W56HZV-17-R-L568.pdf
PDF 406 KB Posted
- Attached to
- Lab Calibration
- Solicitation number
- W56HZV-17-R-L568
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_1_Rev1.xlsx | XLSX spreadsheet | |
| W56HZV-17-R-L568_Amendment_1.pdf | ||
| Attachment_3_-_CDRLs.DOC | DOC document | |
| Attachment_1.xlsx | XLSX spreadsheet | |
| Attachment_2.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W56HZV-17-R-L568 07-May-2018
b. TELEPHONE NUMBER
586-282-2980
8. OFFER DUE DATE/LOCAL TIME
12:00 AM 06 Jun 2018
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W56HZV9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
JASON D. LADD
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
ARMY CONTRACTING COMMAND - WARREN (DTA)
6501 E. 11 MILE RD
WARREN MI 48397-500
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE W91ATL 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
TARDEC - DETROIT ARSENAL
JOHN LINK
JOHN LINK
RDTA-COS-FS
JOHN.L.LINK.CIV@MAIL.MIL
WARREN MI 48397-5000
TEL: 586-282-6299 FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$20,500,000
NAICS:
811219
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF42
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W56HZV-17-R-L568
Section SF 1449 - CONTINUATION SHEET
PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT (PWS)
TARDEC Calibration
Part 1
General Information
1. GENERAL: This is a non-personal services contract to provide calibration work required to support all laboratories in the Tank Automotive Research Development Engineering Center (TARDEC). The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the contractor who, in turn is responsible to the Government.
1.1 Description of Services/Introduction: TARDEC is seeking a comprehensive, single source to provide calibration for the US Army Test, Measurement and Diagnostic Equipment (TMDE). Calibration support is accomplished using Army resources in order to optimize the use of existing workload capacity. Commercial contracts may be used to provide calibration services when the required support (lack of facilities, time constraints, capabilities, expertise, etc.) is not available within the Army.
1.2 Background: TARDEC is a research and development center with several laboratories that are accredited to the International Organization for Standardization (ISO) 17025 standard. TARDEC’s ISO 17025 accreditation and Army Regulations require the use of calibration laboratories that are accredited to ISO 17025 for the work being performed where available.
1.3 Objective: The objective is to reduce turnaround time (TAT) for calibration services by eliminating the need of establishing multiple contracts to multiple vendors for commercial calibration contracts.
1.4 Scope: The scope of this contract is to provide a single point of entry that will coordinate pick-up and delivery of lab equipment that is due for calibration. Lab equipment is listed in Appendix A along with new equipment calibration requirements as mission dictates. Appendix A is a listing of TMDE representative of the approximate mix of TMDE, but is not all-inclusive and subject to changes as Government owned TMDE is replaced and/or disposed. The Government reserves the right to add items (subject to advance coordination with, and acceptance by, the contractor).
1.5 Requirements: See Section 5 of this Performance Work Statement for specific details.
1.6 Period of Performance: The period of performance shall be for one Base Year of 12 months and 2 option years.
1.7 General Information
1.7.1 Quality Control: The contractor shall develop and maintain an effective quality control program (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which the work it performs will be monitored for compliance. The contractor shall deliver the QCP to the contracting officer (KO) and contracting officer’s representative (COR) within 30 days after contract award (CDRL A003). A copy of the comprehensive written QCP shall be resubmitted to the KO and COR within five working days if changes are needed or required. The contractor shall submit the revised QCP before implementing any changes. After acceptance of the quality control plan, the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system.
1.7.2 Quality Assurance: The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.7.3 Recognized Holidays:
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day
1.7.4 Place of Performance: The work to be performed under this contract will be performed at the contractor’s or subcontractor’s location or performed at the Detroit Arsenal.
1.7.5 Type of Contract: The Government will award a Firm Fixed Price Contract with an overall ceiling limit of $975,000.
1.7.6 Physical Security: The contractor shall be responsible for safeguarding all Government equipment, information and property provided for contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.
1.7.7 Special Qualifications: Subcontractors must be ISO 17025 accredited and provide certifications for all TMDE calibrated as identified in 1.5.4 and 1.5.8 above.
