systems (TCAS) II Version 7.1: TCAS
(also known in Europe as Aircraft Collision Avoidance Systems (ACAS)) work with the aircraft transponder to alert the flight crew to the presence of air traffic which is close enough to pose a mid-air collision hazard.
• Air Data and Attitude Heading Reference Systems (ADAHRS): Dual, redundant ADAHRS systems shall be integrated to support other installed avionics. ADAHRS systems measure altitude, vertical speed, airspeed, heading, turn rate, and aircraft attitude.
• Weather Radar System: An onboard aircraft color weather radar system shall be installed to provide the crew with in-flight, real-time indication of convective weather in the aircraft’s flight path.
• Multifunction Displays (MFD): A minimum of one MFD shall be installed to display Communication, Navigation, Surveillance, Weather Radar, and other critical flight information on the center portion of instrument panel.
• Flight Management System (FMS): Dual FMS displays shall be installed to support all the flight crew’s avionics management functions such as navigation data entry, autopilot controls, radio tuning, etc.
• New Autopilot: The autopilots on these aircraft are in danger of component obsolescence and incompatibility with newer avionics and shall be replaced.
• Inertial Reference System (IRS) for mission equipment: IRS systems shall be integrated for use by mission equipment in the cabin.
Airworthiness approval for this modification effort shall be accomplished using FAA or EASA approved STC.
All components and materials removed from the aircraft during the modification process are EAF Owned Property. The Contractor shall prepare a complete listing of all removed components and deliver IAW DI- MGMT-80259, CDRL A007. At a minimum, the component listing shall include each component part number, national stock number (NSN), and serviceability information.
The Contractor shall process components and material removed from the aircraft per FW PO direction and IAW FAR 52.245-1.
4.2 MAINTENANCE AND REPAIR
During the modification period, the Egyptian Air Force (EAF) is responsible for parts and labor associated with unforeseen aircraft repairs or maintenance that do not pertain to the cockpit modification and are outside the scope of the Contractor's work. The EAF will have 72 hours to complete unforeseen maintenance or repair. The 72 hour allowable repair window does not include Egyptian holidays or weekends. The Firm-Fixed Price (FFP) is inclusive of all contractor costs for EAF maintenance and repairs completed within the 72 hour timeline; no additional compensation will be authorized. If maintenance or repair is projected to take longer than 72 hours, the contractor shall immediately notify the KO and COR in writing.
4.3 OVER AND ABOVE (O&A) FOR MAINTENANCE AND REPAIR DELAY
The Contractor shall provide over and above cost which would be incurred for day-to-day slippage if the EAF exceeds the 72 hour repair or maintenance timeline outlined in this PWS. If EAF maintenance or repairs exceed 72 hours, the Contractor shall submit a formal O&A request upon completion of maintenance or repair to the KO for review and approval to become eligible for compensation. Verbal direction from any party does not constitute authorization to bill for delay costs; only written approval from the KO authorizes the Contractor to bill for delays.
Each O&A request shall include:
a. A description of the condition or deficiency
b. Impact to schedule, including an estimate of the total delay duration
c. Proposed cost based on daily delay rate established in the contract
d. Supporting documentation, such as photos or technical justification
4.4 RECOMMENDED SPARES
The Contractor shall develop and provide a recommended two (2) year avionics spares package to include two (2) each spare international variant non-COMSEC AR-1500 radios to have available at delivery of first aircraft.
All spares will be transported to final destination utilizing Egypt's Freight Forward.
5.0 COCKPIT PILOT TRAINING
The Contractor shall provide cockpit pilot training to be conducted in Cairo, Egypt. This training shall include the performance of all required ground and pre-flight inspections to ensure the aircraft is airworthy prior to the commencement of any flight training to include:
• Cockpit pilot training in the customer’s aircraft for the new cockpit profile for up to six (6) pilots, six (6) technicians and three (3) navigators.
• The Contractor shall conduct training to provide hands-on flight training relevant to the cockpit installation and IAW with the Original Equipment Manufacturer (OEM) flight publications for all installed equipment to safely operate the modified Beechcraft King Air B1900C. This training shall include a combination of Computer Based Training (CBT) and hands-on cockpit training and a familiarization flight with Contractor pilots. The training shall address hardware, system operations, and FMS interactions or anomalies that may be observed by the operator.
• The Contractor shall develop and deliver training packages that can be left in country to support subsequent pilot and operator training. The training syllabus shall be provided to the USG IAW DI-MISC-80508, CDRL A008. The Contractor shall leave all training materials used with the EAF upon completion of training.
• The Contractor shall submit a Training Report in IAW DI-MISC-80508, CDRL A009, upon the completion of all training.
