SLIDES - Guajataca Presentation slides.pdf
PDF 10 MB Posted
- Solicitation number
- W51DQV-GUAJATACADAM
- Issued by
-
Department of the Army
About this file
This document is an industry outreach event agenda and presentation for the Guajataca Dam Permanent Repair Project in Puerto Rico, hosted by the U.S. Army Corps of Engineers (USACE) Latin America & Caribbean District on July 28, 2026.
The Guajataca Dam is a hydraulic fill embankment dam built in 1920 with a high hazard potential classification. It serves approximately 350,000 people through four water treatment plants and provides flood risk management, water supply for approximately 250,000 families, irrigation for agricultural purposes, and recreation. Hurricane Maria caused significant damage including spillway breach, outlet tunnel flooding, severed pressurized water connections, and destroyed intake stem guides. USACE has completed emergency and interim risk reduction measures through three phases, including concrete barrier placement, sandbag installation, dewatering systems, under-slab void filling, soil nailing, and reconnection of the 54-inch water supply conduit. The primary risk drivers identified are abutment seepage, embankment cracking and erosion, seismic instability of the puddle core, landslide movements, and spillway overtopping. Proposed permanent risk reduction measures include abutment cutoffs and grouting, core stabilization walls, buttress construction, backup water supply systems, concrete spillway overlays, and chute raising. The acquisition strategy will utilize USACE delivery methods including Design-Bid-Build, Integrated Design and Construction, or progressive design-build approaches. Small business contracting goals include 69.24% small business participation with subcontracting percentages of 13.00-31.00% for small businesses and specific percentages for disadvantaged, veteran-owned, women-owned, and HUBZone small businesses. The event includes two days of activities: Day 1 features presentations on the project, acquisition strategies, and small business programs with Q&A sessions, while Day 2 includes a mandatory safety briefing and guided site tour with working lunch.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AGENDA
GUAJATACA DAM DISCUSSION
DAY 1
TitleTime Registration, Reserve a One-on-One Contractor Teams session & Networking08:00 AM - 09:00 AM
Welcome & Opening Remarks09:00 AM - 09:15 AM
Presentation detailing upcoming Guajataca Dam Project09:15 AM - 10:15 AM
Small Business Program Discussion10:15 AM - 10:45 AM Break10:45 AM - 11:00 AM
One-Hour Open Forum (Q&A)11:00 AM - 12:00 PM Lunch Break12:00 PM - 01:00 PM
Continued, IF NEEDED One-Hour Open Forum (Q&A)01:00 PM - 02:00 PM
Closing Remarks02:00 PM - 02:15 PM Event Adjourns2:15 PM
INDUSTRY OUTREACH
EVENT DAY
PUERTO RICO
GUAJATACA DAM
PERMANENT REPAIR
PROJECT DISCUSSION
USACE - Latin America & Caribbean District 28 July 2026 0800 - 1430
AGENDA - GUAJATACA DAM PERMANENT
REPAIR
DAY 1
DescriptionTitleTime
Sign-in for attendees, coffee, and informal networking. Schedule 1-hour private virtual meetings between industry representatives and USACE technical/contracting personnel over the course of 4-7 Aug.
Registration, Reserve a One-on-One Contractor Teams session & Networking
08:00 AM - 09:00 AM
Project Manager, Chief of Contracting Office and Contracting Officer
Welcome & Opening Remarks09:00 AM - 09:15 AM
Presentation detailing upcoming Guajataca Dam Permanent Repair Project
PowerPoint Presentation: Guajataca Dam Project and Upcoming Opportunities
09:15 AM - 10:15 AM
SBA Introduction and Discussion Small Business Association (SBA) and Puerto Rico Economic Development Introduction
10:15 AM - 10:25 AM
Office of Small Business Programs - How to effectively do business with USACE Caribbean District.
PowerPoint Presentation: Small Business Program Discussion
10:25 AM - 10:55 AM
Transition and coffee break.Break10:55 AM - 11:15 AM
Panel discussion featuring USACE Leadership, Program Managers, and Small Business Professionals. Contractors can ask questions regarding the presentations, measures presented & acquisition strategies.
One-Hour Open Forum (Q&A)11:15 AM - 12:15 PM
Attendees are dismissed for lunch.Lunch Break12:15 PM - 01:15 PM Panel discussion featuring USACE Leadership, Program Managers, and Small Business Professionals. Contractors can ask questions regarding the presentations, measures presented & acquisition strategies.
