W56HZV-22-R-0036 0001.pdf
PDF 87 KB Posted
- Attached to
- Barrel Action
- Solicitation number
- W56HZV-22-R-0036
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers SAM.gov.xlsx | XLSX spreadsheet | |
| XM2010 Purchase Description_from M24E1 W15QKN-10-D-0504 SIGNED COMBINED.pdf | ||
| Files to view 2D-3D Files.doc | DOC document | |
| W56HZV22R0036.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No.
3. Effective Date
4. Requisition/Purchase Req No.
5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)
9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In
The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set
Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print)
16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
W56HZV
ACC-DTA
6501 E. 11 MILE RD.
DETROIT ARSENAL, MI 48397-5000
CHERYL A. GALLAGHER
EMAIL: CHERYL.A.GALLAGHER13.CIV@ARMY.MIL
W56HZV-22-R-0036
2022AUG09
X
X 2022NOV11 05:00pm
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 34
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: CHERYL A. GALLAGHER
Buyer Office Symbol/Telephone Number: CCTA-APD-D/(586)282-1345
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
*** End of Narrative A0000 ***
SOLICITATION: W56HZV-22-R-0036
AMENDMENT: 0001
1. The purpose of this Amendment 0001 to Solicitation W56HZV-22-R-0036 is issued to:
a) Change the solicitation close date from 10 September 2022 to 11 November 2022.
SECTION A:__________
b) Remove A.7, Notice of Random Antiterrorism Measures Program (RAMP), as it is not a requirement.
c) Add new paragraph A.7, Distribution and Destruction of Export Control Technical Data Package.
SECTION B:__________
d) Revise CLIN 0011 narrative A001.
e) Change the nomenclature of CLINs 0011, 0012, 0013, and 0021 from M2010 Enhanced Sniper Rifle to Barrel Action.
f) Revise CLIN 0021 narrative B001 to include more detail.
g) Revise CLIN 0031 narrative C001 to include more detail.
h) Delete narrative B001 from ELIN A001.
SECTION C:__________
i) Delete paragraph C.3, Required TAILORING LANGUAGE TO ELIMINATE CLASS I OZONE-DEPLETING SUBSTANCES (CIODS), as it is not required.
j) Delete paragraph C.5, Drawing Limitations, as it is not required.
k) Delete paragraph C.9, Anti-terrorism Training Requirement for Contractor Personnel Traveling Overseas, as it is not required.
l) Delete paragraph C.10, Access and General Protection/Security Policy and Procedures, as it is not required.
m) Delete paragraph C.11, Trusted Associated Sponsorship System (TASS) Program, as it is not required.
n) Delete paragraph C.12, iWatch Training, as it is not required.
o) Delete paragraph C.14, Army Information System (IS) Security Requirement, as it is not required.
p) Delete paragraph C.15, Information Assurance (IA) / Information Technology (IT) Training, as it is not required.
q) Delete paragraph C.16, Threat Awareness Reporting Program, as it is not required. As a result of the changes made in this Section, the paragraph numbers have been revised.
SECTION E:__________
r) Add clause 52.246-11, Higher-Level Contract Quality Requirement.
s) Delete paragraph E.2, Notice Regarding First Article Test Contractor Sample, as it is not required.
t) Delete paragraph E.3, Surface Quality Standards, as it is not required.
u) Delete paragraph E.7, Ballistic Testing, as it is not required.
v) Delete paragraph E.8, Inspection and Acceptance (First Article Approval), as it is not required.
w) Delete paragraph E.12, Use of MIL-STD 1916, as it is not required.
2 34
W56HZV-22-R-0036
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
x) Delete paragraph E.13, Drawings for Inspection, as it is not required.
SECTION H:__________
y) Delete paragraph H.1, Personnel Qualifications Requirement, as it is not required.
SECTION I:__________
z) Add clause 52.246-26, Reporting Nonconforming Items.
aa) Add the fill-in information to clause 52.209-3, First Article Approval Contractor Testing.
ab) Add the fill-in information to clause 52.209-4, First Article Approval Government Testing.
ac) Add clause 52.216-18, Ordering.
ad) Add clause 52.216-21, Requirements.
SECTION J:__________
ae) Revise the contract references for Exhibit A CDRLS A001 A003.
This concludes all Sections affected by this Amendment.
