This is a set of presentation slides from an Industry Day event hosted by the US Army Corps of Engineers Caribbean District covering two major flood control projects: Rio Puerto Nuevo Contract 3 and Rio de La Plata Contract 1.

The slides detail the scopes, timelines and requirements for both projects. Rio Puerto Nuevo Contract 3 ($250M-$500M) involves channel widening and construction of drilled shaft walls approximately 5,200 feet long, requiring 1,700 six-foot diameter concrete drill shaft piles, 200,000 cubic yards of concrete, and 46,000 tons of reinforcing steel. Advertisement is planned for February 2025 with award in September 2025. Rio de La Plata Contract 1 ($250M-$500M) includes channel excavation of 1.78M cubic yards, levee fill placement of 772,000 cubic yards, and stone protection placement of 160,000 cubic yards. Advertisement is planned for January 2025 with award in September 2025. Both projects are unrestricted with NAICS code 237990 and will require extensive material testing capabilities, with only 65% of required tests currently validated in Puerto Rico. Subcontracting opportunities exist in areas like trucking, pile driving, concrete work, utilities relocation, and environmental monitoring. Questions must be submitted through ProjNet by December 13, 2023 and proposals will only be accepted through the Procurement Integrated Enterprise Environment (PIEE) system.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDUSTRY DAY

RIO PUERTO NUEVO PROJECT

CONTRACT 3

RIO DE LA PLATA PROJECT

CONTRACT 1

US Army Corps of Engineers Caribbean District 05 December 2024

Registration: 8:00 am 8:30 am – 10:00 am

• Welcome Remarks

• How to submit questions

• Rio Puerto Nuevo: Project Overview

• RPN Contract 3: Scope of Work, Design Information

• Rio de La Plata: Project Overview

• RDLP Contract 1: Scope of Work, Design Information

• Construction Considerations

• Testing Requirements

• Contracting Requirements & Acquisition Timelines

• Small Business Opportunities 10:00 am – 10:30 am

• Question and Answer Session 10:30 am – 12:00 pm

• RPN Contract 3: One-on-One Sessions

• Networking

05 December 2024 Morning Session: 0830 – 1200

Focus: Rio Puerto Nuevo Contract 3 and Rio de La Plata Contract 1

AGENDA

1:30 pm – 4:00 pm

• APEX Accelerators presentation and orientation about PIEE

• SBA PCR

• SAME

• AGC PR

• MBDA

05 December 2024 Afternoon Session: 1:00PM – 4:00PM

Focus: Procurement Integrated Enterprise Environment (PIEE)

AGENDA

• Notecards are available at the registration table

• Write down your questions on the notecards and place them in the basket on the registration table

• Questions that can be answered during this event will be addressed during the Q&A session

• All questions and answers will be provided on SAM.gov

05 December 2024 1000 - 1030

QUESTION AND ANSWER SESSION

HOW TO SUBMIT QUESTIONS

• All questions to be submitted through ProjNet

• Deadline: 5:00 pm, AST on 13 December 2023

• RPN Contract 3

• Solicitation Number: W51DQV25S11UY

• Bidder Inquiry Key: I7W97W-UH6XGS

• RDLP Contract 1

• Solicitation Number: W51DQV-25-R-0002

• Bidder Inquiry Key: EGHXFQ-3E5DRK https://www.projnet.org/projnet/binKornHome/index.cfm

RIO PUERTO NUEVO FLOOD

RISK MANAGEMENT

PROJECT

CARIBBEAN DISTRICT

05 DECEMBER 2024

Emily Rivera, P.E.

Rio Puerto Nuevo

RPN CONTRACTS OVERVIEW

CNT2 CNT3 CNT1 CNT5A CNT5B CNT4 CNT6A CNT6B CNT7

Aug Feb Dec Dec Sep Feb Jan Apr TBD 2023 2025 2025 2026 2026 2027 2029 2030

RPN

Contract

Advertisement Date

CNT1 Winter 2025 CNT2 Awarded 2024 CNT3 Spring 2025 CNT4 Spring 2027 CNT5A Winter 2026 CNT5B Fall 2026 CNT6A Winter 2028 CNT6B Spring 2030

CNT7 TBD

Chronological Implementation Schedule

Upcoming Contract Advertisement

Sheet1

CNT1 3/24/26 CNT2 8/31/23 CNT2 CNT3 CNT1 CNT5A CNT5B CNT4 CNT6A CNT6B CNT7

CNT2 8/31/23 CNT3 3/14/25 Aug Feb Dec Dec Sep Feb Jan Apr TBD

CNT3 3/14/25 CNT1 3/24/26 2023 2025 2025 2026 2026 2027 2029 2030

CNT4 2/5/27 CNT5A 12/9/26

CNT5A 12/9/26 CNT5B 2/4/27

CNT5B 2/4/27 CNT4 2/5/27

CNT6A 12/14/28 CNT6A 12/14/28

CNT6B 4/10/30 CNT6B 4/10/30

CNT7 7/12/30 CNT7 7/12/30

CNT7A

CNT7B

CNT7C

Sheet1

RPN Contract Advertisement Date CNT2 8/31/23 CNT2 CNT3 CNT1 CNT5A CNT5B CNT4 CNT6A CNT6B CNT7

CNT1 Winter 2025 CNT3 3/14/25 Aug Mar Mar Dec Feb Feb Dec Apr

CNT2 Awarded 2024 CNT1 3/24/26 2023 2025 2026 2026 2027 2027 2028 2030

CNT3 Spring 2025 CNT5A 12/9/26

CNT4 Spring 2027 CNT5B 2/4/27

CNT5A Winter 2026 CNT4 2/5/27

CNT5B Fall 2026 CNT6A 12/14/28

CNT6A Winter 2028 CNT6B 4/10/30

CNT6B Spring 2030 CNT7 7/12/30

CNT7 TBD

CNT7A

CNT7B

CNT7C

RPN Supplemental Contract 3

SCOPE OF WORK

• Channel Walls

• Demonstration Piles per Crew

• Working Platforms

• Sewer Siphon

• Utility Bridge with 48” Watermain

• Main Channel Transition

• River Diversion

• Josefina Channel Transition

• Power Line Relocation

• Dredging and Excavation

• Stormwater Penetrations

RIO PUERTO NUEVO FLOOD

RISK MANAGEMENT

PROJECT

CONTRACT 3

Stephen Dupries, P.E.