Continued, IF NEEDED One-Hour Open Forum (Q&A)01:15 PM - 02:15 PM
Final words of appreciation and next steps for DAY 2 event. Closing Remarks02:15PM - 02:30 PM
Day 1 Outreach Event Day concludes.Event Adjourns2:30 PM
AGENDA - GUAJATACA DAM PERMANENT
REPAIR DISCUSSION
DAY 2
DescriptionTitleTime
Contractors and USACE personnel gather at the initial meeting point for attendance, logistics, and a mandatory site safety briefing.
Gather & Safety Briefing08:00 - 08:30
Two-Hour transit to the project site location.Inbound Travel08:30 - 10:30
Guided walkthrough of the project location, discussing site conditions, technical requirements, and environmental considerations.
Project Site Tour & Briefing10:30 - 12:30
Lunch on-site (brown bag - depending on logistics). Informal networking.
Working Lunch12:30 - 13:30
Two-Hour Return Transit back to the initial meeting point.
Outbound Travel13:30 - 15:30
Wrap-up questions, final administrative notes, and official conclusion of Outreach Event Day.
Final Debrief & Dismissal15:30 - 16:00
GROUND RULES AND PROCEDURES
1. Mute/silence phone
2. No technical discussion will be held in this forum
3. No recordings (no photographs, video or audio) allowed
4. Avoid sidebar discussion (If you need us to slow down or to repeat anything, please let us know)
DISCLAIMER
Information Provided During Outreach Event Day
Any information contained in the slides, or remarks or explanations made by USACE personnel during the presentations are for general information and will not change the terms and conditions of any resultant solicitation or subsequent contract.
HOW TO SUBMIT QUESTIONS
28 July 2026 0830 – 1100
• Notecards are available at the registration table
• Write down your questions on the notecards and place them in the basket on the registration table
• Questions that can be answered during this event will be addressed during the Q&A session
• All questions and answers will be provided on SAM.gov
PROJECT OVERVIEW
GUAJATACA DAM OVERVIEW
Project Purposes:
• Flood Risk Management
• Water Supply
• Recreation Hazard Potential Classification: High
Guajataca Dam, Quebradillas, Puerto Rico
GUAJATACA DAM PROJECT FEATURES
Owner: Puerto Rico Electric Power Authority (PREPA)
Hydraulic Fill Embankment Dam
Water Supply is primary purpose
• Built in 1920 for the Isabela Irrigation District
• Reservoir Capacity - 34,276 acre-ft
• Population of ~350,000 served
• Primary Source for 4 Water Plants
• Irrigation Canal for Agricultural Purposes
• Rio Guajataca
• Risk Level Similar to DSAC 2 for USACE-
Owned Dams
Project Benefits
• Flood Risk Management
• Water Supply & Irrigation (~250,000 families)
• Recreation
Repairs are a priority for PREPA because water supply is critical. The most important water reservoir for the northwest of the island.
HURRICANE MARIA IMPACT AND SPILLWAY
DAMAGES
Damages Caused to Reservoir Features
• Flooding of the Outlet Tunnel
• Outlet Structure Outfall Completely Clogged
• Spillway Breach due to head cutting
• Spilling event over bare ground were destabilizing some of the embankment.
• Pressurize Water Connection of the 54-inch
Diameter Pipe for the Canal was severed
• Intake Stem guides for gate c were destroyed
• Hydraulic lines inside outlet tunnel were ripped out
Repairs are a priority for PREPA because water supply is critical. The most important water reservoir for the northwest of the island
Dam, Quebradillas, Puerto Rico
EMERGENCY FLOOD FIGHTING ACTIONS
The strategies to prevent the Dam’s collapse were divided into three phases for Stage I :
o Phase I - Placing of 502 concrete barriers in the undercut area for stabilization purposes. This would also help the runoff energy dissipation reducing the surrounding slope erosion effects.
