This is an amendment to a solicitation for roof repair services on Building 350 at the Rock Island Arsenal in Rock Island, Illinois. The amendment answers contractor questions by clarifying that insulation should be 25 psi, non-reinforced membrane will be acceptable in place of reinforced, and that adhesive can be used in lieu of mechanical fastening for insulation. It also incorporates revised specifications and submittal requirements. The Department of the Army Materiel Command Joint Munitions Command is requesting proposals to replace the roofing on Building 350 per the details in the amended solicitation and specifications. The amendment provides additional clarity on technical requirements but does not otherwise alter the opportunity scope or terms.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2022-3282
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Summary of Changes
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Jul-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W52P1J22R5006
X 9B. DATED (SEE ITEM 11)
12-Jul-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Jul-2022
CODE
ARMY CONTRACTING COMMAND - ROCK ISLAND
3055 RODMAN AVENUE
ROCK ISLAND IL 61299-8000
W52P1J 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W52P1J22R5006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
The purpose of this Amendment is:
1. To answer the following Contractor questions:
a. Please clarify - Insulation 20 or 25PSI? spec calls for 20PSI Answer: Insulation shall be 25 psi per the requirements listed on the plans.
b. Please clarify - Membrane spec 90 mil REINFORCED or UNREINFORCED? Spec calls for
REINFORCED
Answer: 90 mil non-reinforced membrane will be acceptable.
c. Can adhesive be used in lieu of mechanically fastening insulation?
Answer: Refer to Revised Specification 07 53 23 dated 20 July 2022
2. To incorporate the following revised documents
a. Revised Scope of Work dated 20 July 2022
b. Revised Specification Section 07 22 00 dated 20 July 2022
c. Revised Specification Section 07 53 23 dated 20 July 2022
d. Revised Specification Section 07 60 00 dated 20 July 2022
e. Revised Submittal Register dated 20 July 2022
3. To provide Contractor requested photographs. See Attachment 0009, dated 20 July 2022
4. All other terms and conditions remain unchanged.
(End of Summary of Changes)