Lead Civil Engineer

• Main channel walls, ~2 Miles of Tangent Piles

• Magnitude of Construction: $250M to $500M

• Period of Performance: 6 years

RPN Supplemental Contract 3

• 1,700 six-foot diameter concrete drill shaft piles (~100 feet deep)

• 200,000 cy of concrete

• 46,000 tons of reinforcing steel

• 600,000 cy of excavated material to be disposed

• 25,000 cy of suitable fill

• 8,000 tons of steel sheet pile

Temporary Sheet Piles

Drilled Shaft Piles

Guardrail

Concrete Cap

Drilled Shaft

RPN Supplemental Contract 3

160’

~2 5’

Channel Bottom

RPN Supplemental Contract 3

• Perform confirmation borings

• Working platform with temporary sheet piles

• Install temporary casing to –50 feet

• Auger material with slurry

• Polymer or mineral slurry

• Inspect hole using sonicaliper testing and bottom excavation inspection device

• Install rebar cage and sonic logging testing tubes

• Concrete mix is critical with several additives

• Tremie concrete into hole

• Remove temporary casing

• Testing of pile

• Install concrete cap

Equipment to install and remove the temporary casing shall have sufficient vibratory, impact, and rotational torque capacity

Excavation

RPN Supplemental Contract 3

Fill

Temporary Sheet Pile

Rio Piedras

Drilled Shaft

Pile

Working Platforms

Demonstration Wall per Crew

Single and Double Rows of Tangent Piles

Jet Grout (in some critical areas)

Drilled Shaft Piles, Heavily Reinforced

Rebar Cage

Sewer Siphon

Sewer Siphon RPN Supplemental Contract 3

Four 20-inch diameter sanitary sewer pipes in 30-inch diameter steel permanent casing pipes

Drilled Shaft Piles

Pile Caps

Drilled Shaft Piles

Rip Rap

New Effluent BoxNew Influent Box

160’

Jack and Bore Pit Temporary Sheet Pile

Drilled Shaft Pile

Perimeter Walers and Bracing

Jacking Equipment

30-inch Diameter Steel Casing

Rio Piedras

Concrete Slab

~3

Fe et

Utility Bridge with 48-inch Diameter Watermain

RPN Supplemental Contract 3

Rip Rap

Drilled Shaft Piles

48-inch Diameter Watermain

Utility Bridge with 48-inch Diameter Watermain

Pipe Saddles

Bridge Girder

Important Notes:

The contractor cannot increase the flooding risk of the surrounding community by obstructing flow

Florida Department of Transportation (FDOT) beams will be used for the utility bridge. This will require special coordination with the prestress beam suppliers in P.R

Valve Box Valve Box

RPN Supplemental Contract 3 Two Channel Transitions

Main Channel

Transition

Josefina Channel

Transition

21RPN Supplemental Contract 3

Main Channel Transition

Articulated Concrete

BlockDrilled Shaft Piles

Concrete Armor Units

Rip Rap

Articulated Concrete Block

Rip Rap

Concrete Armor Units

Sheet Piles

Sheet Piles

River Flow

250’

RPN Supplemental Contract 3

Articulated Concrete Block

Drilled Shaft Piles

Permanent Sheet Piles

Temporary Sheet Piles

Concrete Armor Units

Drilled Shaft Piles

Main Channel Transition Water Diversion

Diverted River

RPN Supplemental Contract 3 Josefina Channel Transition

Articulated Concrete

Block

Drilled Shaft Piles

Concrete Armor Units

Rip Rap

Articulated Concrete

Block

Sheet Piles

Rip Rap Concrete

Armor Units

Sheet Piles

Concrete Armor Units

River Flow

163’

RPN Supplemental Contract 3 Power Line Relocation

Transmission and distribution lines to be demolished

Transmission and distribution lines to be constructed

Drilled Shaft Piles

Stormwater Box Opening

Existing Ground

Concrete Shelf

RPN Supplemental Contract 3 Stormwater Penetrations Through the Wall

Cap Beam

Manhole

Soil Improvement

Existing Storm Water Pipe

Drilled Shaft Piles

Stormwater Box Opening

Guardrail

Cap Beam

Concrete Shelf

RPN Supplemental Contract 3 Stormwater Penetrations Through the Wall

3’ 8’

La Chuleta

Two (2) Material Management Areas:

• La Chuleta for bank excavation

• Offshore for material under the mean high high water line

San Juan Harbor

La Chuleta

Two (2) Material Management Areas:

• La Chuleta for bank excavation

• Offshore for material under the mean high high water line

RPN Supplemental Contract 3

Mean High High Water Line

Offshore

La Chuleta

Drilled Shaft Piles

RIO DE LA PLATA

CARIBBEAN DISTRICT

05 DECEMBER 2024

Emily Rivera, P.E.

