W564KV-18-P-0055_Q&A.pdf
PDF 84 KB Posted
- Attached to
- Facilities Maint & Cleaning Services Federal contract opportunity
- Solicitation number
- W564KV-18-R-0055
About this file
The purpose of this amendment is to answer vendor questions and update the PWS section of Part 5 Specific Tasks replacing occurrence verbiage. Questions are answered on a separate document titled "W564KV-18-R-0055 Q&A All other terms and conditions held within this solicitation remain unchanged.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Responses_to_Q&A_for_W564KV-18-P-0055_MX_CLNG,_17_Sept_18.pdf | ||
| W564KV-18-R-0055_Amendment_01.pdf | ||
| W564KV-18-R-0055.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Dated: 13 September 2018
Facilities Maintenance & Cleaning Services
- W564KV-18-R-0055-
Questions and Answers
Q1. Is it correct that the period of service is 3 month?
A1 YES. THE POP IS 3 MONTHS.
Q2. Does it mean the service in/at sanitary areas would be performed maximum (3x) three times during the period? Does this equate to a maximum of 9 cleaning sessions in sanitary area?
A2.NO. THERE ARE ONLY 3 CLEANING SESSIONS SPREAD OVER 3 MONTH PERIOD.
**Refer to the Updated PWS**
Q3. Service on all other floors/rooms/furniture would be performed at a maximum of one cleaning per month during the period? Does this equate to a maximum of 3 cleaning sessions on all other floors?
A3. NO. The areas identified as sanitary areas will be performed 3-times total; whereas, all other areas are performed only once for the duration of the period of performance. **Refer to the updated PWS**
Q4. What happens when the COR is requesting more than 3 cleaning session per month and the quote should be a firmed fixed price?
A4. The COR will not request more than is provided in the PWS for a FFP contract. **Refer to
Q5. Can the total number of cleaning performances become higher? It reads in the PRS i.e.3 Times at intervals of 1 month or COR determination.
A5.The COR will not request more than is provided in the PWS for a FFP contract. **Refer to