AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Fixed Price Incentive (Cost Based)

0002 2015OCT19

W58RGZ

ARMY CONTRACTING COMMAND-REDSTONE

REDSTONE ARSENAL AL 35898-5280

JULIE A KRESS

EMAIL: JULIE.A.KRESS2.CIV@MAIL.MIL

W58RGZ-15-R-0070

2015SEP24

X

X

/SIGNED/

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 46

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: JULIE A KRESS

Buyer Office Symbol/Telephone Number: CCAM-BH-B/(256)313-1354

Type of Contract 1: Fixed Price Incentive (Cost Based)

Type of Contract 2: Firm Fixed Price

Kind of Contract: Research and Development Contracts

*** End of Narrative A0000 ***

A-1. The US Army Contracting Command-Redstone hereby issues Amendment 0002 to Request for Proposal (RFP) W58RGZ-15-R-0070.

A-2. In Section B CLIN 0003 the sentence, While this CLIN is not separately priced, Offerors shall fill in Blocks 17 and 18 of each individual DD-1423-1 (Exhibit A), is hereby removed.

A-3. The following clauses in Section I of the RFP released on 24 September 2015 have changed as follows:

1) FAR Clause 52.232-16, Progress Payments, is added.

2) FAR 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards, is amended by revising the date of the clause to Oct 2015, and by revising paragraphs (d)(2), (d)(3), and (e) by removing "$25,000" from each and replacing it with "$30,000".

3) FAR 52.209-6, Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment, is amended by revising the date of the clause to Oct 2015, and by revising paragraphs (b), (c), and (e)(1) by removing

"$30,000" from each and replacing it with "$35,000".

4) FAR 52.222-37, Employment Reports on Veterans, is amended by revising the date of the clause to Oct 2015, and by revising paragraph (g) by removing "$100,000" and replacing it with "$150,000".

5) FAR 52.222-54, Employment Eligibility Verification, is amended by revising the date of the clause to Oct 2015, and by revising paragraph (e)(2) by removing "$3,000" and replacing it with "$3,500".

6) FAR 52.244-6, Subcontracts for Commercial Items, is amended by: (i) revising the date of the clause to Oct 2015, (ii) updating the date of the clause in paragraph (c)(1)(i) to Oct 2015 and removing "$5,000,000" and replacing it with "$5.5 million", (iii) revising paragraph (c)(1)(iii) by removing "$650,000" and replacing it with "$700,000", and (iv) by updating the date of the clauses in paragraphs (c)(1)(vi) and (c)(1)(vii) to Oct 2015.

7) DFARS 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting, is amended by: (i) revising the date of the clause to SEP 2015, (ii) revising the title, and (iii) revising the text in its entirety to expand the scope of the clause to cover the safeguarding of covered defense information and require contractors to report cyber incidents involving covered information as well as any cyber incident that may affect the ability to provide operationally critical support.

8) DFARS 252.209-7004, Subcontracting With Firms That Are Owned or Controlled by the Government of a Terrorist Country, is amended by revising the date of the clause to Oct 2015, and by revising paragraph (a) by removing "$30,000" and replacing it with

"$35,000".

9) DFARS 252.209-7009, Organizational Conflict of Interest was removed.

10) FAR 52.217-9 (c) was changed to "The total duration of this contract, including the exercise of any options under this clause, shall not exceed 36 months."

11) DFARS 252-234-7002, Earned Value Management System (Deviation 2015-0015) (DEV 2015-00015) Class Deviation 2015-O0017 rescinds and supersedes Class Deviation 2015-O0015.

12) DFARS 52.203-13, Contractor Code of Business Ethics and Conduct, is amended by revising the date of the clause to Oct 2015, and by revising paragraph (d)(1) by removing "$5,000,000" and replacing it with "$5.5 million".

13) FAR 52.219-9, Small Business Subcontracting Plan (Deviation 2013-O0014)--Alternate II, is amended based on changes to the basic clause; however, the date of the clause is not changed. (The title of the clause is revised to reflect the date change of the basic clause.)

14) FAR 52.222-35, Equal Opportunity for Veterans, is amended by revising the date of the clause to Oct 2015, and by revising paragraph (c) by removing "$100,000" and replacing it with "$150,000".

2 46

W58RGZ-15-R-0070 0002

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

15) FAR 52.230-2, Cost Accounting Standards, is amended by revising the date of the clause to Oct 2015, and by revising paragraph (d) by removing "$700,000" and replacing it with "$750,000".

16) DFARS 252.225-7004, Report of Intended Performance Outside the United States and Canada -- Submission After Award, is added.