LOCATION

Rio Grande de Arecibo

Rio de La Plata

RDLP OVERVIEW

Disposal Area

East Levee

West Levee

Disposal Area

Disposal Area

East Levee

Channel

Channel

Channel

72” Water Line

Dorado Bridge

PR HWY-2

PR HWY-22

PR-2 Bridge and Road Re-alignment

CONTRACT 1

Cory Spence Civil Engineer Huntington District

Edgardo Bermudez Rodriguez Geotechnical Engineer

File Name

LOCATION: Dorado and Toa Baja, PR, about 11 miles west of San Juan

PROJECT IMPLEMENTATION:

DORADO BRIDGE CWSP PROJECT (Ongoing) River channel widening and modifications (0.46 miles), construction of earthen levee (0.53 miles), and scour protection

ARTICULATED CONCRETE BLOCK MAT AND

TOE KEY (Substantially Complete) 500 feet of channel scour protection and toe key revetment

SUPPLEMENTAL CONTRACT 1

River channel widening and modifications (approx. 1.6 miles), construction of earthen levees (approx. 3.1 miles), four concrete culverts through levee, scour protection, and utility relocations

SUPPLEMENTAL CONTRACT 3

River channel widening and modifications (approx. 1.4 miles), construction of earthen levee (approx. 1.3 miles), scour protection, and utility relocations

SUPER-AQUEDUCT RELOCATION

Relocation of a 72-inch water supply aqueduct

Disposal Area

East Levee

West Levee

Disposal Area

Disposal Area

East Levee

Channel

Channel

72” Water Line

Dorado Bridge

PR HWY-2

PR HWY-22

Wetland Mitigation

RDLP CONTRACT 1

MAIN PROJECT FEATURES:

• 1,780,000 m3 channel excavation

• 772,000 m3 levee fill placement

• 160,000 m3 scour protection stone placement

• 4 – concrete culvert structures (2 - west levee, 2 - east levee)

• Pre-cast concrete pipe (5-7 feet in diameter)

• Cast-in-place concrete inlet and outlet head walls

• Composite flap gates (west levee culverts)

ADDITIONAL PROJECT FEATURES:

• Maintenance road on levee crest and within project boundaries

• Drainage ditches

• Utility relocations

• Water lines

• Sewer lines

• Electrical lines

• Material Management Areas for excavated material

• Remaining Wetland mitigation for the project

• Demolition of abandoned structures Levee

Location/Transition

Between Dorado Bridge Channel Widening and Scour Protection to Supplemental Contract 1

• Completion of the west levee

• Continuation of the channel

• Start of the east levee

Contract 1 East Levee

Contract 1 West Levee

DBCWSP

West Levee

DBCWSP

Channel

Contract1

Wetland Mitigation

• Scrub/Shrub Interior

• Series of Finger Channels and Pools

• Earthen Islands

• Sparse Tree and Scrub/Shrub Exterior

• Mangrove Oxbow Buffer

East Levee

Stone Protection

West Levee Stone Protection

Channel Centerline

Channel Centerline

Typical Sections

File Name

RDLP CONTRACT 1

East Levee Culvert 6A

Key Details

• 60-inch Precast Culvert

• Ungated

• Cast-in-place Headwalls

• Stone Energy Dissipation Basin

East Levee Culvert 7 Key Details

• 48-inch Precast Culvert

• Ungated

• Stone Energy Dissipation Basin

West Levee Culvert 3A

Key Details

• 5 - 84-inch Precast Culvert

• Flap Gates

West Levee Culvert 11

Key Details

• 2 - 72-inch Precast Culvert

• Flap Gates

Seismic Concerns and Potential Remediation

• Project located in seismic region

• Geotechnical data identified potential liquefiable soils

• Treatment beneath the east levee is planned to protect against seismic.

Potential Seismic Remediation Treatments

Utility Relocations

Sanitary Sewer

• 12-inch force main (Relocation)

• 8-inch sanitary (Protect in Place)

Potable Water (Treated Drinking Water)

• 12-inch (Protect in Place – Multiple Locations)

Electrical Distribution and Transmission Lines

• 8.32/4.8kV (Relocation)

• 38kV (Relocation)

Telecommunication

• None

CONSTRUCTION CONSIDERATIONS

• Coordination with two municipalities (Dorado and Toa Baja)

• Other concurrent USACE/non-USACE construction project

• Construction access

• Coordination with DTOP and PRHTA for maintenance of traffic

• Communication with La Plata Dam (PRASA)

• Release of water from dam may impact construction activities

• Utility relocations

• PRASA and LUMA

• Coordination with utility agencies to limit impacts to service

• Sufficient work limits for staging and field office

• High water events on La Plata River are short duration

CONSTRUCTION CONSIDERATIONS

RIO DE LA PLATA - CNT 1

RIO PUERTO NUEVO - CNT 3

File Name

Jorge Ayala, P.E.

Construction Division

46PR BIG 3 ESTIMATED QUANTITIES FOR MAIN SUPPLY

NEEDS

Note: Projects are at different stages in the design process.

Estimated quantities developed with the latest available design data.

Subject to change.

FEATURES RDLP CNT 1 RPN CNT 3 TOTAL

Excavation (CY) 2,328,000 600,000 2,928,000 Fill (CY) 1,000,000 25,000 1,025,000 Stone Placement (CY) 210,000 12,000 222,000 Soil Improvement (CY) 271,000 370 271,370 Sheet Piles (Tons) 2,500 8,000 10,500 Concrete (CY) 8,000 200,000 208,000 Reinforcing Steel (Tons) 1,000 46,000 47,000

ACBM (SQFT) 28,000 32,000 60,000

Main Materials

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

RDLP CNT 1 2,323,578 2,080,528 272,000 2412 On the works On the works 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

RDLP CNT 3 1,722,000 224,000 101,000

RGDA 325,000 520,000 29,000 6,500 On the works 14000LF (60in DS), +2000CY, 50000 tons of stone protection

RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

RPN CNT 2 119,000 4,801 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?

RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

RPN CNT 5A 9,000 5,000 636 8,000 537 34,000 100 DS 72 in

RPN CNT 5B 47,000 1,400 1,100 62,000 2,500 140,000 1000 DS 60 in

RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

RPN CNT 7 300,000 100,000 3,200 75,000 2,000

RPN La Chuleta 32,460 32,460 360 360 CY of concrete, 4,834 cy of bituminous pavement

Total 7,729,038 3,463,388 419,005 121,100 32,848 563,860 71,037 799,000

Main Materials (2)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

RDLP CNT 1 2,234,000 1,962,000 272,000 2412 14000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

RDLP CNT 3 1,722,000 224,000 101,000

RGDA 325,000 520,000 29,181 6,500 On the works 14000LF (60in DS), +2000CY, 50000 tons of stone protection

RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

RPN CNT 2 119,000 4,801 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?

RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

RPN La Chuleta 31,700 31,700 360 360 CY of concrete, 2,555 tons of bituminous pavement

Total 7,667,700 3,344,100 419,770 121,100 45,748 573,860 74,755 761,000

Main Materials (3)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

RDLP CNT 1 2,234,000 1,962,000 272,000 2412 14000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

RDLP CNT 3 1,722,000 224,000 101,000

Total RDLP 3,956,000 2,186,000 373,000 0 2,412 14,000 1,000

RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

RPN CNT 2 119,000 4,801 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?

RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

RPN La Chuleta 31,700 31,700 360 360 CY of concrete, 2,555 tons of bituminous pavement

Total RPN 3,386,700 638,100 17,589 121,100 44,944 553,360 73,755 761,000

Total 7,667,700 3,344,100 419,770 121,100 47,356 573,860 76,055 761,000

Sheet2

RPN CNT 2 lb/ft2 tons

Temporary Bypass Sheet Pile 48329 sqft 36.98 893.60321

Temporary Trnasverse Sheet Pile 19275 sqft 36.98 356.39475

Transition Sheet Pile 19372 sqft 36.98 358.18828

1608.18624

Main Materials No LC

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

RDLP CNT 3 1,722,000 224,000 101,000

Total RDLP 3,956,000 2,186,000 373,000 0 2,412 8,000 1,000

RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?

RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974

Total 7,636,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974

Contract Awards

FY23 FY24 FY25 FY26 FY27 FY28

RPN CNT 2 RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3

RGDA RPN CNT 5A RPN CNT 4 RPN CNT 7

RDLP CNT 1 RPN CNT 5B

Excavation (CY) 119,000 925,000 2,243,000 327,000 2,300,000 1,722,000

Fill (CY) 0 545,000 1,967,000 146,400 430,000 224,000

Stone Placement (CY) 4,801 41,385 272,584 0 0 101,000

Soil Improvement (CY) 700 0 0 121,100 0 0

Sheet Piles (Tons) 1,608 8,000 3,048 23,500 11,200 0

Concrete (CY) 19,000 206,500 22,000 165,000 155,000 0

Reinforcing Steel (Tons) 7,000 47,300 4,505 8,250 9,000 0

ACBM (SQFT) 0 31,974 34,000 406,000 321,000 0

Main Materials No LC (2)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

Mar-25 RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

May-28 RDLP CNT 3 1,722,000 224,000 101,000

Total RDLP 3,956,000 2,186,000 373,000 0 2,412 8,000 1,000

17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

8-Jul-24 RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?

17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974

Total 7,636,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974

Contract Awards

2023 2024 2025 2026 2027 2028

RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3

RPN CNT 2 RPN CNT 5A RPN CNT 4 RPN CNT 7 FEATURES 2024 2025 2026 2027 2028 TOTAL

RDLP CNT 1 RPN CNT 5B RGDA Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,722,000 7,636,000

Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 3,312,400

Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,722,000 Stone Placement (CY) 17,005 272,584 29,181 101,000 419,770

Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 Soil Improvement (CY) 700 121,100 121,800

Stone Placement (CY) 17,005 272,584 0 29,181 101,000 Sheet Piles (Tons) 9,608 3,048 23,500 11,200 47,356

Soil Improvement (CY) 700 0 121,100 0 0 Concrete (CY) 219,000 22,000 165,000 161,500 567,500

Sheet Piles (Tons) 9,608 3,048 23,500 11,200 0 Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 76,055

Concrete (CY) 219,000 22,000 165,000 161,500 0 ACBM (SQFT) 31,974 34,000 406,000 321,000 792,974

Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 0

ACBM (SQFT) 31,974 34,000 406,000 321,000 0

FEATURES RPN RDLP RGDA TOTAL

Excavation (CY) 3,355,000 3,956,000 325,000 7,636,000

Fill (CY) 606,400 2,186,000 520,000 3,312,400

Stone Placement (CY) 17,589 373,000 29,181 419,770

Soil Improvement (CY) 121,800 121,800

Sheet Piles (Tons) 44,944 2,412 47,356

Concrete (CY) 553,000 8,000 6,500 567,500

Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055

ACBM (SQFT) 792,974 792,974

Main Materials No LC (3)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

Mar-25 RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

May-28 RDLP CNT 3 1,222,000 224,000 101,000

Total RDLP 3,456,000 2,186,000 373,000 0 2,412 8,000 1,000

17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

8-Jul-24 RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?

