Attachment 0004-Request for Use of Prohibited Materials.doc
DOC document 72 KB Posted
- Attached to
- Water Storage Distribution System (WSDS) Federal contract opportunity
- Solicitation number
- W56HZV21R0011
About this file
This document contains a request for use of prohibited materials attachment related to a federal contract opportunity for a Water Storage Distribution System. The U.S. Army Contracting Command-Detroit Arsenal intends to solicit for the procurement of 123 Water Storage Distribution Systems to provide large water intake, purification and distribution capacity to the Army. Of the 123 systems, 87 will have a 100,000 gallon storage capacity and 36 will be configurable as either a single 100,000 gallon unit or two separate 50,000 gallon units. The contract will also include an estimated 150 fluid distribution pumps with 350 gallons per minute capacity. The Government will utilize a two-phase approach, first soliciting proposals for testing of sample pumps from up to five awardees under IDIQ contracts. After testing, the Government will evaluate test results along with revised price proposals to select a single vendor through fair opportunity procedures to receive a modification for full system production and logistics support under Phase II of the contract. The procurement is set aside entirely for small businesses.
View the file
Other files for this federal contract opportunity
Show all 48
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
Attachment 0004 Request for Use of Prohibited Materials
04 November 2014 Distribution Statement A – Approved for Public Release; distribution unlimited
(*Distribution Statement A only applies when form is not filled in. Once filled check the Security Class Guide for proper distribution statement/markings)
1. General Information
Requesting Company
Date of Request
Point of Contact
Prohibited material for which waiver is requested
2. Explanation of Use
Instructions: Provide a description of the parts/processes where the prohibited material will be used. Identify all components/parts that will contain the prohibited materials upon vehicle delivery including quantities of these parts. Indicate the specific variant and/or trailer the components/parts are on. Identify whether or not the material will be required for operation or maintenance (including during vehicle rebuild). A separate spreadsheet may be attached listing the specific parts/processes, if needed.
3. Health Hazard
Instructions: Provide an explanation of any health hazards associated with the use or presence of the prohibited material. Include likely routes of exposure to both the operator and the maintainer. Identify if any personal protective equipment (PPE) that would be required as a result of using this material. Include the type of PPE and under what circumstances it would be required (manufacturing, operation, maintenance, etc.).
4. Analysis of Alternatives
Instructions: Identify all alternatives that were considered for the prohibited material. If the alternative is only for specific applications, identify what type of parts it is a potential alternative for. Include explanation as to why each cannot be implemented.
5. Technical Justification
Instructions: Provide technical justification for the use of prohibited material. Explain why it is necessary and why it cannot be eliminated.
6. Program Risk
Instructions: Describe the program risk(s) (cost, schedule, and performance) associated with denial of this request by the Government.
7. Get Well Plan
Instructions: Identify which parts where an alternative may be integrated at a later date. Provide a get well plan explaining how this will be accomplished. Also, indicate which parts you will not be able to eliminate and provide a brief explanation.
The following Sections will be filled in by the Government
8. Environmental Safety and Occupational Health Working Group (ESOH WG) Evaluation/ Recommendation
Instructions: Government ESOH WG will to provide evaluation of the above information and a recommendation to the Product Director/Project Manager regarding approval/disapproval of the prohibited material request.
{Name1}
{Date1}
JPO XXXX, ESOH WG Date
9. Concurrence
I concur that use of {prohibited material} as described above under the {Contractor Name} Contract –{Contract Number} is acceptable and justified:
{Name2}
{Date2}
JPO XXXX, CHIEF ENGINEER Date {Name3}
{Date3}
Lead Engineer, XXXX Date {Name4}
{Date4}
Product Director, XXXX Date
10. Approval
Upon the basis of the findings above, I hereby determine that use of {prohibited material} in the parts identified in Section 1 for {Contractor Name} Contract {Contract Number}is acceptable and justified.
{Name5}
{Date5}
Project Manager, XXXX Date
UNCLASSIFIED
File details come from the government source that posted it. Updated .