17) DFARS 252.204-7009, Limitations on the Use and Disclosure of Third-Party Contractor Reported Cyber Incident Information, dated

Aug 2015, is added.

18) DFARS 252.239-7010, Cloud Computing Services, is added.

A-4. The following documents in Section J have changed as follows:

1) Exhibit A, Contract Data Requirements List (CDRLs):

a) Block 18 was changed on all CDRLs (except A019, EMD Proposal) from "Insert in Section B" to "NSP in Section B".

b) C004 Block 16 was revised to read "Blocks 10, 12 and 13: Contractor shall deliver report NLT 30 days after completion of the engine system PDR."

2) Attachment 0001, Performance Work Statement, Attachment G was revised to unhide Column C.

3) Attachment 0004 Specification Development Document (SDD):

a) Paragraph 3.1.5.3 was deleted.

b) Paragraph 3.1.5.1.1 was re-numbered to correct numbering error.

4) Attachment 0005, Technical Data Supplement (TDS):

a) Paragraph 5.5.1.2 deleted "A materials and coatings summary and a design life summary shall be provided as described in

5.5.7 and 5.6 respectively."

b) Paragraph 5.5.3.2 deleted "A materials and coating summary and design life summary shall be provided as described in 5.5.7 and 5.6, respectively."

c) Paragraphs 5.5.5.7 was deleted. Paragraph 5.5.5.10 was added.

d) Paragraph 5.6 deleted "engine specification" and replaced with "Specification Development Document (SDD)."

e) Figure 1, Sample Compressor Map is added.

f) Figure 2, Sample Turbine Performance Map is added.

g) Table X, Failure Mode and Damage Effects Analysis Summary is added.

h) Table XI, Ballistic Vulnerability Estimates is added.

5) Attachment 0015 - Pre-decisional Program Schedule is added.

A-5. The following change was made to Section K:

1) FAR 52.230-1, Cost Accounting Standards Notices and Certification, is amended by revising the date of the clause to Oct 2015, and by revising paragraph (a) by removing "$700,000" and replacing it with "$750,000".

2) DFARS 252.239-7009, Representation of Use of Cloud Computing, is added.

A-6. The following changes were made to Section L:

1) Regulatory Cite 252.209-7008 was removed.

2) DFARS Clause 252.234-7001, Class Deviation 2015-O0017 has been added. See Class Deviation 2015-O0017 for guidance.

3 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

3) Instructions to Offerors paragraph 1.1.7.2 Volume II Technical, e) Sub-factor 4 - Program/Technical Management Approach, 6) second paragraph: Cyber Security was revised to add clarifying language regarding compliance with NIST SP 800-171.

4) DFARS 252.225-7003, Reporting of Intended Performance Outside the United States and Canada -- Submission With Offer, is added.

5) DFARS 252.204-7008, Compliance with Safeguarding Covered Defense Information Controls (DEVIATION 2016-O0001), dated Oct 2015, is added.

A-7. The following changes were made to Section M as follows:

1) Evaluation Factors for Award, 1.1 Basis of Award, (3) Reliability changed:

From: "The engine shall have a 97% probability of completing 11 hours of operation without experiencing an Essential Function

Failure (EFF)"

To: "The engine Mean Time Between Essential Function Failure (MTBEFF) shall be greater than or equal to 453 Engine Operating Hours

(EOH)."

2) Evaluation Factors for Award, 1.1.1 Factor 1, Technical, 1.1.1.4 Sub-factor 4: Program/Technical Management Approach, (6)

Cyber-Security was revised to state that the evaluation will assess the Offerors approach to implementing a cyber security "management program" as opposed to a "control system". Also the requirement for the proposal to address NIST security controls was removed.

A-8. Except as stated herein, all other terms and conditions remain unchanged and in full force and effect.

*** END OF NARRATIVE A0003 ***

4 46

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

0003 CONTRACT DATA REQUIREMENTS LIST (CDRL) ______________________________________

Technical Data as set forth in Contract Data

Requirements List (DD Form 1423) hereinafter referred to as Exhibit A.

Inspection and Acceptance is to be in accordance with Section E.

The Target Cost offered for CLIN 0001 is to include the price for all Contract Data Requirements List

(CDRL) deliverables as well as required Contractor

Manpower Reporting with the exception of CDRL A019

Under CLIN 0002.