2. All other terms and conditions, except for those addressed above, remain unchanged and are in full force and effect.
*** END OF NARRATIVE A0002 ***
A.1 Background/Description of Action
A.1.1 Under the authority of FAR 16.503, Requirements Contracts, the Government intends to award a single, three-year, Firm Fixed Price
(FFP), Requirements, Long term Contract (LTC) to procure the M2010 Sniper Rifle Barreled Action, which is a component of the M2010
Enhanced Sniper Rifle. This is being solicited as a Small Business Set Aside (SBSA).
A.2 Solicitation Structure
A.2.1 Particular attention should be given to clauses and paragraphs throughout the solicitation that require the contractor to fill in various information.
A.2.2 Ordering Period. There will be three, one-year ordering periods beginning the date of contract award.
A.2.3 Delivery Order Period of Performance. Each delivery order will define a specific performance period within a specific ordering year.
A.2.4 Delivery Order Awards. Future delivery orders will be awarded in accordance with (IAW) FAR Clause 52.216-18, Ordering, and FAR
Clause 52.216-21, Requirement.
A.3 Electronic Contracting
A.3.1 All Army Contracting Command Detroit Arsenal solicitations will be publicized on the System for Award Management website
(https://www.sam.gov ). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.
A.3.2 Please pay close attention to the Issued By block location on the cover page of the solicitation for closing date and time. The closing date and time is based on the local time of the listed location of the Issued By office. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.
A.3.3 Interested offerors shall submit a proposal via email to the Contract Specialist, Cheryl Gallagher at cheryl.a.gallagher13.civ@army.mil and cc the Contracting Officer, Patricia Pierce at patricia.pierce3.civ@army.mil with the subject header: Proposal Submission - W56HZV22R0036 (Company Name). Once a proposal is received, the Contract Specialist will reply with the respective offeror stating receipt of proposal submission.
3 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
A.3.4 It is the responsibility of the Offeror to ensure the proposal/quote is received by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the
Government infrastructure (in this case, received through SAM) by the exact date and time specified on the cover page of this solicitation, it will be determined late. Proposal/quote is defined to mean ALL volumes or parts required in the solicitation are included in the electronic submission.
Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.
A.3.5 Solicitations may remain posted on www.SAM.gov after the solicitation closing date. If the response deadline has passed for the solicitation, vendors will no longer be able to submit electronic responses.
A.3.6 Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of the
Governments intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or Pricing data/information. If an Offeror objects to such release in the base contract or contract modifications, the Offeror must notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for the objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.
A.3.7 Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the
Procurement Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.
A.4 ACKNOWLEDGEMENT OF AMENDMENTS
Acknowledge all the amendments received from the Government by identifying the amendment number and its issue date below:
Amendment Number: Date:
A.5 ARMY CONTRACTING COMMAND DETROIT ARSENAL (DTA) OMBUDSPERSON
Information regarding the Ombudsperson for this contract is located at the following website: https://www.tacom.army.mil/ombudsperson .
(Best viewed using Google Chrome or Microsoft Edge)
A.6 ALL OR NONE
Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.
(1) ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.
(2) OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION WILL BE DEEMED NONRESPONSIVE.
A.7 DISTRIBUTION AND DESTRUCTION OF EXPORT CONTROL TECHNICAL DATA PACKAGE
(a) This solicitation and resulting contract contains technical data whose export is restricted by the Arms Export Control Act (Title
22, U.S.C., Sec 2751, et. seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.
(b) To be eligible to gain access to this export controlled TDP (via SAM.gov) an offeror must have a current DD 2345, Militarily
Critical Technical Data Agreement certification on file with the Defense Logistics Information Service (DLIS). To obtain certification, contractors must submit a DD Form 2345 to the United States (U.S.)/Canada Joint Certification Office (JCO), along with a copy of supporting documentation. DD Form 2345 and instructions can be found on the Joint Certification Program website at:
http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplications/JCP.aspx Processing time is estimated at six (6) to ten (10) weeks after receipt. Upon receipt of certification, an offeror may request the TDP in accordance with the solicitation's
Section C Technical Data Package instructions.
4 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
(c) Upon completion of the purposes for which Government Technical Data has been provided, the offeror, and all subcontractors, vendors, and sub-vendors of the offeror, are required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed.
(d) Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.