DVG placed the concrete barriers at the crest of the Dam, once in place US Army and Navy aerial support dropped them in the areas designated by USACE field personnel. Aerial support was a key factor due to limited access.
o Phase II - Construction of two stone abutments, along with the placement of 1,318 Super Sandbags filled with crushed stones (“mogolla”) for the creation of a power-dissipating pool. All bare soil ground areas were covered with blue stone 18 to 24 inches in size. The bags were filled in Mayagüez and were placed in the area with Army Cargo Helicopters, beginning 4 OCT 2017.
o Phase III - Installation of a dewatering system consisting of one 12 inch, one 8 inch and ten 18-inch pumps. This system will help reduce the water level in the dam and at the same time provide water for irrigation and human consumption.
EMERGENCY FLOOD FIGHTING ACTIONS
INTERIM RISK REDUCTION MEASURES
Stage II - Interim Risk Reduction Measures
Slab anchoring of remaining spillway structure using soil nailing
Fill under slab voids with high strength flowable fill, bulkhead construction at the end of breached slab
Concrete modules and coarse aggregate mooring by filling voids with high strength flowable fill
Restoring the connection between the reservoir and the Irrigation Canal by reconnection of the existing structure and continuing water pumping operation
Outlet Works stem gate, guides and operator replacements
Reducing slope of actual spillway
Construction of an energy dissipation pool at the end of existing spillway chute
Repair access roadway and slope repair (#476)
Grout, anchor, and seal cracks in the damaged spillway to prevent additional erosion
Install soil nails and shotcrete facing for the slopes of the eroded spillway channel slopes
Re-establish the 54-inch diameter water supply conduit to provide a more economical and reliable source of water for the water supply canal
Rehabilitate the high-pressure control gates of the intake tower
Stabilize the eroding slopes of the reservoir rim adjacent to the intake tower
Spillway and Channel Reinforcement: backfill eroded spillway channel and install new spillway channel lining to restore interim spillway capacity
UNDER SLAB VOID FILLING AND SOIL NAILING
54-INCH WATER CONNECTION REESTABLISHMENT
ARMOR STONE AND FLOWABLE FILL PLACING
INTERIM RISK REDUCTION FINAL
UP COMING STAGE III FOR THE PERMANENT REPAIR
PRELIMINARY ASSESSMENTS FOR PERMANENT REPAIRS
PRIMARY RISK DRIVERS
20CUI
Downstream
Landslide Movements Below/Within Dam & Spillway
Seismic Instability of Very Soft Puddle Core
Cracking/Erosion of Embankment
Seismic Intake Tower Collapse
Embankment Failure During Earthquake
Upstream
Spillway Chute Overtopping Leads to Embankment Sliding
During high discharge (35k cfs): Spillway flows overtop chute walls and scour dam toe, destabilizing embankment along landslide plane.
Left Abut. Void
Karst Voids in Abutments
N N
N PFMs E-10 & E-23
PFM E-3 & E-22
PFM O-3
PFMs S-2B & S-7
PFMs E-17 & E-22
Contributes to several PFMs
CUI 20
HYDROLOGIC LOADING CURVE/HAZARD CURVE
Spillway activates frequently (~1/3 chance in any given year)
EMBANKMENT – ORIGINAL CONSTRUCTION 1928
• Crest Elevation: 202.5 m;
• Hydraulically sluiced, very soft clay puddle core up to El. 194 m;
• Roller compacted core from El. 194 m to 202.5 m;
• Concrete key wall at foundation contact extending into bedrock
Small Slide (Feb 15, 1927)
Pre-Dam Topography
Embankment
Ground cracking and embankment deformations (1927)
Emergency stabilization berm and drain tunnel
March 1927
Enclosed depressions
Irregular and hummocky slope morphology on left bank slope (enclosed depressions, convex areas, arcuate slope-breaks, mid-slope benches, variable slopes, disorganized drainage patterns, View looking down spillway
HOWEVER: deformations were slowed but continued creep and distress was expressed in the embankment and spillway in the decades following construction
Steep, uniform right bank slope
MOVEMENTS DURING AND AFTER
CONSTRUCTION: 1927-1954
• Cracking and downstream movements occurred in Feb 1927 while dam construction was at 194 m and reservoir was at
182.5 m.
• Vertical displacement: Max movement at top of dam was about 1.4 m (4.6 ft) downward.
• Horizontal displacement: 1 m (3.3 ft) of movement in the downstream direction at toe of dam. 1.8 m (5.9 ft) further downstream of dam toe.
• Response:
• Reservoir was drained.
• Draining of core attempted through use of ditches and tunnels.