(End of narrative B001)

5 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION I - CONTRACT CLAUSES

Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________

I-1 CHANGED 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS OCT/2015

I-2 CHANGED 52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH OCT/2015

CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT

I-3 CHANGED 52.222-37 EMPLOYMENT REPORTS ON VETERANS OCT/2015

I-4 CHANGED 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION OCT/2015

I-5 CHANGED 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS OCT/2015

I-6 ADDED 252.204-7009 LIMITATIONS ON THE USE OR DISCLOSURE OF THIRD-PARTY CONTRACTOR AUG/2015

REPORTED CYBER INCIDENT INFORMATION

I-7 CHANGED 252.204-7012 SAFEGUARDING COVERED DEFENSE INFORMATION AND CYBER INCIDENT REPORTING SEP/2015

I-8 CHANGED 252.209-7004 SUBCONTRACTING WITH FIRMS THAT ARE OWNED OR CONTROLLED BY THE OCT/2015

GOVERNMENT OF A TERRORIST COUNTRY

I-9 DELETED 252.209-7009 ORGANIZATIONAL CONFLICT OF INTEREST -- MAJOR DEFENSE ACQUISITION DEC/2012

PROGRAM

I-10 ADDED 252.225-7004 REPORT OF INTENDED PERFORMANCE OUTSIDE THE UNITED STATES AND CANADA-- OCT/2015

SUBMISSION AFTER AWARD

I-11 ADDED 252.239-7010 CLOUD COMPUTING SERVICES AUG/2015

I-12 CHANGED 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT MAR/2000

(a) The Government may extend the term of this contract by written notice to the Contractor within 10 days; provided that the

Government gives the Contractor a preliminary written notice of its intent to extend at least 10 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 36 months.

(End of Clause)

I-13 CHANGED 52.232-16 PROGRESS PAYMENTS APR/2012

The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:

(a) Computation of amounts.

(1) Unless the Contractor requests a smaller amount, the Government will compute each progress payment as 80 percent of the

Contractors total costs incurred under this contract whether or not actually paid, plus financing payments to subcontractors (see paragraph (j) of this clause), less the sum of all previous progress payments made by the Government under this contract. The

Contracting Officer will consider cost of money that would be allowable under FAR 31.205-10 as an incurred cost for progress payment purposes.

(2) The amount of financing and other payments for supplies and services purchased directly for the contract are limited to the amounts that have been paid by cash, check, or other forms of payment, or that are determined due will be paid to subcontractors--

(i) In accordance with the terms and conditions of a subcontract of invoice; and

(ii) Ordinarily within 30 days of the submission of the Contractors payment request to the Government.

(3) The Government will exclude accrued costs of Contractor contributions under employee pension plans until actually paid unless--

(i) The Contractors practice is to make contributions to the retirement fund quarterly or more frequently; and

(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractors total costs for progress payments until paid).

(4) The Contractor shall not include the following in total costs for progress payment purposes in paragraph (a)(1) of this clause:

(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.

6 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(ii) Costs incurred by subcontractors or suppliers.

(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.

(iv) Payments made or amounts payable to the subcontractors or suppliers, except for--

(A) completed work, including partial deliveries, to which the Contractor has acquired title; and

(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.

(5) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor (ii) the value, for progress payment purposes, of the incomplete work.

Incomplete work shall be considered to be the supplies and services required by this contract, for which delivery and invoicing by the

Contractor and acceptance by the Government are incomplete.

(6) The total amount of progress payments shall not exceed 80 percent of the total contract price.

(7) If a progress payment or the unliquidated progress payments exceed the amounts permitted by subparagraphs (a)(4) or (a)(5) above, the Contractor shall repay the amount of such excess to the Government on demand.

(8) Notwithstanding any other terms of the contract, the Contractor agrees not to request progress payments in dollar amounts of less than $2,500. The Contracting Officer may make exceptions.

(9) The costs applicable to items delivered, invoiced, and accepted shall not include costs in excess of the contract price of the items.

(b) Liquidation. Except as provided in the Termination for Convenience of the Government clause, all progress payments shall be liquidated by deducting from any payment under this contract, other than advance or progress payments, the unliquidated progress payments, or 80 percent of the amount invoiced, whichever is less. The Contractor shall repay to the Government any amounts required by a retroactive price reduction, after computing liquidations and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly. The Government reserves the right to unilaterally change from the ordinary liquidation rate to an alternate rate when deemed appropriate for proper contract financing.

(c) Reduction or suspension. The Contracting Officer may reduce or suspend progress payments, increase the rate of liquidation, or take a combination of these actions, after finding on substantial evidence any of the following conditions:

(1) The Contractor failed to comply with any material requirement of this contract (which includes paragraphs (f) and (g) below).

(2) Performance of this contract is endangered by the Contractors --

(i) Failure to make progress; or

(ii) Unsatisfactory financial condition.

(3) Inventory allocated to this contract substantially exceeds reasonable requirements.

