This document is the Questions and Answers (Q&A) exhibit for Solicitation W51AA1-25-R-0003, a sealed bid invitation for paving and line painting work on the U-Lot parking area at Tobyhanna Army Depot in Pennsylvania. Key details include:
The solicitation requires excavation, regrading, paving, and line striping of the U-Lot. Bidders are instructed not to price CLIN 0002 as it is a not-separately-priced post-award item. Warm mix asphalt for the wearing course is acceptable. A formal traffic control plan is not required, but access to 1B West must be maintained. The anticipated 70-day period of performance may be extended if weather conditions warrant deferring completion to Spring 2025. Bids are due by 1:00 PM EST on October 30, 2024. This is a 100% small business set-aside with a $45 million size standard. The Government estimates the magnitude of construction to be between $150,000 and $250,000.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposal W51AA1-25-R-0003 Project Title: U-Lot Paving and Line Painting
Exhibit 6 - Questions and Answers
Date: 21 October 2024
Note: Verbiage may have changed from the initial Requests for Information (RFI)/Questions submitted, however, the context of the questions did not. Similar questions may have been combined and one answer provided. If you feel as though a(n) RFI/Question you submitted was not addressed, or was done so without providing a clear and concise answer, please notify the Contracting Officer, Mark Buonomo.
This Question and Answer document shall be incorporated into the solicitation and any resultant contract and considered binding.
Question #1: Please confirm if the transformer being removed is sitting on a vault and will need to be demoed and filled in.
Answer #1: The transformer has been removed and vault was demoed 2 feet below grade and backfilled.
Question #2: Please confirm that all excess blacktop and stone will need to be disposed of off the base.
Answer #2: Confirmed. Material to be disposed of off the base. However, Contractors may submit a request to the Government to dispose of material onsite.
Question #3: Due to the time of the year that paving will occur, is it acceptable to change the wearing course to a warm mix asphalt design or wait to top the parking lot when the weather conditions permit in the spring?
Answer #3: Warm mix is acceptable for wearing course application.
Question #4: Please confirm that an official traffic control plan will be needed and how much notice will be needed for the shutdown?
Answer #4: A formal traffic control plan is not required. However, access to 1B West will need to be maintained throughout performance.
Question #5: Reference solicitation, CLIN 0002. Confirm that item needs no pricing, due to it being a post award document ?
Answer #5: Confirmed. Bidders are instructed NOT to submit pricing for CLIN 0002 or to complete Exhibit 5 - CDRL 001. CLIN 0002 is a Not Separately Priced (NSP) line item and Exhibit 5 is to be completed by the awardee after contract award.
Exhibit 6 – Questions and Answers Invitation for Bid W51AA1-25-R-0003
Question #6: Could you confirm the project has to be completed within 70 calendar days from the date of award? By the time all approvals are finalized, and construction is ready to begin, it will be close to Thanksgiving. During this time of year, temperatures in the Pocono Mountains are highly variable and unpredictable. Given these factors, is it possible to defer the project until Spring 2025
Answer #6: The anticipated number of calendar days to complete the project in its entirety shall remain unchanged. However, if, during performance, weather becomes unsatisfactory, the Government will consider stopping work and extending the PoP to allow completion in Spring 2025.