17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974

Total 7,136,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974

Contract Awards

2023 2024 2025 2026 2027 2028

RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3

RPN CNT 2 RPN CNT 5A RPN CNT 4 RPN CNT 7 FEATURES 2024 2025 2026 2027 2028 TOTAL

RDLP CNT 1 RPN CNT 5B RGDA Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,222,000 7,136,000

Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 3,312,400

Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,222,000 Stone Placement (CY) 17,005 272,584 29,181 101,000 419,770

Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 Soil Improvement (CY) 700 121,100 121,800

Stone Placement (CY) 17,005 272,584 0 29,181 101,000 Sheet Piles (Tons) 9,608 3,048 23,500 11,200 47,356

Soil Improvement (CY) 700 0 121,100 0 0 Concrete (CY) 219,000 22,000 165,000 161,500 567,500

Sheet Piles (Tons) 9,608 3,048 23,500 11,200 0 Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 76,055

Concrete (CY) 219,000 22,000 165,000 161,500 0 ACBM (SQFT) 31,974 34,000 406,000 321,000 792,974

Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 0

ACBM (SQFT) 31,974 34,000 406,000 321,000 0

FEATURES RPN RDLP RGDA TOTAL

Excavation (CY) 3,355,000 3,456,000 325,000 7,136,000

Fill (CY) 606,400 2,186,000 520,000 3,312,400

Stone Placement (CY) 17,589 373,000 29,181 419,770

Soil Improvement (CY) 121,800 121,800

Sheet Piles (Tons) 44,944 2,412 47,356

Concrete (CY) 553,000 8,000 6,500 567,500

Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055

ACBM (SQFT) 792,974 792,974

CMP QTYs

[yd3] [Tons] [Tons] [yd3] [Tons]

Estimated award date Materials: Dedging Stone Placement Steel Sheet Pile Concrete Reinforcing Steel Concrete Culverts

Oct-24 CMP CNT 2 22,000 13,200 323 105 14 4 concrete culverts (need to estimate this and add to concrete quantities)

Oct-25 CMP CNT 3 PH1 440,000 1,650 3,274 1,173 155 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

Feb-28 CMP CNT 3 PH2 300,000 7,857 2,816 373

Total CMP 762,000 14,850 11,454 4,094 542

17-Jun-27 RGDA 14000LF (60in DS), +2000CY, 50000 tons of stone protection

28-Nov-25 RPN CNT 1 30,000 CY of concrete, asphalt 28990 SY

19-Jul-24 RPN CNT 2 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

8-Jul-24 RPN CNT 3 1600 DS 72 in ERROR:#NAME?

17-Aug-26 RPN CNT 4 1200 DS 60 in

3-Jan-25 RPN CNT 5A 100 DS 72 in, 1000 tons of riprap

30-Jun-26 RPN CNT 5B 1000 DS 60 in

28-May-27 RPN CNT 6 1300 DS 60 in

30-Jun-27 RPN CNT 7 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 0 0 0 0 0 0 0 0

Total 762,000 14,850 11,454 4,094 542 0 0 0

Contract Awards

2023 2024 2025 2026 2027 2028

CMP CNT 2 CMP CNT 3 PH1 RDLP CNT 3

FEATURES 2024 2025 2026 2027 2028 TOTAL

Dredging (CY) 22,000 440,000 300,000 762,000

Stone Placement (Tons) 13,200 1,650 14,850

Dredging (CY) 22,000 440,000 0 0 300,000 Steel Sheet Pile (Tons) 323 3,274 7,857 11,454

Stone Placement (Tons) 13,200 1,650 0 0 0 Concrete (CY) 105 1,173 2,816 4,094

Steel Sheet Pile (Tons) 323 3,274 0 0 7,857 Reinforcing Steel (Tons) 14 155 373 542

Concrete (CY) 105 1,173 0 0 2,816

Reinforcing Steel (Tons) 14 155 0 0 373

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

FEATURES CNT 2 CNT 3 PH1 CNT 3 PH2 TOTAL

Dredging (CY) 22,000 440,000 300,000 762,000

Stone Placement (Tons) 13,200 1,650 14,850

Steel Sheet Pile (Tons) 323 3,274 7,857 11,454

Concrete (CY) 105 1,173 2,816 4,094

Reinforcing Steel (Tons) 14 155 373 542

Main Materials (RPN3-RDLP1)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts 1780000

Mar-25 RDLP CNT 1 2,328,000 1,000,000 210,000 271,000 2500 8000 1000 28000 4 concrete culverts (need to estimate this and add to concrete quantities) 772000

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold 160000

May-28 RDLP CNT 3 1,222,000 224,000 101,000

Total RDLP 3,550,000 1,224,000 311,000 271,000 2,500 8,000 1,000

17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

1-Jun-26 RPN CNT 3 600,000 25,000 12,000 370 8,000 200,000 46,000 32,000 1600 DS 72 in ERROR:#NAME?

17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 3,355,000 606,400 17,385 122,170 44,944 553,000 73,755 793,000

Total 7,230,000 2,350,400 357,566 393,170 47,444 567,500 76,055 821,000

Contract Awards

2023 2024 2025 2026 2027 2028

RDLP CNT 1 RPN CNT 3

FEATURES 2024 2025 2026 2027 2028 TOTAL FEATURES 2025 2026 TOTAL

Excavation (CY) 0 2,328,000 600,000 0 0 2,928,000 Excavation (CY) 2,328,000 600,000 2,928,000

Fill (CY) 0 1,000,000 25,000 0 0 1,025,000 Fill (CY) 1,000,000 25,000 1,025,000

Excavation (CY) 2,328,000 600,000 Stone Placement (CY) 0 210,000 0 0 210,000 Stone Placement (CY) 210,000 12,000 222,000

Fill (CY) 1,000,000 25,000 Soil Improvement (CY) 0 370 370 Soil Improvement (CY) 271,000 370 271,370

Stone Placement (CY) 210,000 12,000 Sheet Piles (Tons) 0 2,500 8,000 0 10,500 Sheet Piles (Tons) 2,500 8,000 10,500

Soil Improvement (CY) 271,000 370 Concrete (CY) 0 8,000 200,000 0 208,000 Concrete (CY) 8,000 200,000 208,000

Sheet Piles (Tons) 2,500 8,000 Reinforcing Steel (Tons) 0 1,000 46,000 0 47,000 Reinforcing Steel (Tons) 1,000 46,000 47,000

Concrete (CY) 8,000 200,000 ACBM (SQFT) 0 28,000 32,000 0 60,000 ACBM (SQFT) 28,000 32,000 60,000