(4) The Contractor is delinquent in payment of the costs of performing this contract in the ordinary course of business.

(5) The fair value of the undelivered work is less than the amount of unliquidated progress payments for that work.

(6) The Contractor is realizing less profit than that reflected in the establishment of any alternate liquidation rate in paragraph

(b) above, and that rate is less than the progress payment rate stated in subparagraph (a)(1) above.

(d) Title.

(1) Title to the property described in this paragraph (d) shall vest in the Government. Vestiture shall be immediately upon the date of this contract, for property acquired or produced before that date. Otherwise, vestiture shall occur when the property is or should have been allocable or properly chargeable to this contract.

(2) Property, as used in this clause, includes all of the below-described items acquired or produced by the Contractor that are or should be allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices.

(i) Parts, materials, inventories, and work in process;

(ii) Special tooling and special test equipment to which the Government is to acquire title;

7 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(iii) Nondurable (i.e., noncapital) tools, jigs, dies, fixtures, molds, patterns, taps, gauges, test equipment, and other similar manufacturing aids, title to which would not be obtained as special tooling under subparagraph (ii) above; and

(iv) Drawings and technical data, to the extent the Contractor or subcontractors are required to deliver them to the Government by other clauses of this contract.

(3) Although title to property is in the Government under this clause, other applicable clauses of this contract; e.g., the termination clauses, shall determine the handling and disposition of the property.

(4) The Contractor may sell any scrap resulting from production under this contract without requesting the Contracting Officers approval, but the proceeds shall be credited against the costs of performance.

(5) To acquire for its own use or dispose of property to which title is vested in the Government under this clause, the Contractor must obtain the Contracting Officers advance approval of the action and the terms. The Contractor shall

(i) exclude the allocable costs of the property from the costs of contract performance, and

(ii) repay to the Government any amount of unliquidated progress payments allocable to the property. Repayment may be by cash or credit memorandum.

(6) When the Contractor completes all of the obligations under this contract, including liquidation of all progress payments, title shall vest in the Contractor for all property (or the proceeds thereof) not --

(i) Delivered to, and accepted by, the Government under this contract; or

(ii) Incorporated in supplies delivered to, and accepted by, the Government under this contract and to which title is vested in the

Government under this clause.

(7) The terms of this contract concerning liability for Government-furnished property shall not apply to property to which the

Government acquired title solely under this clause.

(e) Risk of loss. Before delivery to and acceptance by the Government, the Contractor shall bear the risk of loss for property, the title to which vests in the Government under this clause, except to the extent the Government expressly assumes the risk. The Contractor shall repay the Government an amount equal to the unliquidated progress payments that are based on costs allocable to property that is lost (see 45.101).

(f) Control of costs and property. The Contractor shall maintain an accounting system and controls adequate for the proper administration of this clause.

(g) Reports, forms, and access to records.

(1) The Contractor shall promptly furnish reports, certificates, financial statements, and other pertinent information (including estimates to complete) reasonably requested by the Contracting Officer for the administration of this clause. Also, the Contractor shall give the Government reasonable opportunity to examine and verify the Contractor's books, records, and accounts.

(2) The Contractor shall furnish estimates to complete that have been developed or updated within six months of the date of the progress payment request. The estimates to complete shall represent the Contractor's best estimate of total costs to complete all remaining contract work required under the contract. The estimates shall include sufficient detail to permit Government verification.

(3) Each Contractor request for progress payment shall:

(i) Be submitted on Standard Form 1443, Contractor's Request for Progress Payment, or the electronic equivalent as required by agency regulations, in accordance with the form instructions and the contract terms; and

(ii) Include any additional supporting documentation requested by the Contracting Officer.

(h) Special terms regarding default. If this contract is terminated under the Default clause,

(i) the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments and

(ii) title shall vest in the Contractor, on full liquidation of progress payments, for all property for which the Government elects not to require delivery under the Default clause. The Government shall be liable for no payment except as provided by the Default clause.

8 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(i) Reservations of rights.

(1) No payment or vesting of title under this clause shall --

(i) Excuse the Contractor from performance of obligations under this contract; or

(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.

(2) The Governments rights and remedies under this clause --

(i) Shall not be exclusive but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(j) Financing payments to subcontractors. The financing payments to subcontractors mentioned in paragraphs (a)(1) and (a)(2) of this clause shall be all financing payments to subcontractors or divisions, if the following conditions are met:

(1) The amounts included are limited to --

(i) The unliquidated remainder of financing payments made; plus

(ii) Any unpaid subcontractor requests for financing payments.