*** END OF NARRATIVE A0001 ***
5 34
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
IN THE FOUR DIGIT ITEM NUMBER CLINS THAT FOLLOW, THE
NUMBERING SYSTEM THAT IS USED IS AS FOLLOWS: THE
FIRST THREE DIGITS SIGNIFY ITEM AND THE FOURTH (LAST)
DIGIT SIGNIFIES THE APPLICABLE CONTRACT YEAR, i.e., CLIN 0011 IS FOR THE FIRST ITEM - FIRST ORDERING
YEAR, CLIN 0012 IS FOR THE FIRST ITEM -
SECOND ORDERING YEAR, CLIN 0013 IS FOR THE FIRST ITEM
- THIRD ORDERING YEAR, ETC.
THE FINAL LINE ITEM(S) ASSOCIATED WITH EACH PART,
SUCH AS FAT, WILL BECOME THE LAST ITEM NUMBER IN
NUMERICAL SEQUENCE FOR EACH ITEM, e.g. 0021.
THE FOLLOWING DEFINITIONS APPLY TO THE
ENTIRE SOLICITATION AND RESULTING CONTRACT:
FIRST ORDERING YEAR OF THE CONTRACT IS THE DATE OF
AWARD PLUS 364 DAYS.
SECOND ORDERING YEAR OF THE CONTRACT IS 365 DAYS
THROUGH 729 DAYS AFTER CONTRACT AWARD.
THIRD ORDERING YEAR OF THE CONTRACT IS 730 DAYS
THROUGH 1,094 DAYS AFTER CONTRACT AWARD.
NOTE:
1) THE PRICE APPLICABLE TO AN INDIVIDUAL ORDER IS THE
PRICE FOR THE ORDERING YEAR IN WHICH THE ORDER IS
ISSUED. THE DELIVERY DATE DOES NOT DETERMINE THE
CONTRACT YEAR.
2) THE QUANTITIES IDENTIFIED IN THIS
SOLICITATION AND THE RESULTING CONTRACT ARE ESTIMATES
ONLY AND NOT A REPRESENTATION THEY WILL BE ORDERED,
NOR IS IT A REPRESENTATION THAT CONDITIONS AFFECTING
GOVERNMENT NEEDS WILL BE STABLE.
(End of narrative A001)
0011 FIRST ORDERING YEAR EST 215 EA $ $ ___________________ ______________ __________________
NSN: 1005-01-697-6892
COMMODITY NAME: BARREL ACTION
CLIN CONTRACT TYPE:
Firm Fixed Price
Mfr CAGE: 19200
Mfr Part Number: 13105978
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING REQUIREMENTS SECTION D.1
LEVEL PRESERVATION: Military
LEVEL PACKING: B
6 34
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
7 34
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0012 SECOND ORDERING YEAR EST 70 EA $ $ ____________________ ______________ __________________
NSN: 1005-01-697-6892
COMMODITY NAME: BARREL ACTION
CLIN CONTRACT TYPE:
Firm Fixed Price
Mfr CAGE: 19200
Mfr Part Number: 13105978
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING REQUIREMENTS SECTION D.1
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
8 34
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0013 THIRD ORDERING YEAR EST 70 EA $ $ ___________________ ______________ __________________
NSN: 1005-01-697-6892
COMMODITY NAME: BARREL ACTION
CLIN CONTRACT TYPE:
Firm Fixed Price
Mfr CAGE: 19200
Mfr Part Number: 13105978
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING REQUIREMENTS SECTION D.1
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
9 34
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0021 FIRST ARTICLE TEST- CONTRACTOR 10 EA $ $ ______________________________ ______________ __________________
NSN: 1005-01-697-6892
COMMODITY NAME: BARREL ACTION
CLIN CONTRACT TYPE:
Firm Fixed Price
Mfr CAGE: 19200
Mfr Part Number: 13105978
First Article Test (FAT), Contractor Testing, pursuant to the requirements listed in:
SECTION E:
- E.6, Supplemental Requirements to First Article
Approval (Contractor Testing); and
SECTION I:
- FAR 52.209-3, First Article Approval - Contractor
Testing.
Please refer to Section B, ELIN A001 for the associated First Article Test Report (FATR) requirement.
(End of narrative B001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING REQUIREMENTS SECTION D.1
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Government Approval/Disapproval Days: 30
10 34
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0031 FIRST ARTICLE TEST- GOVERNMENT 3 EA $ $ ______________________________ ______________ __________________
NSN: 1005-01-697-6892
COMMODITY NAME: BARREL ACTION
CLIN CONTRACT TYPE:
Firm Fixed Price
Mfr CAGE: 19200
Mfr Part Number: 13105978
First Article Test (FAT), Government Testing, pursuant to the requirements listed in:
SECTION E:
- E.5, Supplemental Requirements to First Article
Approval (Government Testing); and
SECTION I:
- FAR 52.209-4, First Article Approval - Government
Testing.