Reinforcing Steel (Tons) 1,000 46,000

ACBM (SQFT) 28,000 32,000

FEATURES RPN RDLP RGDA TOTAL FEATURES RDLP CNT 1 RPN CNT 3 TOTAL

Excavation (CY) 3,355,000 3,550,000 325,000 7,230,000 Excavation (CY) 2,328,000 600,000 2,928,000

Fill (CY) 606,400 1,224,000 520,000 2,350,400 Fill (CY) 1,000,000 25,000 1,025,000

Stone Placement (CY) 17,385 311,000 29,181 357,566 Stone Placement (CY) 210,000 12,000 222,000

Soil Improvement (CY) 122,170 122,170 Soil Improvement (CY) 271,000 370 271,370

Sheet Piles (Tons) 44,944 2,500 47,444 Sheet Piles (Tons) 2,500 8,000 10,500

Concrete (CY) 553,000 8,000 6,500 567,500 Concrete (CY) 8,000 200,000 208,000

Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055 Reinforcing Steel (Tons) 1,000 46,000 47,000

ACBM (SQFT) 793,000 793,000 ACBM (SQFT) 28,000 32,000 60,000

47PR BIG 3 ESTIMATED QUANTITIES FOR MAIN SUPPLY

NEEDS

Note: Projects are at different stages in the design process.

Estimated quantities developed with the latest available design data.

Subject to change.

FEATURES 2025 2026 TOTAL

Excavation (CY) 2,328,000 600,000 2,928,000 Fill (CY) 1,000,000 25,000 1,025,000 Stone Placement (CY) 210,000 12,000 222,000 Soil Improvement (CY) 271,000 370 271,370 Sheet Piles (Tons) 2,500 8,000 10,500 Concrete (CY) 8,000 200,000 208,000 Reinforcing Steel (Tons) 1,000 46,000 47,000

ACBM (SQFT) 28,000 32,000 60,000

Main Materials

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

RDLP CNT 1 2,323,578 2,080,528 272,000 2412 On the works On the works 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

RDLP CNT 3 1,722,000 224,000 101,000

RGDA 325,000 520,000 29,000 6,500 On the works 14000LF (60in DS), +2000CY, 50000 tons of stone protection

RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

RPN CNT 2 119,000 4,801 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?

RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

RPN CNT 5A 9,000 5,000 636 8,000 537 34,000 100 DS 72 in

RPN CNT 5B 47,000 1,400 1,100 62,000 2,500 140,000 1000 DS 60 in

RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

RPN CNT 7 300,000 100,000 3,200 75,000 2,000

RPN La Chuleta 32,460 32,460 360 360 CY of concrete, 4,834 cy of bituminous pavement

Total 7,729,038 3,463,388 419,005 121,100 32,848 563,860 71,037 799,000

Main Materials (2)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

RDLP CNT 1 2,234,000 1,962,000 272,000 2412 14000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

RDLP CNT 3 1,722,000 224,000 101,000

RGDA 325,000 520,000 29,181 6,500 On the works 14000LF (60in DS), +2000CY, 50000 tons of stone protection

RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

RPN CNT 2 119,000 4,801 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?

RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

RPN La Chuleta 31,700 31,700 360 360 CY of concrete, 2,555 tons of bituminous pavement

Total 7,667,700 3,344,100 419,770 121,100 45,748 573,860 74,755 761,000

Main Materials (3)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

RDLP CNT 1 2,234,000 1,962,000 272,000 2412 14000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

RDLP CNT 3 1,722,000 224,000 101,000

Total RDLP 3,956,000 2,186,000 373,000 0 2,412 14,000 1,000

RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

RPN CNT 2 119,000 4,801 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?

RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

RPN La Chuleta 31,700 31,700 360 360 CY of concrete, 2,555 tons of bituminous pavement

Total RPN 3,386,700 638,100 17,589 121,100 44,944 553,360 73,755 761,000

Total 7,667,700 3,344,100 419,770 121,100 47,356 573,860 76,055 761,000

Sheet2

RPN CNT 2 lb/ft2 tons

Temporary Bypass Sheet Pile 48329 sqft 36.98 893.60321

Temporary Trnasverse Sheet Pile 19275 sqft 36.98 356.39475

Transition Sheet Pile 19372 sqft 36.98 358.18828

1608.18624

Main Materials No LC

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

RDLP CNT 3 1,722,000 224,000 101,000

Total RDLP 3,956,000 2,186,000 373,000 0 2,412 8,000 1,000

RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?

RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974

Total 7,636,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974

Contract Awards

FY23 FY24 FY25 FY26 FY27 FY28

RPN CNT 2 RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3

RGDA RPN CNT 5A RPN CNT 4 RPN CNT 7

RDLP CNT 1 RPN CNT 5B

Excavation (CY) 119,000 925,000 2,243,000 327,000 2,300,000 1,722,000

Fill (CY) 0 545,000 1,967,000 146,400 430,000 224,000

Stone Placement (CY) 4,801 41,385 272,584 0 0 101,000

Soil Improvement (CY) 700 0 0 121,100 0 0

Sheet Piles (Tons) 1,608 8,000 3,048 23,500 11,200 0

Concrete (CY) 19,000 206,500 22,000 165,000 155,000 0

Reinforcing Steel (Tons) 7,000 47,300 4,505 8,250 9,000 0

ACBM (SQFT) 0 31,974 34,000 406,000 321,000 0

Main Materials No LC (2)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

Mar-25 RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

May-28 RDLP CNT 3 1,722,000 224,000 101,000

Total RDLP 3,956,000 2,186,000 373,000 0 2,412 8,000 1,000

17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

8-Jul-24 RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?