• All training and training material shall be provided in English.
Training shall commence after completion of the ground and flight ATP in Cairo, Egypt. No Government services will be provided to the Contractor during the performance of the training.
6.0 PRODUCT REQUIREMENTS
6.1 EGYPTIAN AIR FORCE (EAF) FURNISHED PROPERTY
The EAF will provide two (2) each Beechcraft B1900C aircraft. The aircraft will be delivered in place at a designated facility in Cairo, Egypt, mutually agreed to by the EAF and the United States Government (USG).
The EAF will provide all Ground Support Equipment (powercart, tug, tow bar, etc.)
needed to support the aircraft during modifications.
6.2 GOVERNMENT FURNISHED INFORMATION
No documents will be provided by the USG or EAF.
6.3 CONTRACTOR FURNISHED PROPERTY
The Contractor shall provide all equipment, material and tools required to complete the modification.
7.0 WEIGHT AND BALANCE DOCUMENTATION
The Contractor shall weigh each aircraft after completion of the modification effort.
Weight and Balance Report shall contain all data required IAW Society of Allied Weight Engineers (SAWE). Report shall be delivered IAW DI-MGMT-81501, CDRL A010. The USG shall have unlimited rights, per DFARS 252.227-7013, to the weight and balance documentation generated under this effort.
8.0 FORMS, RECORDS, AND PUBLICATIONS
The Contractor shall provide the Government the OEM Operator and Maintenance Manuals, updates, and addendums to all applicable Aircrew Flight Manual Supplements (AFMS) for all equipment and modifications for this effort. As each aircraft completes the modifications, the Contractor shall deliver the AFMS and all publications applicable to the installed equipment IAW DI-TMSS-81816, CDRL A011.
9.0 QUALITY CONTROL
A Quality Management System compliant to ISO9001 AS9100 or equivalent, shall be implemented for the entire period of performance. The Contractor shall ensure that the aircraft meets design criteria specified in Title 14 of the Code of Federal Regulations (14 CFR), Part 23 airworthiness standards. The aircraft shall be Certified IAW 14 CFR, Part 21 certification procedures. The aircraft shall be maintained IAW manufacturer’s approved instructions and service bulletins, FAA Regulations, 14 CFR, Part 43, and 14 CFR, Part 39 requirements.
10.0 AIRCRAFT INDUCTION AND ACCEPTANCE
The two (2) Beechcraft King Air B1900C aircraft will be available to the Contractor Not Later Than (NLT) sixty (60) days after contract award.
The Contractor shall provide an inspection team that includes FAA-certified Airframe and Powerplant (A&P) mechanics to conduct, with the USG, a site visit, joint inspection and acceptance of the aircraft after contract award.
The EAF will be responsible for all fuel for the aircraft during test flights.
11.0 WARRANTIES
The Contractor shall pass all commercial warranties to the EAF. The Contractor shall ensure warranty coverage of all work associated with the cockpit avionics system modification and new procurement items for the period of one (1) year from the signing of the DD-250.
12.0 AIRCRAFT ACCEPTANCE / FINAL INSPECTION
The Contractor shall provide a seven (7) calendar day notification and permit FWPO-approved USG, and other FWPO-approved representatives to participate and witness all testing and final acceptance processes. The Contractor shall perform both in-process and final inspections with USG representatives at the facility where the aircraft is modified. The Contractor shall provide FAA approved mechanics for installation and inspection. FWPO Program Integrator and Quality Assurance (QA) will travel to perform periodic inspections with a final inspection and operations check at the end of the modification. Final source inspection and acceptance will be performed by EAF and the FWPO personnel at the facility where the modification is performed. Final acceptance of aircraft will be by the USG. Final acceptance will be completed via the DD-250/Wide Area Workflow (WAWF) process.
13.0 SECURITY REQUIREMENTS
The Contractor shall comply with Department of Defense (DoD) requirements as specified in paragraphs identified below.
13.1 ANTI-TERRORISM (AT) REQUIREMENTS FOR CONTRACTOR
PERSONNEL TRAVELLING OVERSEAS
All Contractor employees, including subcontractor employees required to travel overseas as a condition of this contract shall receive Government provided AT awareness training, specific to the destination countries. Additionally, all Contractor employees, including subcontractor employees stationed or deployed in OCONUS contingency operations areas or designated combat zones shall receive Government provided AT awareness training specific to the area of responsibility (AOR) at their overseas location. Specific AOR training content is directed by the combatant commander, with the Antiterrorism Officer (ATO) being the local point of contract.