Please refer to Section B, ELIN A001 for the associated First Article Test Report (FATR) requirement.
(End of narrative C001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING REQUIREMENTS SECTION D.1
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Government Approval/Disapproval Days: 30
11 34
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
1000 EXHIBIT A- CONTRACT DATA REQUIREMENTS LIST (CDRL) _________________________________________________
A001-A003 _________
A001 FIRST ARTICLE TEST REPORT (FATR) $ ** NSP ** ________________________________ __________________
SERVICE REQUESTED: FATR
A002 ACCEPTANCE INSPECTION EQUIPMENT (AIE) REPORT $ ** NSP ** ____________________________________________ __________________
SERVICE REQUESTED: AIE REPORT
A003 AMMUNITION CONSUMPTION REPORT $ ** NSP ** _____________________________ __________________
SERVICE REQUESTED: AMMUNITION CONSUMPTION REPORT
12 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
C.1 SCOPE OF WORK
C.1.2 The contractor shall prepare and deliver data submissions IAW Attachment 0001 - Purchase Description.
C.2 CONFIGURATION MANAGEMENT DOCUMENTATION
C.2.1 The Configuration Change Management section of SAE EIA-649-1 Configuration Management Requirement for Defense Contracts, Paragraph
3.3, shall be used for configuration control of material with the following exclusions: paragraph 3.3(3); the second sentence of paragraph 3.3.1.8.1(1), and the General Note in paragraph 3.3.2.4(1) which reads as Generally, Minor RFVs address product changes that are temporary and do not impact the baseline.
C.2.2 Furnished item(s) shall conform to the approved configuration requirements/revision, unless a Request for Variance (RFV) is processed and approved as provided by Paragraph E. below. The term "Request for Variance" includes Requests for Deviations and Waivers.
C.2.3 Value Engineering Change Proposals (VECPs) for cost saving improvements to the Technical Data Package (TDP) should not be processed per SAE EIA-649-1 and should be referred to FAR Part 48 Value Engineering.
C.2.4 All Engineering Change Proposals (ECPs) submitted will be deemed routine. If an ECP is considered as an emergency or urgent; that justification for the rationale shall be included in the ECP submittal with all applicable supporting documentation.
C.2.5 For ECPs, RFVs, Notices of Revision (NORs) or Specification Change Notices (SCNs), the Contractor must submit the applicable documentation listed in sub-paragraphs e (i) through e (iv) to the Administrative Contracting Officer (ACO), with an information copy to the Procuring Contracting Officer (PCO). Failure to submit a complete legible package may result in return of the ECP/RFV/SCN/NOR without processing.
(i) Documentation or use of DD Form 1692 (current revision) and delivery of data per DI-SESS-80639 is detailed in paragraph 3.3.1 of EIA-
649-1 for ECPs.
(ii) Documentation or use of DD Form 1694 (current revision) and delivery of data per DI-SESS-80640 is detailed in paragraph 3.3.2 of
EIA-649-1 for RFVs.
(iii) Documentation or use of DD Form 169 (current revision) and delivery of data per DI-SESS-80642 is detailed in paragraph 3.3.4 of
EIA-649-1 for NORs.
(iv) Documentation and delivery of data per DI-SESS-80643 is detailed in Paragraph 3.3.3 of EIA-649-1 for SCNs.
C.2.6 Questions regarding the status of previously submitted ECP or RFV should be directed to the PCO. Incorporation of an approved RFV and/or ECP will require a contract modification execution.
C.2.7 The submission of an ECP/RFV/SCN/NOR does not affect the required delivery date of the contract. If a delivery date change is needed, a contract modification is required.
C.3 TECHNICAL DATA PACKAGE INFORMATION
The following Xd item applies to this solicitation:
[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.
[ X ] 2. The TDP for this solicitation resides within the System for Award Management (SAM) (https://SAM.gov ) associated with this solicitation number:
W56HZV-22-R-0036
To access the data through SAM:
a. Log on to the SAM web site: https://SAM.gov .
b. Search for the solicitation number.
c. Click on the attachment you would like to view.
d. If the attachment is restricted, request access to the document.
(1) TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec 2751, 13 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
et.seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq..