(2) The subcontract or interdivisional order is expected to involve a minimum of approximately 6 months between the beginning of work and the first delivery, or, if the subcontractor is a small business concern, 4 months.

(3) If the financing payments are in the form or progress payments, the terms of the subcontract or interdivisional order concerning progress payments --

(i) Are substantially similar to the terms of the clause for any subcontractor that is a large business concern, or that clause with its Alternate I for any subcontractor that is a small business concern;

(ii) Are at least as favorable to the Government as the terms of this clause;

(iii) Are not more favorable to the subcontractor or division than the terms of this clause are to the Contractor;

(iv) Are in conformance with the requirements of FAR 32.504(e); and

(v) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the

Governments right to require delivery of the property to the Government if --

(A) The Contractor defaults; or

(B) The subcontractor becomes bankrupt or insolvent.

(4) If the financing payments are in the form of performance-based payments, the terms of the subcontract or interdivisional order concerning payments--

(i) Are substantially similar to the Performance-Based Payments clause at FAR 52.232-32 and meet the criteria for, and definition of, performance-based payments in FAR Part 32;

(ii) Are in conformance with the requirements of FAR 32.504(f); and

(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the

Governments right to require delivery of the property to the Government if--

(A) The Contractor defaults; or

(B) The subcontractor becomes bankrupt or insolvent.

(5) If the financing payments are in the form of commercial item financing payments, the terms of the subcontract or interdivisional order concerning payments

(i) Are constructed in accordance with FAR 32.206(c) and included in a subcontract for a commercial item purchase that meets the

9 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

definition and standards for acquisition of commercial items in FAR Part 2 and 12;

(ii) Are in conformance with the requirements of FAR 32.504(g); and

(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the

Governments right to require delivery of the property to the Government if--

(A) The Contractor defaults; or

(B) The subcontractor becomes bankrupt or insolvent.

(6) If financing is in the form of progress payments, the progress payment rate in the subcontract is the customary rate used by the contracting agency, depending on whether the subcontractor is or is not a small business concern.

(7) Concerning any proceeds received by the Government for property to which title has vested in the Government under the subcontract terms, the parties agree that the proceeds shall be applied to reducing any unliquidated financing payments by the Government to the

Contractor under this contract.

(8) If no unliquidated financing payments to the Contractor remain, but there are unliquidated financing payments that the Contractor has made to any subcontractor, the Contractor shall be subrogated to all the rights the Government obtained through the terms required by this clause to be in any subcontract, as if all such rights had been assigned and transferred to the Contractor.

(9) To facilitate small business participation in subcontracting under this contract, the Contractor shall provide financing payments to small business concerns, in conformity with the standards for customary contract financing payments stated in Subpart 32.113. The

Contractor shall not consider the need for such financing payments as a handicap or adverse factor in the award of subcontracts.

(k) Limitations on undefinitized contract actions. Notwithstanding any other progress payment provisions in this contract, progress payments may not exceed 80 percent of costs incurred on work accomplished under undefinitized contract actions. A contract action is any action resulting in a contract, as defined in Subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes. This limitation shall apply to the costs incurred, as computed in accordance with paragraph (a) of this clause, and shall remain in effect until the contract action is definitized. Costs incurred which are subject to this limitation shall be segregated on Contractor progress payment requests and invoices from those costs eligible for higher progress payment rates. For purposes of progress payment liquidation, as described in paragraph (b) of this clause, progress payments for undefinitized contract actions shall be liquidated at 80 percent of the amount invoiced for work performed under the undefinitized contract action as long as the contract action remains undefinitized. The amount of unliquidated progress payments for undefinitized contract actions shall not exceed 80 percent of the maximum liability of the Government under the undefinitized contract action or such lower limit specified elsewhere in the contract. Separate limits may be specified for separate actions.

(l) Due date. The designated payment office will make progress payments on the 30th day after the designated billing office receives a proper progress payment request. In the event that the Government requires an audit or other review of a specific progress payment request to ensure compliance with the terms and conditions of the contract, the designated payment office is not compelled to make a payment by the specified due date. Progress payments are considered contract financing and are not subject to the interest penalty provisions of the Prompt Payment Act.

(m) Progress payments under indefinitedelivery contracts. The Contractor shall account for and submit progress payment requests under individual orders as if the order constituted a separate contract, unless otherwise specified in this contract.

(End of Clause)

I-14 CHANGED 252.234-7002 EARNED VALUE MANAGEMENT SYSTEM (DEVIATION 2015-O0017) SEP/2015

(DEV 2015-

O0017)

(a) Definitions. As used in this clause--

"Acceptable earned value management system" means an earned value management system that generally complies with system criteria in paragraph (b) of this clause.