17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974

Total 7,636,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974

Contract Awards

2023 2024 2025 2026 2027 2028

RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3

RPN CNT 2 RPN CNT 5A RPN CNT 4 RPN CNT 7 FEATURES 2024 2025 2026 2027 2028 TOTAL

RDLP CNT 1 RPN CNT 5B RGDA Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,722,000 7,636,000

Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 3,312,400

Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,722,000 Stone Placement (CY) 17,005 272,584 29,181 101,000 419,770

Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 Soil Improvement (CY) 700 121,100 121,800

Stone Placement (CY) 17,005 272,584 0 29,181 101,000 Sheet Piles (Tons) 9,608 3,048 23,500 11,200 47,356

Soil Improvement (CY) 700 0 121,100 0 0 Concrete (CY) 219,000 22,000 165,000 161,500 567,500

Sheet Piles (Tons) 9,608 3,048 23,500 11,200 0 Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 76,055

Concrete (CY) 219,000 22,000 165,000 161,500 0 ACBM (SQFT) 31,974 34,000 406,000 321,000 792,974

Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 0

ACBM (SQFT) 31,974 34,000 406,000 321,000 0

FEATURES RPN RDLP RGDA TOTAL

Excavation (CY) 3,355,000 3,956,000 325,000 7,636,000

Fill (CY) 606,400 2,186,000 520,000 3,312,400

Stone Placement (CY) 17,589 373,000 29,181 419,770

Soil Improvement (CY) 121,800 121,800

Sheet Piles (Tons) 44,944 2,412 47,356

Concrete (CY) 553,000 8,000 6,500 567,500

Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055

ACBM (SQFT) 792,974 792,974

Main Materials No LC (3)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts

Mar-25 RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

May-28 RDLP CNT 3 1,222,000 224,000 101,000

Total RDLP 3,456,000 2,186,000 373,000 0 2,412 8,000 1,000

17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

8-Jul-24 RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?

17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974

Total 7,136,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974

Contract Awards

2023 2024 2025 2026 2027 2028

RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3

RPN CNT 2 RPN CNT 5A RPN CNT 4 RPN CNT 7 FEATURES 2024 2025 2026 2027 2028 TOTAL

RDLP CNT 1 RPN CNT 5B RGDA Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,222,000 7,136,000

Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 3,312,400

Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,222,000 Stone Placement (CY) 17,005 272,584 29,181 101,000 419,770

Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 Soil Improvement (CY) 700 121,100 121,800

Stone Placement (CY) 17,005 272,584 0 29,181 101,000 Sheet Piles (Tons) 9,608 3,048 23,500 11,200 47,356

Soil Improvement (CY) 700 0 121,100 0 0 Concrete (CY) 219,000 22,000 165,000 161,500 567,500

Sheet Piles (Tons) 9,608 3,048 23,500 11,200 0 Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 76,055

Concrete (CY) 219,000 22,000 165,000 161,500 0 ACBM (SQFT) 31,974 34,000 406,000 321,000 792,974

Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 0

ACBM (SQFT) 31,974 34,000 406,000 321,000 0

FEATURES RPN RDLP RGDA TOTAL

Excavation (CY) 3,355,000 3,456,000 325,000 7,136,000

Fill (CY) 606,400 2,186,000 520,000 3,312,400

Stone Placement (CY) 17,589 373,000 29,181 419,770

Soil Improvement (CY) 121,800 121,800

Sheet Piles (Tons) 44,944 2,412 47,356

Concrete (CY) 553,000 8,000 6,500 567,500

Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055

ACBM (SQFT) 792,974 792,974

CMP QTYs

[yd3] [Tons] [Tons] [yd3] [Tons]

Estimated award date Materials: Dedging Stone Placement Steel Sheet Pile Concrete Reinforcing Steel Concrete Culverts

Oct-24 CMP CNT 2 22,000 13,200 323 105 14 4 concrete culverts (need to estimate this and add to concrete quantities)

Oct-25 CMP CNT 3 PH1 440,000 1,650 3,274 1,173 155 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold

Feb-28 CMP CNT 3 PH2 300,000 7,857 2,816 373

Total CMP 762,000 14,850 11,454 4,094 542

17-Jun-27 RGDA 14000LF (60in DS), +2000CY, 50000 tons of stone protection

28-Nov-25 RPN CNT 1 30,000 CY of concrete, asphalt 28990 SY

19-Jul-24 RPN CNT 2 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

8-Jul-24 RPN CNT 3 1600 DS 72 in ERROR:#NAME?

17-Aug-26 RPN CNT 4 1200 DS 60 in

3-Jan-25 RPN CNT 5A 100 DS 72 in, 1000 tons of riprap

30-Jun-26 RPN CNT 5B 1000 DS 60 in

28-May-27 RPN CNT 6 1300 DS 60 in

30-Jun-27 RPN CNT 7 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 0 0 0 0 0 0 0 0

Total 762,000 14,850 11,454 4,094 542 0 0 0

Contract Awards

2023 2024 2025 2026 2027 2028

CMP CNT 2 CMP CNT 3 PH1 RDLP CNT 3

FEATURES 2024 2025 2026 2027 2028 TOTAL

Dredging (CY) 22,000 440,000 300,000 762,000

Stone Placement (Tons) 13,200 1,650 14,850

Dredging (CY) 22,000 440,000 0 0 300,000 Steel Sheet Pile (Tons) 323 3,274 7,857 11,454

Stone Placement (Tons) 13,200 1,650 0 0 0 Concrete (CY) 105 1,173 2,816 4,094

Steel Sheet Pile (Tons) 323 3,274 0 0 7,857 Reinforcing Steel (Tons) 14 155 373 542

Concrete (CY) 105 1,173 0 0 2,816

Reinforcing Steel (Tons) 14 155 0 0 373

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

FEATURES CNT 2 CNT 3 PH1 CNT 3 PH2 TOTAL

Dredging (CY) 22,000 440,000 300,000 762,000

Stone Placement (Tons) 13,200 1,650 14,850

Steel Sheet Pile (Tons) 323 3,274 7,857 11,454

Concrete (CY) 105 1,173 2,816 4,094

Reinforcing Steel (Tons) 14 155 373 542

Main Materials (RPN3-RDLP1)

[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]

Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts 1780000

Mar-25 RDLP CNT 1 2,328,000 1,000,000 210,000 271,000 2500 8000 1000 28000 4 concrete culverts (need to estimate this and add to concrete quantities) 772000

RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold 160000

May-28 RDLP CNT 3 1,222,000 224,000 101,000

Total RDLP 3,550,000 1,224,000 311,000 271,000 2,500 8,000 1,000

17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection

28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY

19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)

1-Jun-26 RPN CNT 3 600,000 25,000 12,000 370 8,000 200,000 46,000 32,000 1600 DS 72 in ERROR:#NAME?