• Remaining core up to 202.5m was constructed with horse-drawn roller compacted dry fill.
• Additional material placed downstream of dam toe to the river channel.
• Movements again observed in May 1927, but this time on the upstream face. Measured to be 35 cm (1.1 ft) in upstream direction.
• Response was to add additional material to upstream toe.
• From 1927-1929: Creep rates measured 0.35m (1.1 ft) per year.
• “Slight” movements reported in the wet years of 1930-31.
• Response in 1935 was to place additional downstream fill.
• From 1942-1951: Creep rates measured 10 mm (0.4 inch) per year.
• Crest raised in 1954 (porous, low-density material)
USBR DAM SAFETY MODIFICATION: 1971 - 1984
• 1971: PRWRA was concerned with the dam and requested the USBR to perform evaluation.
• 1977: Both agencies agreed to modifications, including:
• Rebuilding upper 3 m of the crest.
• Constructing stability berm on downstream slope
• Replacing upper portion of damaged spillway
• Grouting and improving outlet works tunnel
• 1981: Construction contract awarded
• 1982: Excavation near river channel triggered dam movements.
• Investigations indicated “green clay” layer was likely responsible.
• Response was to construct a downstream toe buttress and cease placement of downstream stability/filter berm at El. 191 m
(instead of designed El. 195 m).
USBR Report Excerpt
USBR DAM SAFETY MODIFICATION: 1971 - 1984
• Spillway modifications
• Crest reconstruction
• Outlet works changes
USBR DAM SAFETY MODIFICATION: 1971 - 1984
Berm constructed to El.
191 (down from planned El. 195 m) due to embankment movement during construction.
USBR DAM SAFETY MODIFICATION: 1971 – 1984 (TUNNEL)
Intake Tower Gate C Gate A closed / silted in Gate B missing • Outlet controls at uptake shaft control building
• Concrete bulkhead and two high-pressure gates constructed in 1980s.
• Release capacity ~500cfs
USBR DAM SAFETY MODIFICATION: 1971 – 1984 (TUNNEL)
File Name
River Outlet
54-in Canal Outlet
Canal Outlet Gate River Outlet Gate
HP gates are 4’x4’ cast steel
• Additional toe buttress material added as a result of movement
• River Channel backfilled and replaced with 96” Dia Pipe
New Spillway Crest
LANDSLIDE MOVEMENTS (1982-1992)
I-14
NOTE: Dam foundation continues to creep at rate of about 25 mm (1 inch) per year along “green clay” sliding plane.
PROPOSED RISK REDUCTION MEASURES
POTENTIAL RISK REDUCTION MEASURES
Average Life Loss
A n nu al
P ro ba b ili ty o f
F a ilu re
1E-06
1E-05
1E-04
1E-03
1E-02
10 100 1,000
1E-01
1E-07
0.1 10,000
1E-00
E-E-
E-E-
Risk-Driving Potential Failure Modes
• E-23: Stoping into the right abutment
• E-10: Stoping into the left abutment
E-10
E-23
Abutment Cutoffs and Grouting
E-3
Average Life Loss
A nn ua l P ro ba bi lit y o f F ai lu re
1E-06
1E-05
1E-04
1E-03
1E-02
10 100 1,000
1E-01
1E-07
0.1 10,000
1E-00
E-17 & E-22
E-17 & E-22
Buttress
E-3E-3
Risk-Driving Potential Failure Modes
• E-22: Transverse cracking due to seismic loading
• E-17: Seismic deformation and cyclic softening of the puddle core leads to crest lowering and overtopping
• E-3: CLE along embankment transverse crack caused by landslide movement
E-3 & E-
E-3 & E-
Core Stabilization Wall
E-17
E-22
Risk-Driving Potential Failure Modes
• O-3: Seismic failure of the control tower
Average Life Loss
A nn ua l P ro ba bi lit y of
F ai lu re
1E-06
1E-05
1E-04
1E-03
1E-02
10 100 1,000
1E-01
1E-07
0.1 10,000
1E-00
O-3
Siphon or Pumped Backup Water Supply System
Canal Supply
River Supply
Average Life Loss A n nu al P ro ba b ili ty o f F a ilu re
1E-06
1E-05
1E-04
1E-03
1E-02
10 100 1,000
1E-01
1E-07
0.1 10,000
1E-00
Actionable only under As-Low-As-Reasonably- Practicable (ALARP) – (2)
• S-7: Scour of the grouted riprap chute
• S-2B: Overtopping of the right side of the spillway causing embankment scour and stability failure
Concrete Overlay
S-7S-7
S-2BS-2B
S-7
S-2B
Chute Raise
38CUI
CUI
GUAJATACA DAM PERMANENT REPAIR
CHALLENGES
Constructability (Means and Methods):
• Limited Space:
• Water Diversion and Care:
• Material Availability, Hauling and Management:
• Traffic Control:
• Long Lead Items:
OVERVIEW OF ACQUISITION APPROACHES
40CUI
USACE ACQUISITION STRATEGIES
SMALL BUSINESS PROGRAM
OFFICE OF SMALL
BUSINESS
PROGRAMS
Mariano Torres Feliciano Chief, Office of Small Business Programs USACE, Latin America & Caribbean District
Date: July 2026
Working Today to Build a Better Tomorrow
43CUI
OFFICE OF SMALL BUSINESS PROGRAMS
MISSION: USACE Office of Small Business leads the organization to fully utilize small businesses, to deliver the USACE mission.