1.7.8 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5.
1.7.09 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract;
perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor’s performance and notify both the Contracting Officer and Contractor of any deficiencies; coordinate availability of Government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting contract.
1.7.10 Key Personnel: The following personnel are considered key personnel by the Government: Contract Manager and Alternate Contract Manager. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 7:30 a.m. and 5:00 p.m., Monday thru Friday except for Federal holidays or when the Government facility is closed for administrative reasons. Contractor shall notify the Contracting Officer of any changes to the Key Personnel. Qualifications for all key personnel are listed below:
1.7.10.1 Contract Manager and Alternate Contract Manager
1.7.10.1.1 Experience with coordinating, executing, and ensuring quality return of TMDE calibration.
1.7.10.1.2 Knowledge of lab and test equipment and ISO procedures.
1.7.11 Identification of Contractor Employees: All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed. Contractor personnel will be required to obtain and display access badges while working on Detroit Arsenal.
1.7.12 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. DEFINITIONS:
2.1.1. CONTRACTOR. A supplier or vendor having a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5. DELIVERABLE. Anything that can be physically delivered but may include non-physical things such as meeting minutes.
2.1.6. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.7. QUALITY ASSURANCE. The Government procedures to verify that services being performed by the
Contractor are performed according to acceptable standards.
2.1.8. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.9. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.10. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.11. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.12. WORK WEEK. Is defined as Monday through Friday, unless specified otherwise.
2.2. ACRONYMS:
ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation
CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial Off the Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
See Attachments 1 and 2
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1 General: The contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, and other items and non-personal services necessary to have equipment calibrated for all laboratories in TARDEC as defined in this Performance Work Statement. The contractor shall perform to the standards set forth in this contract.
PART 5
SPECIFIC TASKS
5.1 The contractor shall be responsible for coordination of calibration services for all TMDE presented for calibration including pick-up and delivery of equipment to TMDE owner specified locations.
5.2 The contractor shall be available to be contacted by telephone and email. The contractor shall receive or be notified of equipment due for calibration and respond to customer’s request within 24 hours.
5.3 The contractor shall be ISO 17025 accredited recognized under ILAC and ensure that the equipment is calibrated at a sub-contract facility be accredited to ISO 17025 recognized by ILAC for the parameter and range of the device being calibrated and that the calibrations performed by the lab are reported on an ISO 17025 accredited certificate.
A copy of the Scope of Accreditation shall be submitted along with a quote from the facility performing the calibration. In the calibration of specific equipment, the contractor is responsible for notifying the TMDE owner to gain approval prior to use of any non-accredited subcontract work. The contractor will ensure that traceability requirements of ISO 17025 Section 5.6 are met by the subcontractor.
5.4 The contractor shall have the option to perform calibrations on site for the convenience of the Government, if and only if the contractor is accredited to ISO 17025 to perform calibrations at customer locations or using mobile facilities.
5.5 If the Government requests that TMDE not listed be calibrated, the contractor shall respond to said requests (accept/decline) by the close of business of the 2nd business day. Business days are defined as 0700-1530, Monday thru Friday, excluding Government holidays. If the request is accepted, the contractor shall provide the Government a cost estimate and adhere to the remainder of these requirements for said TMDE. The Government reserves the right to reject contractor estimates.
5.6 The contractor shall ensure that calibrations are accredited to ISO 17025 for all measurement parameters and ranges required for the calibration of all TMDE. The contractor shall also ensure the laboratory performing the calibration is accredited to ISO 17025, uses methods in the laboratory’s Scope of Accreditation appropriate for the equipment being calibrated, and is capable of operating the equipment IAW the TARDEC specified requirements or when not specified by TARDEC the equipment manufacturer’s specifications shall be utilized while performing the measurement(s) on the equipment to be calibrated.