17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in

3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap

30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in

28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in

30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed

Total RPN 3,355,000 606,400 17,385 122,170 44,944 553,000 73,755 793,000

Total 7,230,000 2,350,400 357,566 393,170 47,444 567,500 76,055 821,000

Contract Awards

2023 2024 2025 2026 2027 2028

RDLP CNT 1 RPN CNT 3

FEATURES 2024 2025 2026 2027 2028 TOTAL FEATURES 2025 2026 TOTAL

Excavation (CY) 0 2,328,000 600,000 0 0 2,928,000 Excavation (CY) 2,328,000 600,000 2,928,000

Fill (CY) 0 1,000,000 25,000 0 0 1,025,000 Fill (CY) 1,000,000 25,000 1,025,000

Excavation (CY) 2,328,000 600,000 Stone Placement (CY) 0 210,000 0 0 210,000 Stone Placement (CY) 210,000 12,000 222,000

Fill (CY) 1,000,000 25,000 Soil Improvement (CY) 0 370 370 Soil Improvement (CY) 271,000 370 271,370

Stone Placement (CY) 210,000 12,000 Sheet Piles (Tons) 0 2,500 8,000 0 10,500 Sheet Piles (Tons) 2,500 8,000 10,500

Soil Improvement (CY) 271,000 370 Concrete (CY) 0 8,000 200,000 0 208,000 Concrete (CY) 8,000 200,000 208,000

Sheet Piles (Tons) 2,500 8,000 Reinforcing Steel (Tons) 0 1,000 46,000 0 47,000 Reinforcing Steel (Tons) 1,000 46,000 47,000

Concrete (CY) 8,000 200,000 ACBM (SQFT) 0 28,000 32,000 0 60,000 ACBM (SQFT) 28,000 32,000 60,000

Reinforcing Steel (Tons) 1,000 46,000

ACBM (SQFT) 28,000 32,000

FEATURES RPN RDLP RGDA TOTAL FEATURES RDLP CNT 1 RPN CNT 3 TOTAL

Excavation (CY) 3,355,000 3,550,000 325,000 7,230,000 Excavation (CY) 2,328,000 600,000 2,928,000

Fill (CY) 606,400 1,224,000 520,000 2,350,400 Fill (CY) 1,000,000 25,000 1,025,000

Stone Placement (CY) 17,385 311,000 29,181 357,566 Stone Placement (CY) 210,000 12,000 222,000

Soil Improvement (CY) 122,170 122,170 Soil Improvement (CY) 271,000 370 271,370

Sheet Piles (Tons) 44,944 2,500 47,444 Sheet Piles (Tons) 2,500 8,000 10,500

Concrete (CY) 553,000 8,000 6,500 567,500 Concrete (CY) 8,000 200,000 208,000

Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055 Reinforcing Steel (Tons) 1,000 46,000 47,000

ACBM (SQFT) 793,000 793,000 ACBM (SQFT) 28,000 32,000 60,000

HEAVY EQUIPMENT

• Excavator

• Dredging Equipment

• Dozer

• Loader

• Backhoe loader

• Roller compactor

• Sheepsfoot roller

• Crane

• Water truck

• Dump truck (on-road and off-road)

• Generators

• Pumps

• Vibratory hammer

• Impact hammer

• Power unit

Note: This list is not all inclusive

SERVICES

Note: This list is not all inclusive

• QC Staff Personnel:

• Surveyors,

• Geotechnical and Structural Consultants,

• Scheduler,

• Environmental Monitoring (Puerto Rican Boa Monitor, Manatee

Observer, Environmental Compliance Inspections), etc.

• Safety Personnel

• Vibration Monitoring

• Material Testing

MATERIAL TESTING

Note: This list is not all inclusive of all the required tests

Aggregates C 33 - Standard Specification for Concrete

Aggregates C 88 - Soundness of Aggregates C 117 - Material Finer than 75 μm (No. 200)

Sieve C 127 - Density, Relative Density, and

Absorption of Coarse Aggregates C 128 - Density, Relative Density, and

Absorption of Fine Aggregates C 131 - Resistance to Degradation by Abrasion and Impact C 136 - Sieve Analysis of Aggregates C 535 - Resistance to Degradation of Large-Size

Coarse Aggregate C 566 - Total Moisture Content

Concrete C 39 - Compressive Strength of Cylindrical

Specimens C 143 - Slump C 231 - Air Content by Pressure C 1064 - Temperature of Concrete

Masonry C 109 - Compressive Strength of Cement Mortars Using Cube Specimens

Bituminous D 2726 - Bulk Specific Gravity and Density of Non- Absorptive Compacted Bituminous Mixtures D 2950 - Density of Bituminous Concrete in Place by Nuclear Methods D 6926 - Preparation of Bituminous Specimens Using Marshall Apparatus D 1074 - Compressive Strength of Bituminous Mixtures

Soils D 698 - Compaction Characteristics by Standard Effort D 1556 - Density & Unit Weight by Sand Cone D 1557 - Compaction Characteristics by Modified Effort D 2166 - Unconfined…

This is the start of the file's text. The full file is on GovTribe.