(2) Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.
(3) To obtain these TDPs, contractors must have a current DD 2345, Militarily Critical Technical Data Agreement on file with
Defense Logistics Information Service (DLIS). To obtain certification, go to https://public.logisticsinformationservice.dla.mil/jcp/search.aspx
C.3.1 Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor.
Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.
C.3.2 If technical data is otherwise restricted, select Request Explicit Access. This will generate an email to the Contract Specialist and Contracting Officer at Army Contract Command - Warren (DTA) with all the information needed to grant contractor access to restricted documents. SAM will automatically generate an email stating when the requesting contractor has permission to view or download TDP items.
C.3.3 If multiple individuals in the contractors organization need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP.
Those same individuals MUST be registered in SAM. Any individuals no longer with the company should be deleted. Questions related to registration in SAM should be directed to https://www.sam.gov/ . The SAM helpdesk phone number is (866) 606-8220. Vendors are responsible for placing correct information in SAM.
C.3.4 It is strongly suggested that contractors submit the explicit access request and provide the buyer with the completed Use and Non-
Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.
C.4 REQUIREMENT FOR AN OPSEC STANDING OPERATION PROCEDURE/PLAN
C.4.1 The contractor is subject to provisions of the TACOM LCMC OPSEC Standing Operating Procedures (SOP/Plan), or other U.S. Government
OPSEC plan, per AR 530-1, Operations Security. This SOP/Plan specifies the governments critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.
C.4.2 The contractor will receive a copy of the SOP/Plan at time of award. Local form STA Form 7114 (or similar) will be used to document and record security OPSEC reviews which are conducted by G2, TACOM LCMC or individual organizations supporting OPSEC Officers.
C.4.3 The contractor shall identify an individual who will be an OPSEC Coordinator. The contractor will ensure that this individual is
OPSEC Level I.
C.5 OPSEC TRAINING REQUIREMENT
Per AR 530-1, Operations Security, new contractor employees must complete Level I OPSEC training within 30 calendar days of reporting for duty. All contractor employees must complete annual OPSEC awareness training. OPSEC awareness training is available at:
https://securityawareness.usalearning.gov/opsec/index.htm . Within 10 days of completing the training, the Contractor shall provide certificates/proof of completion to the Contracting Officers Representative (COR), if assigned to the contract, or the Procuring
Contracting Officer (PCO).
*** END OF NARRATIVE C0001 ***
14 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION E - INSPECTION AND ACCEPTANCE
Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________
E-1 CHANGED 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014
(a) The contractor shall comply with the higher-level quality standard(s) listed below.
Untailored
(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
E.1 INSPECTION AND ACCEPTANCE POINTS: ORIGIN ________________________________________
The Government's inspection and acceptance of the supplies offered under this contract/purchase order shall take place at ORIGIN.
Offeror must specify below the exact name, address, and CAGE of the facility where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.
INSPECTION POINT: __________________________________________
(Name) (CAGE)
(Address) (City) (State) (Zip)
ACCEPTANCE POINT: __________________________________________
(Name) (CAGE)
(Address) (City) (State) (Zip)
E.2 REWORK AND REPAIR OF NONCONFORMING MATERIAL ___________________________________________
E.2.1 Rework and Repair are defined as follows:
E.2.1.1 Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
E.2.1.2 Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not eliminate the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all the applicable drawings, specifications, or contract requirements.
E.2.2 Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the
Government Representative for review and approval prior to implementation. Rework procedures are subject to the Governments disapproval.
E.2.3 Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, to the Contracting
Officer for review and written Government approval prior to implementation.
E.2.4 Whenever the Contractor submits a repair or rework procedure for Government review and approval, the submission shall also include a description of the cause for the nonconformances, and a description of the action taken or to be taken to prevent recurrence.
E.2.5 The Government approved rework or repair procedure shall also contain a provision for re-inspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
E.3 ACCEPTANCE INSPECTION EQUIPMENT (AIE) _____________________________________
E.3.1 The contractor shall use a calibration system with traceability to a national or international standard for the AIE IAW CDRL A002
ACCEPTANCE INSPECTION EQUIPMENT used on this contract.
15 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
E.3.2 The contractor shall provide all AIE (except for any AIE listed as available in Section H or Appendix I) necessary to assure conformance of material to the contract requirements.
E.3.3 AIE shall be available for use on the First Article (FA) submission, if FAT is required, or prior to use for acceptance of production material on this contract.
