Exhibit A - CDRL A001 - Test Inspection Report - First Article.pdf
PDF 220 KB Posted
- Attached to
- Pull Ring and Chain Assembly Federal contract opportunity
- Solicitation number
- W52P1J-20-Q-3002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 20Q3002-Amendment 0001.pdf | ||
| Attachment 0001 - Pull Ring and Chain Assembly Price Matrix.xlsx | XLSX spreadsheet | |
| W52P1J-20-Q-3002 - Pull Ring and Chain Assembly Solicitation.pdf | ||
| Exhibit B - CDRL A002 - Technical Report - Certificate of Analysis and Material Certification.PDF |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 1 Pages APD PE v1.00
17. PRICE GROUP
18. ESTIMATED
TOTAL PRICE
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM
OTHER
D. SYSTEM/ITEM
M8 pull ring and chain assembly
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
Test/Inspection Report
3. SUBTITLE
First Article Test (FAT) Report, Lot Acceptance Test (LAT) Report
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80004
5. CONTRACT REFERENCE
Sec E
6. REQUIRING OFFICE
JMPB-MMQ
7. DD 250 REQ
no
9. DIST STATEMENT
REQUIRED
no
10. FREQUENCY
as required
12. DATE OF FIRST SUBMISSION
see Block 16
14 . DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE
see Block 16
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft
Final
Reg Repro
16. REMARKS
The contractor is required to perform all required measurements for all components and prepare a FAT/LAT Report detailing all of those measurements. Every requirement of every drawing and specification must be measured and reported. Also, all required Material Certifications along with Certificates of Analysis are to be included in the FA and LAT Report.
Material certification shall be submitted at time of FAT and a copy shall accompany each shipment.
Certification shall address compliance with all applicable requirements of the material specification(s) listed in the contract. The certification shall be signed by a representative of the Contractor along with the date and title of the representative and shall contain (at a minimum), that the material conforms to the specification, revision, amendment and dates, along with type, grade,size, test methods, etc. called out by the contract.
Mail or email to:
Attn: Kenny Daniel 10-020 Kabrich Circle Pine Bluff Arsenal Pine Bluff, AR 71602-9500
Contracting:
Please forward report to Kenny Daniel bldg. 34-120 kenneth.g.daniel2.civ@mail.mil
JMPB-MMQ 1
15. TOTAL 1
G. PREPARED BY
Kenny Daniel
H. DATE
28 August 2019
I. APPROVED BY
II. Scott Ellis
J. DATE
28 August 2019 mailto:kenneth.g.daniel2.civ@mail.mil
APD PE v1.00
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
M8 pull ring and chain assembly
E. CONTRACT/PR NO. F. CONTRACTOR
16. REMARKS (Continued)
DD FORM 1423-1, FEB 2001 Page of Pages
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoD 5010.12-M for detailed instructions.)
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package;
TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support.
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Signature of preparer of CDRL.
Item H. Date CDRL was prepared.
Item I. Signature of CDRL approval authority.
Item J. Date CDRL was approved.
Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, Item 2. Enter title as it appears on data acquisition document cited in Item 4. or quality of the data item.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Item 13.
Specify when subsequent submittals are required, when applicable.
Estimated Price - Group IV items should normally be shown on the Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15.
Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.
DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data. These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.
DD FORM 1423-1 (BACK), FEB 2001
APD PE v1.00
| DD FORM 1423-1, FEB 2001 |
| INSTRUCTIONS FOR COMPLETING DD FORM 1423 |
| FOR GOVERNMENT PERSONNEL |
| FOR THE CONTRACTOR |
| Item 2. |
| Item 13. |
DD FORM 1423-1 (BACK), FEB 2001