5.7 The contractor shall report as-found and as-left calibration data, along with the associated measurement uncertainties reported with a coverage factor of k=2 estimating an approximate 95 percent confidence interval, and identify traceability to the Si through the use of an International Laboratory Accreditation Cooperation (ILAC) recognized National Measurement Institute (NMI). Data shall include:
5.7.1 Who calibrated the item
5.7.2 What was calibrated
5.7.3 Date and time when calibrated
5.7.4 Calibration data
5.7.5 Standards traceability back to National Institute of Standards and Technology
5.7.6 Pass/Fail result on report
5.7.7 Location where calibration took place (commercial lab or at TARDEC facilities)
5.8 The contractor’s chosen facility shall have the capability to provide testing, inspection, analysis, and repair services if/when necessary. The contractor or subcontractor shall remove the existing calibration decals (old) and place a new calibration decal in the same location as the old decal, if applicable. The contractor or subcontractor must provide calibration certificates/reports meeting the requirements of ISO 17025 for equipment calibrated. In the event repair is required to return an item to a functional status as required by the submitting TARDEC laboratory the respective laboratory shall be contacted with any additional repair cost as applicable and all repairs will be authorized in writing by TARDEC prior to being initiated. Repairs not pre-authorized by the submitting TARDEC laboratory will not be reimbursed to the supplier.
5.9 The contractor shall provide a clear Return Material Authorization (RMA) Process to manage and track Government TMDE throughout shipment, calibration, and the return to/from any subcontracted calibration lab.
5.9.1 The contractor shall respond to RMA requests and issue RMA numbers by the close of business of the next business day. Business days shall be defined as 0700-1530, Monday thru Friday, excluding Government holidays.
5.10 The contractor shall assume responsibility for all shipping/transportation costs to and from contractor’s facility and any subcontractors’ facilities for all TMDE presented for calibration. The contractor shall utilize durable, protective shipping containers and packaging of TMDE when shipping and returning TMDE.
5.10.1 The contractor shall ensure transportation carrier(s) provide door-to-door tracking capability of TMDE during shipment.
5.10.2 The contractor shall return TMDE to the point of contact and location indicated on the RMA#.
5.11 The TMDE will be calibrated not to exceed 14 day TAT, unless otherwise agreed by submitting TARDEC Laboratory.
5.12 The quantities listed in the attachment are estimates only and do not necessarily represent the actual quantities that may be required or ordered.
5.13 The contractor shall report any assets broken/damaged while in their possession to the appropriate Lab TMDE Coordinator. The contractor shall replace broken/damaged assets, as directed by the appropriate Lab TMDE Coordinator. The replacements shall have the same form, fit, function, and applicable accredited calibration as required by the submitting laboratory.
5.14 CONTRACTOR MANPOWER REPORTING (CMR) : The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the contractor shall report ALL Contractor manpower (including subContractor manpower) required for performance of this contract.
The Contractor shall completely fill in all the information in the format using the following web address https://Contractormanpower.army.pentagon.mil. The required information includes: (1) Contracting Office, Contracting Officer, Contracting Officer’s Technical Representative (COTR) or also known as the Contracting Officer’s Representative (COR); (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor's name, address, phone number, e-mail address, identity of Contractor employee entering data; (5) Estimated direct labor hours (including sub-Contractors); (6) Estimated direct labor dollars paid this reporting period (including sub-Contractors); (7) Total payments (including sub- Contractors); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the Contractor with its UIC for the purposes of reporting this information); (11) Locations where Contractor and sub-Contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and (13) Number of Contractor and sub-Contractor employees deployed in theater this reporting period (by country). As part of its submission, the Contractor shall provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period shall be the period of performance not to exceed 12 months ending September 30 of each Government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s system to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.
CLAUSES
A.1 Electronic Contracting
(a) All Army Contracting Command – Warren solicitations will be publicized on the Federal Business Opportunities website (https://www.fbo.gov). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.
(b) As of 10 August 2015, unless directed to do otherwise in Section L of this solicitation, vendors are required to submit a quote or proposal via the Federal Business Opportunities (FBO) system. Proposals or quotes submitted after this date using any other mechanism, including the Army Single Face to Industry Bid Response System (ASFI BRS) may be deemed non-responsive.
