About this file
The purpose of this amendment is to answer vendor questions from 14 Sept to 17 Sept. All other terms and conditions of this solicitation remain unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W564KV-18-P-0055_Q&A.pdf | ||
| W564KV-18-R-0055_Amendment_01.pdf | ||
| W564KV-18-R-0055.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Dated: 17 September 2018
Facilities Maintenance & Cleaning Services
- W564KV-18-R-0055-
Questions and Answers
Q1. Is this a new requirement?
A1. YES. This is a new requirement.
Q2. Is there a timeframe for specific buildings or can the work be completed over the period of three (3) months?
A2. All buildings must be completed within the period of performance as specified in accordance with the PWS and will be further established at the post award conference.