13.2 OPERATIONS SECURITY (OPSEC) REQUIREMENTS
Per AR 530-1 Operations Security, the Contractor employees travelling to Cairo, Egypt in support of this effort must complete Level I OPSEC Awareness training.
New employees shall be trained within 30 calendar days of their reporting for duty and annually thereafter.
13.3 THREAT AWARENESS REPORTING PROGRAM (TARP)
Per AR 381-12, all Contractor employees with a security clearance shall receive annual TARP training.
14.0 INTERNATIONAL TRAFFIC IN ARMS REGULATIONS (ITAR)
REQUIREMENTS
To satisfy its import/export requirements, the Contractor may utilize the Foreign Military Sales (FMS) exemption pursuant to 22 CFR Section 126.6 of the ITAR.
The contract period of performance and scope of technical data and services are within the scope of the implementing LOA. For purposes of invoking the exemption listed in ITAR Section 126.6 for FMS materiel, the applicable LOA to be cited is
EG-B-VGT.
15.0 PERIOD OF PERFORMANCE (PoP)
The Contractor shall have a PoP of 12 months ACA.
• Aircraft shall be inducted for modifications sixty (60) days ACA.
APPENDIX A - LIST OF ACRONYMS
A&P Aircraft and Powerplant ACA After Contract Award ACAS Aircraft Collision Avoidance Systems ADAHRS Air Data and Attitude Heading Reference System ADS-B Automatic Dependent Surveillance – Broadcast AFMS Aircrew Flight Manual Supplement AOR Area of Responsibility AT Anti-Terrorism ATO Anti-Terrorism Officer ATP Acceptance Test Procedure CBT Computer Based Training CDR Critical Design Review CDRL Contract Data Requirements List CFR Code of Federal Regulations DD Department of Defense (forms) DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense DSL Document Summary List EAF Egyptian Air Force EASA European Aviation Safety Agency EHS Enhanced Surveillance ELA Electrical Load Analysis FAA Federal Aviation Administration FAR Federal Acquisition Regulations FMS Flight Management System FMS Foreign Military Sales FWPO Fixed Wing Project Office GNSS Global Navigation Satellite Systems GPS Global Positioning System IAW In Accordance With ICAO International Civil Aviation Organization IFR Instrument Flight Rules IMS Integrated Master Schedule IPT Integrated Product Team IRS Inertial Reference System ITAR International Traffic in Arms Regulations LOA Letter of Offer and Acceptance MFD Multifunction Displays MIL Military NLT Not Later Than NSN National Stock Number OCONUS Outside the Continental United States OEM Original Equipment Manufacturer
OPSEC Operations Security PCO Procuring Contracting Officer PDR Preliminary Design Review PWS Performance Work Statement POP Period of Performance QA Quality Assurance RTVM Requirements Traceability Verification Matrix SAWE Society of Allied Weight Engineers SBAS Space Based Augmentation System SME Subject Matter Expert SRR System Requirements Review STC Supplemental Type Certification TARP Threat Awareness Reporting Program TCAS Traffic and Collision Avoidance Systems TIM Technical Interchange Meeting USG United States Government WAWF Wide Area Workflow
APPENDIX B - DOCUMENT SUMMARY LIST (DSL)
CONTRACTORS ARE ENCOURAGED TO OFFER SUGGESTIONS, COMMENTS, OR
ALTERNATIVES TO THE DOCUMENTS CITED HEREIN. TAILORING, CATEGORY
OF APPLICATION, REVISION LEVELS, AND THE DOCUMENTS CITED ARE ALL
CANDIDATES.
Definition of Document Categories
1. Category 0 (Cat 0). The requirements contained in the directly cited document are non-mandatory and are for reference and information only.
2. Category 1 (Cat 1). The requirements contained in the directly cited document are contractually applicable to the extent specified. Unless otherwise specified in the solicitation, contract, or contract modifications, all requirements contained in reference and subsequently referenced documents are contractually for guidance and information only.
3. Category 2 (Cat 2). The requirements contained in the directly cited document and the reference documents identified in the directly cited document are contractually applicable to the extent specified. Unless otherwise specified in the solicitation, contract, or contract modifications, all requirements contained in subsequently referenced documents within reference documents are contractually for guidance and information only.
DD Form 1423 Definitions
Blocks 10, 11, 12, 13: "Submit" means to deliver to the Government as specified in the shipping instructions for data, which are located in section F of the contract.
Block 14: Regular/Repro Copies
Regular Copy - Blueline, Blackline, Xerographic (originals of reports, plans, or routine data also fall into this definition).
Repro Copy - Multilith, Vellum, photographic negatives, etc. (originals of drawings, ECPs, ERRs, technical publications).