(c) Requirements for the online FBO bid submission:
(1) Vendors must log into the FBO System to be able to submit electronic responses for opportunities.
(2) Vendors must be registered in the System for Award Management (SAM) at www.sam.gov (a Federal Government owned and operated free web site) and have a CAGE Code and CCR Marketing Partner Identification Number (MPIN).
(3) Once logged into the FBO System, vendors will be asked to enter basic information and directed to upload one or more files containing the proposal/quote and any additional information as outlined in the solicitation.
(4) FBO will send an email to vendor’s registered email address confirming the electronic submission.
(5) For additional information on submitting electronic bid responses via the FBO system see the FBO Vendor Guide – Section 4.3.1 “Submitting an Electronic Response” (https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf).
Note to offerors:
(d) Please pay close attention to the Issued By block location on the cover page of the solicitation for closing date and time. The closing date and time is based on the local time of the listed location of the Issued By office. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.
(e) It is the responsibility of the Offeror to ensure the proposal/quote is received by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the Government infrastructure (in this case, received through FBO) by the exact date and time specified on the cover page of this solicitation, it will be determined late. Proposal/quote is defined to mean ALL volumes or parts required in the solicitation are included in the electronic submission.
Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.
(f) Solicitations may remain posted on the FBO after the solicitation closing date. If the response deadline has passed for the solicitation, vendors will no longer be able to submit electronic responses.
(g) Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of the Government’s intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or Pricing data/information. If an Offeror objects to such release in the base contract or contract modifications, the Offeror must notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for the objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.
(h) Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the Procurement Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.
A.2 ACKNOWLEDGEMENT OF AMENDMENTS
Acknowledge all the amendments received from the Government by identifying the amendment number and its issue date below:
Amendment Number: Date:
A.3 ARMY CONTRACTING COMMAND – WARREN (DTA) OMBUDSPERSON
Information regarding the Ombudsperson for this contract is located at the following website:
http://acc.army.mil/contractingcenters/acc-wrn/CompMgmtOffice.html
A.4 ALL OR NONE-COMMERCIAL ITEM ACQUISITION
(a) This provision serves as an addendum that modifies paragraph (h) of FAR 52.212-1, entitled INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS. Paragraph (h) is modified to say that the proposal or quote must offer to provide the total quantity of the items in this solicitation.
(b) Only one award will be made as a result of this solicitation. Offers submitted for less than the total quantities of all the items in this solicitation will NOT be considered for award
A.5 NOTICE OF ELEVATED THREAT LEVEL FORCE PROTECTION CONDITION (FPCON)
Contractor is hereby notified that there is a potential impact on contractor performance on during increased FPCON during periods of increased threat. During FPCONs Charlie and Delta, services may be discontinued / postponed due to higher threat. Services will resume when FPCON level is reduced to level Bravo or lower.
A.6 NOTICE OF RANDOM ANTITERRORISM MEASURES PROGRAM (RAMP)
In accordance with AR 525-13, Contractor personnel working on an Army installation, arsenal, base or other DoD facility (owned or leased by DoD/Department of the Army), are subject to participation in Installation RAMP security program (e.g. vehicles searches, wearing of ID badges, etc).
C.1 ANTI-TERRORISM (AT) LEVEL I TRAINING REQUIREMENT
All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete AT Level I awareness training within 60 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies. The contractor shall submit certificates of completion for each contractor employee and subcontractor employee requiring access to Army installations, facilities, or controlled access areas to the COR (or to the contracting officer, if a COR is not assigned) within [XX]*** calendar days after completion of training. AT Level I awareness training is available at https://jkodirect.jten.mil Course #JS-US007-14.
C.2 iWATCH TRAINING
The contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity Anti-Terrorism Officer (ATO)). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR, if assigned, or the Contracting Officer. This training shall be completed within 60 calendar days of contract award and within 60 calendar days of new employees’ commencing performance, with the results reported to the COR, or Contracting Officer, no later than 60 calendar days after contract award. Training may be obtained at http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx
C.3 TRUSTED ASSOCIATE SPONSORSHIP SYSTEM (TASS) PROGRAM
(a) The contractor is responsible for processing applications for Common Access Cards (CAC) for every contractor employee who deploys with the military force, OR who has need to access any government computer network in accordance with FAR 52.204-9, “Personal Identity Verification of Contractor Personnel.”