E.3.4 Contractor furnished AIE shall be made (i) to the AIE designs specified in Section C, or (ii) to any other design provided the contractor's proposed AIE design is approved by the Government. Contractor's proposed AIE design for inspection of characteristics listed as "Critical, Special or Major" shall be submitted to the Government for review and approval as directed on the Contract Data
Requirements List, DD Form 1423. Government approval of AIE design shall not be considered to modify the contract requirements.
E.3.5 When the contractor submits its proposed AIE on commercial off the shelf equipment, the contractor shall include the manufacturer's name and model number, and sufficient information to show capability of the proposed AIE to perform the inspection required. When submitting proposed AIE design documentation on commercial computer-controlled test and measuring equipment include information on (1) test program listing (2) flowcharts showing accept and reject limits and computer-generated test stimuli (3) calibration program listing (4) sample of the printout of an actual test and calibration (5) test plan to verify accuracy of inspection and correctness of accept or reject decision (6) identification of the equipment by model name and number.
E.3.6 Resubmission of the contractor's proposed AIE design for Government approval on a follow-on Government contract is not required, provided the inspection characteristic parameters specified in the technical data package and the previously Government approved AIE designs have not changed. In this situation, the contractor shall provide written correspondence in the place of the AIE designs that indicates the prior Government approval and states that no changes have occurred.
E.3.7 The Government reserves the right to disapprove, at any time during the performance of this contract, any AIE that is not accomplishing its intended use in verifying an inspection or test characteristic.
E.3.8 If the contractor changes the design after the initial approval, the modified design must be submitted for approval prior to use.
E.4 GOVERNMENT FURNISHED AMMUNITION (GFA) _____________________________________
E.4.1 Ammunition has been programmed to support contractual test requirements as follows:
Rounds: 40* rounds per Barrel Action
*Total number of rounds determined at the delivery order level
Cartridges: .300 Winchester Magnum
Type: MK 248 MOD 1
National Stock Number: 1305-01-018-1547
Part Number: 8330252
Department of Defense Identification Code: AB43
E.4.2 Contractor FAT requires testing on 5 Barreled Actions. In support of contractor FAT, the following GFA is required:
Rounds: 200 (40 Rounds per barreled action)
Cartridges: .300 Winchester Magnum, Match Grade, MK 248 MOD 1
National Stock Number: 1305-01-568-7504
Department of Defense Identification Code: AB43
E.4.2.1 High Pressure Resistance: 1 per barrel.
E.4.2.2 Targeting and Accuracy: 30 per barrel.
E.4.2.3 Muzzle Velocity: 5 per barrel.
E.4.3 Government FAT requires testing on 3 Barreled Actions. In support of contractor FAT, the following GFA is required:
Rounds: 39,300 rounds (31,800 if Endurance and Reliability combined)
Cartridges: .300 Winchester Magnum, Match Grade, MK 248 MOD 1
National Stock Number 1305-01-568-7504
Department of Defense Identification Code: AB43
E.4.3.1 Endurance: 10,000 rounds per barrel
E.4.3.2 Reliability: 2,600 rounds per barrel
E.4.3.3 Cold Temperature functioning: 300 rounds per barrel
E.4.3.4 Hot Temperature functioning: 300 rounds per barrel
E.4.4 Requests for all ammunition shall be submitted electronically to the contract specialist on DD Form 1348 no later than 90 days prior to desired delivery dates. The completed request may be submitted via electronic mail to the Contracting Officer, and usarmy.detroit.tacom.mbx.ilsc-mca@army.mil.
16 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
E.4.5 The contractor shall be responsible for reporting on the status of ammunition expenditures throughout the life of the contract as follows:
E.4.5.1 Every 90 days after the initial receipt of government furnished ammunition, the contractor shall provide an ammunition consumption report in accordance with (IAW) CDRL A003 - Government Furnished Ammunition Request to the Contracting Officer.
E.4.5.2 No later than 30 days after completion of the contract, the contractor shall report to the Contracting Officer on the remaining ammunition IAW CDRL A003. The contractor shall request disposition instructions for the remaining ammunition. The contractor shall execute the disposition instructions and provide confirmation to the Contracting Officer.
E.4.6 The contractor shall furnish a copy of the above ammunition reports and disposition requests to the cognizant Defense Contract
Management Agency (DCMA) Quality Assurance Representative (QAR) and to the Government Furnished Material/Management Control Activity
(GFM/MCA), at usarmy.detroit.tacom.mbx.ilsc-mca@army.mil.