"Earned value management system" means an earned value management system that complies with the earned value management system guidelines in the ANSI/EIA-748.

"Significant deficiency" means a shortcoming in the system that materially affects the ability of officials of the Department of Defense to rely upon information produced by the system that is needed for management purposes.

10 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(b) System criteria. In the performance of this contract, the Contractor shall use--

(1) An Earned Value Management System (EVMS) that complies with the EVMS guidelines in the American National Standards

Institute/Electronic Industries Alliance Standard 748, Earned Value Management Systems (ANSI/EIA-748); and

(2) Management procedures that provide for generation of timely, reliable, and verifiable information for the Contract Performance

Report (CPR) and the Integrated Master Schedule (IMS) required by the CPR and IMS data items of this contract.

(c) If this contract has a value of $100 million or more, the Contractor shall use an EVMS that has been determined to be acceptable by the Cognizant Federal Agency (CFA). If, at the time of award, the Contractors EVMS has not been determined by the CFA to be in compliance with the EVMS guidelines as stated in paragraph (b)(1) of this clause, the Contractor shall apply its current system to the contract and shall take necessary actions to meet the milestones in the Contractors EVMS plan.

(d) If this contract has a value of less than $100 million, the Government will not make a formal determination that the Contractors

EVMS complies with the EVMS guidelines in ANSI/EIA-748 with respect to the contract. The use of the Contractors EVMS for this contract does not imply a Government determination of the Contractors compliance with the EVMS guidelines in ANSI/EIA-748 for application to future contracts. The Government will allow the use of a Contractors EVMS that has been formally reviewed and determined by the CFA to be in compliance with the EVMS guidelines in ANSI/EIA-748.

(e) The Contractor shall submit notification of any proposed substantive changes to the EVMS procedures and the impact of those changes to the CFA. If this contract has a value of $100 million or more, unless a waiver is granted by the CFA, any EVMS changes proposed by the Contractor require approval of the CFA prior to implementation. The CFA will advise the Contractor of the acceptability of such changes as soon as practicable (generally within 30 calendar days) after receipt of the Contractors notice of proposed changes. If the

CFA waives the advance approval requirements, the Contractor shall disclose EVMS changes to the CFA at least 14 calendar days prior to the effective date of implementation.

(f) The Government will schedule integrated baseline reviews as early as practicable, and the review process will be conducted not later than 180 calendar days after--

(1) Contract award;

(2) The exercise of significant contract options; and

(3) The incorporation of major modifications.

During such reviews, the Government and the Contractor will jointly assess the Contractors baseline to be used for performance measurement to ensure complete coverage of the statement of work, logical scheduling of the work activities, adequate resourcing, and identification of inherent risks.

(g) The Contractor shall provide access to all pertinent records and data requested by the Contracting Officer or duly authorized representative as necessary to permit Government surveillance to ensure that the EVMS complies, and continues to comply, with the performance criteria referenced in paragraph (b) of this clause.

(h) When indicated by contract performance, the Contractor shall submit a request for approval to initiate an over-target baseline or over-target schedule to the Contracting Officer. The request shall include a top-level projection of cost and/or schedule growth, a determination of whether or not performance variances will be retained, and a schedule of implementation for the rebaselining. The

Government will acknowledge receipt of the request in a timely manner (generally within 30 calendar days).

(i) Significant deficiencies. (1) The Contracting Officer will provide an initial determination to the Contractor, in writing, of any significant deficiencies. The initial determination will describe the deficiency in sufficient detail to allow the Contractor to understand the deficiency.

(2) The Contractor shall respond within 30 days to a written initial determination from the Contracting Officer that identifies significant deficiencies in the Contractor's EVMS. If the Contractor disagrees with the initial determination, the Contractor shall state, in writing, its rationale for disagreeing.

(3) The Contracting Officer will evaluate the Contractor's response and notify the Contractor, in writing, of the Contracting

Officers final determination concerning--

(i) Remaining significant deficiencies;

(ii) The adequacy of any proposed or completed corrective action;

(iii) System noncompliance, when the Contractors existing EVMS fails to comply with the earned value management system guidelines

11 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

in the ANSI/EIA-748; and

(iv) System disapproval, if initial EVMS validation is not successfully completed within the timeframe approved by the Contracting

Officer, or if the Contracting Officer determines that the Contractor's earned value management system contains one or more significant deficiencies in high-risk guidelines in ANSI/EIA-748 standards (guidelines 1, 3, 6, 7, 8, 9, 10, 12, 16, 21, 23, 26, 27, 28, 30, or 32).