(b) The contractor is responsible for managing requests for new or renewal CAC cards in sufficient time to ensure that all contractor employees have them when needed to perform work under this contract. The norm is at least ten calendar days’ advance notice to the Trusted Agent* (TA), unless there are extenuating circumstances approved by the Contracting Officer’s Representative (COR) or Contracting Officer. *The COR will be the TA for this contract.
(c) The contractor shall obtain an Army Knowledge Online (AKO) email address for each applicant, including subcontractors, who may be deployed or require logical access to a government computer network. This can be done by going to http://www.us.army.mil and register as an “Army Guest” with the sponsor being the COR. Note:
If a contractor employee loses the privilege to access AKO, they lose the ability to renew their CAC. Therefore, it is critical that contractor employees maintain their AKO accounts.
(d) It is recommended that a “Corporate Facility Security Officer (FSO) be established to serve as the firm’s single point of contact for Trusted Associate Sponsorship System (TASS). If a FSO is not established, each contractor employee requiring a CAC card will be required to process their own applications.
(e) CAC applications must be processed through the DOD’s TASS. The contractor’s FSO or contractor employee shall submit requests for a CAC via email to the TASS Trusted Agent (TA) at -1- before accessing the TASS website.
(f) The government will establish a TASS application account for each CAC request and will provide each contractor employee a USER ID and Password via email to the FSO. The FSO or contractor employee shall access the TASS account and complete the CAC application (entering/editing contractor information as applicable) at https://www.dmdc.osd.mil/tass/operator/consent?continueToUrl=%2Ftass%2Findex.jsp.
(g) The FSO or contractor employee will submit completed applications in TASS, and will follow up to ensure that the TA is processing the request.
(h) The government will inform the contractor’s applicant via email of one of the following:
- Approved*. Upon approval, the information is transferred to the Defense Enrollment Eligibility Reporting System (DEERS) database and an email notification is sent to the contractor with instructions on obtaining their CAC. The contractor proceeds to a Real-Time Automated Personnel Identification System (RAPIDS) station (https://www.dmdc.osd.mil/rsl/ provides RAPIDS locations).
- Rejected*. Government in separate correspondence will provide reason(s) for rejection.
- Returned. Additional information, or correction to the application, required by the contractor employee.
*The contractor will maintain records of all approved and rejected applications.
(i) At the RAPIDS station, the RAPIDS Verification Officer will verify the contractor by SSN, and two forms of identification, one of which must be a picture ID. The Verification Officer will capture primary and alternate fingerprints and picture, and updates to DEERS and will then issue a CAC.
(j) Issued CACs shall be for a period of performance not longer than three (3) years or the individual’s contract end date (inclusive of any options) whichever is earlier.
(k) The contractor shall return issued CAC’s to the DEERS office upon return from deployment, departure or dismissal of each contractor employee. A receipt for each card must be obtained and provided to the TA/COR.
(l) A CAC cannot be issued without evidence that a National Agency Check with Written Inquires (NACI) has at least been initiated by the FSO. TASS will be linked to the Joint Personnel Adjudication System (JPAS) in the near future. The TA will have to verify via JPAS that the NACI has been initiated by the FSO before he/she can approve a contractor request for a CAC.
(m) Details and training on TASS are available on AKO at https://www.us.army.mil/suite/portal/index.jsp or by contacting the CAC helpdesk at cacsupport@mail.mil or 866-738-3222.