VISION: Expand the USACE Office of Small Business and community, Commit to add value to all projects and communicate outcomes & Maximize innovation to lead the small business program into the future.
44SMALL BUSINESS’ ROLES DURING THE
CONTRACTING PROCESS
Pre-Solicitation: Attend planning meeting as the requirement is developed. Once the projects is clearly defined, assist in market research to identify potential work for small businesses. After market research is completed, assist in developing the acquisition strategy.
Solicitation-Award: Asist in the development of the solicitation and source selection plan (if required).
Ensure the solicitation contains proper small business clauses required by the regulations and policies. During award, assist in evaluating bids or proposals and subcontracting plans. Also, take lead to resolve protests concerning small business related issues.
Post Award: Monitor the performance of small business contractors and evaluate how well large businesses comply with subcontracting requirements.
45SMALL BUSINESS GOALS
FY26
FY26 GOALSSOCIO ECONOMIC CATEGORY
69.24%SMALL BUSINESS
12.40%SMALL DISADBANTAGED BUSINESS (SDB)
INCLUDING 8(a) SB DEVELOPMENT PROGRAM
1.00%SERVICE DISABLE VETERAN OWNED SB
(SDVOSB)
0.57%WOMEN OWNED SB (WOSB) &
ECONOMICALLY DISADVANTAGED WOSB
64.85%HUBZONE SMALL BUSINESSES
46SMALL BUSINESS PROPOSED
SUB-CONTRACTING PERCENTAGES
FY26 SOCIO ECONOMIC CATEGORY
13.00% - 31.00%SMALL BUSINESS
5.00% - 25.37%SMALL DISADBANTAGED BUSINESS (SDB)
INCLUDING 8(a) SB DEVELOPMENT PROGRAM
0.50% - 2.59%SERVICE DISABLE VETERAN OWNED SB
(SDVOSB)
2.30% - 3.61%WOMEN OWNED SB (WOSB) &
ECONOMICALLY DISADVANTAGED WOSB
1.00% - 5.00%HUBZONE SMALL BUSINESSES
PROCUREMENT ASSISTANCE
SBA Resources
• Business Opportunity Specialist
• Procurement Center Representative
Marketing Resources
• Contract Opportunities on SAM.gov
• Contract Data on SAM.gov
• System for Award Management
• Dynamic Small Business Search System
• Subcontracting Networking System
(SubNet)
Other Resources
• USASpending
• GSA Subcontracting Directory
• DoD Prime Contracting Directory
48CONTACT INFORMATION
Mariano Torres-Feliciano Chief Small Business Programs
USACE, Latin America & Caribbean District Fundación Angel Ramos, Annex Building
2nd Floor, Suite 202 383 Franklin D. Roosevelt Ave.
San Juan, PR 00918 Mobile: 787-220-0225
SB Email: saa-sb@usace.army.mil
SUBMIT QUESTIONS AND Q&A
SAM.GOV
• Please visit SAM.gov after Industry Day.
• All presentations, questions and answers, and the attendance sheet will be posted.
• Answers provided in this session are preliminary and the official answers will be posted with questions on SAM.
Notice ID: W51DQV-GUAJATACADAM
File details come from the government source that posted it. Updated .