When the Contracting Officer determines that the existing earned value management system contains one or more significant deficiencies in one or more of the remaining 16 guidelines in ANSI/EIA-748 standards, the Contracting Officer will use discretion to disapprove the system based on input received from functional specialists and the auditor.

(4) If the Contractor receives the Contracting Officers final determination of significant deficiencies, the Contractor shall, within

45 days of receipt of the final determination, either correct the significant deficiencies or submit an acceptable corrective action plan showing milestones and actions to eliminate the significant deficiencies.

(j) Withholding payments. If the Contracting Officer makes a final determination to disapprove the Contractors EVMS, and the contract includes the clause at 252.242-7005, Contractor Business Systems, the Contracting Officer will withhold payments in accordance with that clause.

(k) With the exception of paragraphs (i) and (j) of this clause, the Contractor shall require its subcontractors to comply with EVMS requirements as follows:

(1) For subcontracts valued at $100 million or more, the following subcontractors shall comply with the requirements of this clause:

-1-

(2) For subcontracts valued at less than $100 million, the following subcontractors shall comply with the requirements of this clause, excluding the requirements of paragraph (c) of this clause:

-2-

(End of clause)

I-15 CHANGED 52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT OCT/2015

(a) Definitions. As used in this clause--

"Agent" means any individual, including a director, an officer, an employee, or an independent Contractor, authorized to act on behalf of the organization.

"Full cooperation"--

(1) Means disclosure to the Government of the information sufficient for law enforcement to identify the nature and extent of the offense and the individuals responsible for the conduct. It includes providing timely and complete response to Government auditors and investigators' request for documents and access to employees with information;

(2) Does not foreclose any Contractor rights arising in law, the FAR, or the terms of the contract. It does not require--

(i) A Contractor to waive its attorney-client privilege or the protections afforded by the attorney work product doctrine; or

(ii) Any officer, director, owner, or employee of the Contractor, including a sole proprietor, to waive his or her attorney client privilege or Fifth Amendment rights; and

(3) Does not restrict a Contractor from--

(i) Conducting an internal investigation; or

(ii) Defending a proceeding or dispute arising under the contract or related to a potential or disclosed violation.

"Principal" means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).

"Subcontract" means any contract entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract.

"Subcontractor" means any supplier, distributor, vendor, or firm that furnished supplies or services to or for a prime contractor or

12 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

another subcontractor.

"United States," means the 50 States, the District of Columbia, and outlying areas.

(b) Code of business ethics and conduct.

(1) Within 30 days after contract award, unless the Contracting Officer establishes a longer time period, the Contractor shall--

(i) Have a written code of business ethics and conduct; and

(ii) Make a copy of the code available to each employee engaged in performance of the contract.

(2) The Contractor shall--

(i) Exercise due diligence to prevent and detect criminal conduct; and

(ii) Otherwise promote an organizational culture that encourages ethical conduct and a commitment to compliance with the law.

(3)(i) The Contractor shall timely disclose, in writing, to the agency Office of the Inspector General (OIG), with a copy to the

Contracting Officer, whenever, in connection with the award, performance, or closeout of this contract or any subcontract thereunder, the Contractor has credible evidence that a principal, employee, agent, or subcontractor of the Contractor has committed--

(A) A violation of Federal criminal law involving fraud, conflict of interest, bribery, or gratuity violations found in Title 18 of the United States Code; or

(B) A violation of the civil False Claims Act (31 U.S.C. 3729-3733).

(ii) The Government, to the extent permitted by law and regulation, will safeguard and treat information obtained pursuant to the

Contractors disclosure as confidential where the information has been marked confidential or proprietary by the company. To the extent permitted by law and regulation, such information will not be released by the Government to the public pursuant to a Freedom of

Information Act request, 5 U.S.C. Section 552, without prior notification to the Contractor. The Government may transfer documents provided by the Contractor to any department or agency within the Executive Branch if the information relates to matters within the organizations jurisdiction.

(iii) If the violation relates to an order against a Governmentwide acquisition contract, a multi-agency contract, a multiple-award schedule contract such as the Federal Supply Schedule, or any other procurement instrument intended for use by multiple agencies, the

Contractor shall notify the OIG of the ordering agency and the IG of the agency responsible for the basic contract.

(c) Business ethics awareness and compliance program and internal control system. This paragraph (c) does not apply if the Contractor has represented itself as a small business concern pursuant to the award of this contract or if this contract is for the acquisition of a commercial item as defined at FAR 2.101. The Contractor shall establish the following within 90 days after contract award, unless the

Contracting Officer establishes a longer time period:

(1) An ongoing business ethics awareness and compliance program.