C.4 CONTRACTOR MANPOWER REPORTING (CMR)
(a) The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the contractor will report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via secure data collection site. The contractor is required to completely fill in all required data fields in the format using the following web address: https://armycmra.dmdc.osd.mil/. The required information includes the following:
(1) Contracting Office, Contracting Officer, Contracting Officer's Technical Representative;
(2) Contract number, including task and delivery order number;
(3) Beginning and ending dates covered by reporting period;
(4) Contractor name, address, phone number, e-mail address, identity of contractor employee entering data;
(5) Direct labor hours (including sub-contractors);
(6) Direct labor dollars paid this reporting period (including sub-contractors);
(7) Total payments (including sub-contractors);
(8) Predominant Federal Service Code (FSC) reflecting services provided by contractor (and separate predominant FSC for each sub-contractor if different);
(9) Data collection cost;
(10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the contractor with its UIC for the purposes of reporting this information);
(11) Locations where contractor and sub-contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website);
(12) Presence of deployment or contingency contract language; and
(13) Number of contractor and sub-contractor employees deployed in theater this reporting period (by country).
(b) Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at: https://armycmra.dmdc.osd.mil/ and clicking on the “Send an Email” link which is located under the Help Resources ribbon on the right hand side of the login page.
C.5 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
(a) The contractor and all associated subcontractors’ employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the
Government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9 “Personal Identity Verification of Contractor Personnel”) as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
(b) For contractors requiring Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05, The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of six (6) months or more. At the discretion of the sponsoring activity, an initial CAC may be issued on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personal Management.
(c) For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards, and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures elsewhere in Section C; Non-disclosure Statement; for OCONUS locations, refer to the Status of Forces Agreement and other theater regulations.
C.6 CONTRACTOR EMPLOYEES WHO REQUIRE ACCESS TO GOVERNMENT INFORMATION SYSTEMS
All contractor employees shall be registered in the ATCTS (Army Training Certification Tracking System) at commencement of services and must successfully complete the DoD Information Assurance Awareness training prior to access to the information system, and annually thereafter.
C.7 ARMY INFORMATION SYSTEM (IS) SECURITY REQUIREMENT
CONTRACTOR INVESTIGATION/CLEARANCE. Reference AR25-2, AR 380-67, DoD 5200.2-R and Final Credentialing Standards for Issuing Personal Identity Verification Cards under HSPD-12 (31 Jul 2008). All contractors and consultants that access government owned or operated automated information systems, networks, or databases and to safeguard controlled unclassified information shall have a favorable background investigation as required above references positions designated as IT-I, IT-II or IT-III to perform functions stipulated in contract scope of work. The minimum investigative requirements are as follows: IT-I (Privileged Access) = Single Scope Background Investigation (SSBI); IT-II (Limited Privileged Access) = National Agency Check with Law and Credit Check (NACLC); IT-III (Non-Privileged Access) = National Agency Check with Inquiries (NACI). An investigation in-process is acceptable if the 7th Signal Command Designated Approval Authority (DAA) has granted an IT Waiver. Investigations will be coordinated with the G2, TACOM LCMC (AMSTA-CSS / 586-282-6262) and investigations will be through the Personnel Security Investigations Portal Center of Excellence (PSIP COE). Non- U.S. citizens shall be Permanent Resident Aliens with requisite investigation. All personnel shall receive and certify to an Information Systems Security Briefing.
C.8 INFORMATION ASSURANCE (IA)/INFORMATION TECHNOLOGY (IT) TRAINING
All contractor employees and associated subcontractor employees must complete the DoD IA awareness training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DoD and Army training requirements in DoD 8570.01, DoD 8570.01-M, and AR 25-2 within six months of employment. Within 10 days of completing the training, the Contractor shall provide certificates/proof of completion to the Contracting Officer’s Representative (COR), if assigned to the contract, or the Procuring Contracting Officer (PCO).
SECTION L
L.1 Proposal Preparation Instructions
L.1.1 Certifications/Representations
a. Must contain a scanned image of the Standard Form 33 (SF 33) cover page signed by the person authorized to sign proposals on the behalf of the offeror. Include completed fill-ins of SF 33 blocks 12, 13, 15a, 15b, 16, 17 and 18.
b. This solicitation, Sections A through K, with all fill-ins completed.
c. An affirmative statement that the offeror proposes to meet all requirements of RFP PWS.
d. A statement of agreement to all the terms, conditions and provisions of this solicitation.
e. An affirmative statement that the offeror has ISO 17025 certifications.