E.5 SUPPLEMENTAL REQUIREMENTS TO FIRST ARTICLE APPROVAL (GOVERNMENT TESTING) ________________________________________________________________________
E.5.1 In accordance with the requirements under FAR clause 52.209-4, found in Section I of this document, the first article approval item(s) shall be examined and tested as required by the item specification(s), Quality Assurance Provisions (QAPs) and all drawings listed in the Technical Data Package.
E.5.2 The first article shall be delivered by the Contractor Free on Board (FOB) destination except when transportation protective service or transportation security is required by other provision of this contract. If such is the case, the first article shall be delivered FOB origin and shipped on Government Bill of Lading.
E.5.3 The first article shall be representative of items to be manufactured using the same processes and procedures as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have been produced by the
Contractor (including subcontractors) using the technical data package provided by the Government.
E.5.4 Prior to delivery, each of the first article assemblies, subassemblies, and components shall be inspected by the Contractor for all contract, drawing, QAP and specification requirements except for the tests indicated below: -1- (buyer copy/paste requirements from engineering here) The Contractor shall provide to the Contracting Officer at least 15 calendar days advance notice of the schedule date for final inspection of the first article. Those inspections which are of a destructive nature shall be performed upon additional sample parts selected from the same lot(s) or batch(es) from which the first article was selected. Results of contractor inspections (including supplier's and vendor's inspection records when applicable) shall be verified by the Government Quality Assurance Representative (QAR).
One copy of the contractor's inspection report with evidence of the QAR's verification shall be forwarded with the first article; two copies shall be provided to the Contracting Officer. Upon delivery to the Government, the first article shall be subjected to inspection for contract, drawing, specification, and QAP requirements as stated separately in Section E of the contract.
E.5.5 Notwithstanding the provisions for waiver of first article, an additional first article sample or portion thereof, may be ordered by the Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of 90 days, or (iii) whenever a change occurs in the place of performance, manufacturing process, material used, drawing, specification or source supply. When conditions (i), (ii), or (iii) above occurs, the Contractor shall notify the Contracting Officer so that a determination can be made concerning the need for an additional first article sample or portion thereof, and instructions provided concerning the submission, inspection, and notification of results. Costs of the additional first article testing resulting from any of the causes listed herein that were instituted by the contractor and not due to changes directed by the Government shall be borne by the Contractor.
E.5.6 Rejected first articles or portions thereof not destroyed during inspection and testing will be held at the government first article test site for a period of 30 days following the date of notification of rejection, pending receipt of instructions from the
Contractor for the disposition of the rejected material. The Contractor agrees that failure to furnish such instructions within said 30-day period shall constitute abandonment of said material by the Contractor and shall confer upon the Government the right to destroy or otherwise dispose of the rejected items at the discretion of the Government without liability to the Contractor by reason of such destruction or disposition.
E.6 SUPPLEMENTAL REQUIREMENTS TO FIRST ARTICLE APPROVAL (CONTRACTOR TESTING) ________________________________________________________________________
E.6.1 In accordance with the requirements under FAR clause 52.209-3, found in Section I of this document, the first article approval item(s) shall be examined and tested as required by the item specification(s), Quality Assurance Provisions (QAPs) and all drawings listed in the Technical Data Package.
E.6.2 The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have
17 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
been produced by the Contractor (including subcontractors) using the technical data package applicable to this procurement.
E.6.3 The first article shall be inspected and tested by the contractor for all requirements of the drawing(s), the QAPs, and specification(s) referenced thereon, except for:
E.6.3.1 Inspections and tests contained in material specifications provided that the required inspection and tests have been performed within the last year and the results are submitted with the Certificates of Conformance are submitted with the First Article Test
Report.
E.6.3.2 Inspections and tests for Military Standard (MS) components and parts provided that inspection and tests have been performed previously and certifications for the components and parts are submitted with the First Article Test Report.
E.6.3.3 Corrosion resistance tests over 10 days in length provided that a test specimen or sample representing the same process has successfully passed the same test within 30 days prior to processing the first article, and results of the tests are submitted with the
First Article Test Report.
E.6.3.4 Life cycle tests over 10 days in length provided that the same or similar items manufactured using the same processes have successfully passed the same test within 1 year prior to processing the first article and results of the tests are submitted with the
First Article Test Report.