(i) This program shall include reasonable steps to communicate periodically and in a practical manner the Contractors standards and procedures and other aspects of the Contractors business ethics awareness and compliance program and internal control system, by conducting effective training programs and otherwise disseminating information appropriate to an individuals respective roles and responsibilities.

(ii) The training conducted under this program shall be provided to the Contractors principals and employees, and as appropriate, the Contractors agents and subcontractors.

(2) An internal control system.

(i) The Contractors internal control system shall--

(A) Establish standards and procedures to facilitate timely discovery of improper conduct in connection with Government contracts;

and

(B) Ensure corrective measures are promptly instituted and carried out.

(ii) At a minimum, the Contractors internal control system shall provide for the following:

(A) Assignment of responsibility at a sufficiently high level and adequate resources to ensure effectiveness of the business

13 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

ethics awareness and compliance program and internal control system.

(B) Reasonable efforts not to include an individual as a principal, whom due diligence would have exposed as having engaged in conduct that is in conflict with the Contractors code of business ethics and conduct.

(C) Periodic reviews of company business practices, procedures, policies, and internal controls for compliance with the

Contractors code of business ethics and conduct and the special requirements of Government contracting, including--

(1) Monitoring and auditing to detect criminal conduct;

(2) Periodic evaluation of the effectiveness of the business ethics awareness and compliance program and internal control system, especially if criminal conduct has been detected; and

(3) Periodic assessment of the risk of criminal conduct, with appropriate steps to design, implement, or modify the business ethics awareness and compliance program and the internal control system as necessary to reduce the risk of criminal conduct identified through this process.

(D) An internal reporting mechanism, such as a hotline, which allows for anonymity or confidentiality, by which employees may report suspected instances of improper conduct, and instructions that encourage employees to make such reports.

(E) Disciplinary action for improper conduct or for failing to take reasonable steps to prevent or detect improper conduct.

(F) Timely disclosure, in writing, to the agency OIG, with a copy to the Contracting Officer, whenever, in connection with the award, performance, or closeout of any Government contract performed by the Contractor or a subcontract thereunder, the Contractor has credible evidence that a principal, employee, agent, or subcontractor of the Contractor has committed a violation of Federal criminal law involving fraud, conflict of interest, bribery, or gratuity violations found in Title 18 U.S.C. or a violation of the civil False

Claims Act (31 U.S.C. 3729-3733).

(1) If a violation relates to more than one Government contract, the Contractor may make the disclosure to the agency OIG and

Contracting Officer responsible for the largest dollar value contract impacted by the violation.

(2) If the violation relates to an order against a Governmentwide acquisition contract, a multi-agency contract, a multiple-award schedule contract such as the Federal Supply Schedule, or any other procurement instrument intended for use by multiple agencies, the contractor shall notify the OIG of the ordering agency and the IG of the agency responsible for the basic contract, and the respective agencies contracting officers.

(3) The disclosure requirement for an individual contract continues until at least 3 years after final payment on the contract.

(4) The Government will safeguard such disclosures in accordance with paragraph (b)(3)(ii) of this clause.

(G) Full cooperation with any Government agencies responsible for audits, investigations, or corrective actions.

(d) Subcontracts.

(1) The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts that have a value in excess of $5,500,000 and a performance period of more than 120 days.

(2) In altering this clause to identify the appropriate parties, all disclosures of violation of the civil False Claims Act or of

Federal criminal law shall be directed to the agency Office of the Inspector General, with a copy to the Contracting Officer.

(End of clause)

I-16 CHANGED 52.219-9 (DEV SMALL BUSINESS SUBCONTRACTING PLAN (DEVIATION 2013-O0014) (OCT OCT/2001

2013-O0014) 2015) -- ALTERNATE II (OCT 2001)

(a) This clause does not apply to small business concerns.

(b) Definitions. As used in this clause--

"Alaska Native Corporation (ANC)" means any Regional Corporation, Village Corporation, Urban Corporation, or Group Corporation organized under the laws of the State of Alaska in accordance with the Alaska Native Claims Settlement Act, as amended (43 U.S.C. 1601, et seq.)

and which is considered a minority and economically disadvantaged concern under the criteria at 43 U.S.C. 1626(e)(1). This definition also includes ANC direct and indirect subsidiary corporations, joint ventures, and partnerships that meet the requirements of 43 U.S.C.

1626(e)(2).

14 46

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

"Commercial item" means a product or service that satisfies the definition of commercial item in section 2.101 of the Federal

Acquisition Regulation.

"Commercial plan" means a subcontracting plan (including goals) that covers the offerors fiscal year and that applies to the entire production of commercial items…