L.1.2 Cost Factor
a. The offerors cost proposal shall include substantiating information (non-certified) supporting the realism of the estimated cost and fee, in sufficient detail for the Government to evaluate the estimated costs. After proposal submission, the Government reserves the right to request more detailed cost information if necessary.
b. The offeror shall propose to all of the items listed on Attachment 1. Attachment 2 contains all of the possible items that potentially could be calibrated during the life of this contract and shall be utilized as a reference only.
c. The offeror shall assume $10,000 per year for material and other direct costs. The offeror may apply indirect expenses to the USG plug figure and shall provide an explanation of how the indirect expenses were developed (material handling, G&A, etc.). No profit/fee shall be applied to the USG provided plug figure. All proposed indirect rates shall be in accordance with the offeror's normal accounting practices and procedures.
d. For all items that cannot be calibrated at TARDEC, the offeror shall segregate shipping costs in their proposal.
L.2 HANDCARRIED OFFERS - INCLUDING OFFERS DELIVERED BY EXPRESS SERVICES (NON-US
POSTAL SERVICE MAIL)
(a) Unless specifically authorized elsewhere in this solicitation, paper offers will not be accepted. The term "handcarried offers" generally refers to offers contained on electronic media, which we recognize may be delivered "by hand." Handcarried offers must be delivered to Building 255.
(b) Handcarried offers, including disks or other electronic media, shall be addressed to:
U.S. Army Contracting Command - Warren Bid Room, Bldg 231, Mail Stop 303 6501 East 11 Mile Road
Warren, MI 48397-5000
(c) Offers shall not be addressed to an individual buyer. All offers must be addressed to the Offer Receipt Office at the above address.
(d) The external delivery envelope or wrapper must be marked with the solicitation number and the date and time of the solicitation closing. Each envelope should contain only one offer.
(e) Handcarried offers must be delivered to Building 255. Directions to U.S. Army TACOM – Detroit Arsenal:
From Van Dyke Avenue, travel westbound on 11 Mile Road; enter the first Arsenal gate immediately west of the railroad tracks on the north side of the street. Take an immediate right and follow security officer directions to the Receiving Dock in Building 255. The driver may need to obtain a badge, and must be a US citizen. The Government will forward the package to the Offer Receipt Office in Building 231.
(f) Offerors must ensure that the commercial carrier they use has a tracking system that can provide documentation of the date and time of delivery to the Government. For handcarried offers delivered by other than a commercial carrier, the offeror must ensure that the delivery person obtains a signature from Receiving Dock personnel on a receipt that shows the date and time of delivery to the Government. The delivery person must provide the receipt since Receiving Dock personnel do not have them.
(g) Packages must be delivered to Building 255 between the hours of 8:00 am and 3:00 pm local time.
L.3 HQ-AMC LEVEL PROTEST PROCEDURES
Complete AMC Protest Procedures can be found at: http://www.amc.army.mil/Connect/Legal-Resources/ An agency protest may be filed with either the contracting officer or to HQAMC but not both following the procedures listed on the website above.
L.4 PACKING/PACKAGING LEVEL FOR OPTION QUANTITIES
For purposes of computing a price for the option quantity specified in Section B of this solicitation and unless otherwise indicated in Section B, it is understood and agreed that the option unit price includes the same level(s) of packing/packaging as those that apply to the basic contract quantity.
L.5 SUBMISSION OF SUBCONTRACTING PLAN
(a) Concurrent with the offer in response to this solicitation, the offeror shall submit a subcontracting plan required by FAR 52.219-9, entitled SMALL BUSINESS AND SMALL DISADVANTAGED BUSINESS SUBCONTRACTING PLAN. Note that such a plan is not required of offerors that are small businesses. The plan shall be submitted to the buyer's e-mail address on the face page of the solicitation.
(b) Each page of the subcontracting plan will be marked with the solicitation number and date, and may also be marked with other codes or identification symbols to aid in later identification. If this is a negotiated acquisition, the subcontracting plan may be negotiated along with the cost, technical, and managerial features of the offeror's proposal, and the Government reserves the right to discuss the…