This solicitation amendment modifies the request for proposal for a well closure and sealing project on Rock Island Arsenal. The Army Contracting Command - Rock Island seeks proposals to remove aggregate and seal an entire well in accordance with the scope of work. The contractor must complete all work under the specifications and drawings by the revised due date of May 14, 2020. Proposal submissions and bid bonds must now be sent electronically rather than physically delivered. This project is set aside as 100% small business and has an estimated value between $500,000 and $1,000,000. The amendment provides answers to contractor questions about environmental concerns, utility clearances, and the availability of engineering drawings.

View the file

Other files for this federal contract opportunity

Other files attached to Well Closure and Sealing, newest first.
File Type Posted
20R5004 Solicitation Amendment 0002.pdf PDF
B08 -- W52P1J20R5004 -- Solicitation closing 02Jun2020.pdf PDF
20R5004 Attachment 0004 -- Davis Bacon Wage -- as of 15Apr2020.pdf PDF
20R5004 Attachment 0001 -- SOW.pdf PDF
20R5004 Solicitation for Close Seal Deep Well.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2017-6607

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Please see narrative for details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-May-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W52P1J20R5004

X 9B. DATED (SEE ITEM 11)

30-Apr-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-May-2020

CODE

ARMY CONTRACTING COMMAND ROCK ISLAND

3055 RODMAN AVENUE

ROCK ISLAND IL 61299-8000

W52P1J 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W52P1J20R5004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

SOLICITATION AMENDMENT 0001

The purpose of Amendment 0001 is the following:

1. Revise proposal and bid bond procedures as follows:

From:

All Contractor proposal submission and bid bonds may be overnighted or mailed to:

Army Contracting Command Attention: Megan Frost 3055 Rodman Avenue Building 60, 3rd Floor Rock Island, IL 61299 OR

Proposal submission only may be sent electronically to megan.k.frost2.civ@mail.mil. Bid Bonds must be sent overnight or by mail.

To:

Contractor proposal submission shall be submitted via email to the following email addresses:

megan.k.frost2.civ@mail.mil and molly.j.lewis4.civ@mail.mil.

Please note that large attachments may take longer to be accepted into the ACC-RI email system. Please be aware that large files may require extra time to be delivered into our email system. All proposal documents must be fully delivered into the email system, and time- stamped no later than the date and time listed in BLOCK 13 of the solicitation. Our email system standard is an estimated limit of ten (10) megabits per incoming email.

Bid bonds cannot be accepted electronically or in person due to restricted access at the Rock Island Arsenal. All bid bonds shall be mailed to the following address. Please note 20R5004 in the address area.

Army Contracting Command, Rock Island Attention: Megan Frost – Solicitation 20R5004 3055 Rodman Avenue Building 60 Rock Island, IL 61299

2. Answer industry questions.

Q1. Building 51 demolition - are there any environmental concerns that need to be addressed prior to demolition of the building - such as asbestos, PCBs, mercury containing equipment/devices, or lead-based paint?

A1. This are no known asbestos or lead containing construction materials as part of BLDG051. The scope of work is written with the expectation that all demolition material will be considered normal

All bids bonds must be received no later than the date and time listed in BLOCK 13 of the solicitation.

W52P1J20R5004 construction debris. Regarding the presents of PCBs and Mercury, it was often large electrical supply equipment and pump switches that would have contained this respective hazardous materials. Such equipment has already been removed from the structure.

Q2. Will RIIS be completing utility clearance of work area or is that to be included as part of the scope of work?

A2. RIIS will locate and determine status (in use) of exposed utilities.

Q3. Who is responsible for determining which below grade utilities and utility conduits to/from building 51 are no longer in use?

A3. The contractor will be responsible to remove unused utilities per SOW paragraph(s):

5.4.1.3 Remove below grade utilities and utility conduits to and from BLDG051 that are no longer in use-at least 50 linear foot each instance.

5.4.1.3.1 Remove 50ft of well discharge pipe.

5.4.1.3.2 Remove 50ft of unused utilities and conduits (electrical, communication, etc.)

5.4.1.3.3 Utilities discovered and not removed during the utility demo shall be noted on the red line drawings.

Q4. Will MicroStation engineering drawings be provided?

A4. No MicroStation engineering drawings be provided.

3. All other terms and conditions remain unchanged.

(End of Summary of Changes)