E.6.3.5 Onetime qualification tests, which are defined as a one-time on the drawing(s), provided that the same or similar item manufactured using the same processes has successfully passed the tests, and results of the test are on file at the contractor's facility and certifications are submitted with the First Article Test Report.
E.6.4 Those inspections which are of a destructive nature shall be performed upon additional sample parts selected from the same lot(s) or batch(es) from which the first article was selected.
E.6.5 A First Article Test Report shall be compiled by the contractor documenting the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable) IAW CDRL A001 First Article Test Report. The First
Article Test Report shall include actual inspection and test results to include all measurements, recorded test data, and certifications
(if applicable) keyed to each drawing, specification and QAP requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. Evidence of the QAR's verification will be provided. One copy of the
First Article Test Report will be copy furnished to the Contracting Officer, Patricia Pierce, patricia.pierce3.civ@army.mil.
E.6.6 Notwithstanding the provisions for waiver of first article, an additional first article sample or portion thereof, may be ordered by the Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of 90 days, or (iii) whenever a change occurs in place of performance, manufacturing process, material used, drawing, specification or source of supply. When conditions (i), (ii), or (iii) above occurs, the Contractor shall notify the
Contracting Officer so that a determination can be made concerning the need for the additional first article sample or portion thereof, and instructions provided concerning the submission, inspection, and notification of results. Costs of the additional first article testing resulting from any of the causes listed herein that were instituted by the contractor and not due to changes directed by the
Government shall be borne by the Contractor.
*** END OF NARRATIVE E0001 ***
18 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION F - DELIVERIES OR PERFORMANCE
Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________
F-1 CHANGED 52.211-8 TIME OF DELIVERY JUN/1997
(a) The Government requires delivery to be made according to the following schedule:
REQUIRED DELIVERY SCHEDULE
CLIN NO. QUANTITY WITHIN DAYS AFTER
DATE OF DELIVERY ORDER AWARD
0011 EST 215 EA; 25 EA/Month 240 Days without FAT; 330 Days with FAT
0012 EST 70 EA; 25 EA/Month 240 Days without FAT; 330 Days with FAT
0013 EST 70 EA; 25 EA/Month 240 Days without FAT; 330 Days with FAT
0021 FAT - Contractor 300 Days
0031 FAT - Government 300 Days
NOTE: Early delivery is acceptable at no cost to the Government.
The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.
OFFERORS PROPOSED DELIVERY SCHEDULE
CLIN NO. QUANTITY WITHIN DAYS AFTER
DATE OF DELIVERY ORDER AWARD
0011 EST 215 EA; 25 EA/Month Days without FAT; or 90 additional days if FAT is required ___
0012 EST 70 EA; 25 EA/Month Days without FAT; or 90 additional days if FAT is required ___
0013 EST 70 EA; 25 EA/Month Days without FAT; or 90 additional days if FAT is required ___
NOTE: CLINs 0021 and 0031 -- Offerors may not propose an alternative Delivery Schedule for these CLINs.
(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed, or otherwise furnished to the successful offeror, results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day award is dated. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the
Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the
Contractors date of receipt of the contract or notice of award by adding
(1) five calendar days for delivery of the award through the ordinary mails, or
(2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term working day excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.
(End of Clause)
19 34
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1 DEMILITARIZATION AND TRADE SECURITY CONTROL REQUIREMENTS AND PROCEDURES
I. Demil and/or Trade Security Controls (TSCs) Summary:
H.1.1 This procurement action has a Demil and/or TSC consideration requirement. The Demil and Trade Security Control provisions in this solicitation implement the policy and requirements of the Arms Export Control Act, 22 United States Code (U.S.C.), Section 2778, the
International Traffic in Arms Regulations (ITAR) at 22 Code of Federal Regulations (CFR), Parts 120-130, the Export Administration
Regulations (EAR), at 15 CFR 730-774 and the Export Administration Act. Regulatory requirements and guidance are contained in Federal
Acquisition Regulation (FAR) 45.6, Reporting, Redistribution, and Disposal of Contractor Inventory and Defense Federal Acquisition
Regulation (DFAR) 245.604, Restrictions on Purchase or Retention of Contractor Inventory.
H.1.2 Demil and TSC policy is promulgated via Department of Defense (DoD) regulations and in the establishment of contract requirements.
Accordingly, the governments right to require demilitarization under this clause is a contractual right, subject to the authority and discretion of the Procuring Contracting Officer (PCO).