CONTRACTUAL REQUIREMENTS OF DATA ITEM DESCRIPTION (DID)
DD FORM 1664, Block 10 - Preparation Instructions. This block contains the only portion of the DID that represents a contractual requirement imposed on the Contractor. All other blocks are for Government use and for reference only. ALL
REFERENCES TO SOURCE DOCUMENTS IN BLOCK 10 OF DATA ITEM
DESCRIPTION ARE USED FOR REFERENCE ONLY.
DOCUMENT
NUMBER
TITLE DATE/CATE
GORY
1. DI-ADMN-81249C
Data Item No. A001
Meeting Agenda 30 Jul 21
CAT 1
2. DI-MGMT-81250C
Data Item No. A002
Meeting Minutes 30 Jul 21
CAT 1
3. DI-MGMT-82133A
Data Item No. A003
Requirements Traceability Verification Matrix (RTVM)
29 Jul 25
CAT 1
4. DI-MGMT-81605
Data Item No. A004
Briefing Material 15 Feb 01
CAT 1
3. DI-MGMT-81861C
Data Item No. A005
Tailoring is delineated as the following:
Only 1.2.2, 1.3.1,
1.6.2.2 applicable
Integrated Program Management Data and Analysis Report (IPMDAR)
30 Aug 21
CAT 1
4. DI-NDTI-80603A
Data Item No. A006
Test Procedure 14 Nov 06
CAT 1
5. DI-MGMT-80259
Data Item No. A007
Physical Inventories Report 13 Oct 86
CAT 1
6. DI-MISC-80508B
Data Item No. A008
Technical Report – Study/Services Training Syllabus
14 Nov 06
CAT 1
7. DI-MISC-80508B
Data Item No. A009
Technical Report – Study/Services Training Report
14 Nov 06
CAT 1
8. DI-MGMT-81501A
Data Item No. A010
Weight and Balance Report for Aircraft 27 Sep 07
CAT 1
9. DI-TMSS-81816
Data Item No. A011
Commercial Off-The-Shelf (COTS) Manual Supplemental Data
25 May 10
CAT 1
ISO 9001:2015, Fifth Edition.
Para: 7.0
Quality Management Systems – Requirements
15 SEP 15
CAT 2
AS 9100D
Para: 7.0
Quality Management Systems – Requirements for Aviation, Space, and Defense Organizations
SEP 16
CAT 2
| 1.0 SCOPE |
| 2.0 APPLICABLE DOCUMENTS |
| 3.0 PROGRAM MANAGEMENT |
| 3.1 PROGRAM KICK-OFF MEETING |
| 3.2 INTEGRATED PRODUCT TEAM (IPT) COORDINATION |
| 3.3 INTEGRATED MASTER SCHEDULE (IMS) |
| 3.4 TESTING |
| 4.0 PERFORMANCE REQUIREMENTS |
| 4.1 COCKPIT MODIFICATION UPGRADE |
| 4.2 MAINTENANCE AND REPAIR |
| 4.3 OVER AND ABOVE (O&A) FOR MAINTENANCE AND REPAIR DELAY |
| 4.4 RECOMMENDED SPARES |
| 5.0 COCKPIT PILOT TRAINING |
| 6.0 PRODUCT REQUIREMENTS |
| 6.1 EGYPTIAN AIR FORCE (EAF) FURNISHED PROPERTY |
| 6.2 GOVERNMENT FURNISHED INFORMATION |
| 6.3 CONTRACTOR FURNISHED PROPERTY |
| 7.0 WEIGHT AND BALANCE DOCUMENTATION |
| 8.0 FORMS, RECORDS, AND PUBLICATIONS |
| 9.0 QUALITY CONTROL |
| 10.0 AIRCRAFT INDUCTION AND ACCEPTANCE |
| 11.0 WARRANTIES |
| 12.0 AIRCRAFT ACCEPTANCE / FINAL INSPECTION |
| 13.0 SECURITY REQUIREMENTS |
| 13.1 ANTI-TERRORISM (AT) REQUIREMENTS FOR CONTRACTOR |
| PERSONNEL TRAVELLING OVERSEAS |
| 13.2 OPERATIONS SECURITY (OPSEC) REQUIREMENTS |
| 13.3 THREAT AWARENESS REPORTING PROGRAM (TARP) |
| 14.0 INTERNATIONAL TRAFFIC IN ARMS REGULATIONS (ITAR) |
| REQUIREMENTS |
| 15.0 PERIOD OF PERFORMANCE (PoP) |
| APPENDIX A - LIST OF ACRONYMS |
| APPENDIX B - DOCUMENT SUMMARY LIST (DSL) |