B08 Att 0024 PWS Annex A - Maintenance PRS.pdf

PDF 260 KB Posted

Attached to
EAGLE Ft. Carson CO W519TC-27-R-A014
Solicitation number
W519TC-27-R-A014
Issued by

About this file

This document is a Performance Work Statement (PWS) Annex A detailing the Maintenance Performance Requirement Summary (PRS) for equipment repair shop operations. The PRS establishes quality standards, sampling methods, and Acceptable Quality Levels (AQL) across multiple maintenance service categories.

The maintenance scope encompasses materiel maintenance general operations (5.1.1, 5.1.4), including establishment and management of repair shops with 95% AQL and random sampling conducted periodically. Materiel maintenance support requirements (5.2.1) address repair work performed in accordance with Technical Manuals, Technical Bulletins, Modification Work Orders, and equivalent publications, with 95% AQL for general repairs and differentiated AQLs of 97% for mechanical and 98% for electrical work to meet first-time pass rates. Additional maintenance support includes air conditioning and refrigeration services (5.2.12) compliant with 40 CFR Part 82 at 95% AQL. Materiel maintenance programs and efforts (Section 5.3) cover performance metrics, wheel alignment, glass repairs (all 95% AQL), sensitive items management (100% AQL with monthly sampling), and Small Arms Repair Parts management (100% AQL, monthly). Allied trades (Section 5.4) encompass welding and non-destructive testing by certified personnel, metal machining, painting and body repair services (95% AQL), and paint booth maintenance (100% AQL, periodic). Repair parts and materiel management (5.5.1) requires shop supply services using automated Army supply systems at 95% AQL, and Standard Pricing item management at 95% AQL with periodic sampling. Production control (5.6.1) mandates workload management capability at 95% AQL. Food Service Equipment maintenance (Section 5.7) requires preventive, scheduled, and unscheduled repair services at 90% AQL with bi-weekly sampling, inspector services at 90% AQL, 24-hour response times for unscheduled calls, and use of Other Direct Costs (ODCs) for specialized repairs requiring unique skillsets.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PWS Annex A – Maintenance Performance Requirement Summary (PRS)

Task/Requirement Standard Sampling Method, Lot & Acceptable

Quality Level (AQL)

MATERIEL MAINTENANCE – GENERAL

5.1.1 Establish, operate, and manage equipment repair shops, and supporting functions.

Quality: IAW AR 750-1, DA PAM 750-8, applicable LIS publications, installation policies and procedures, external and internal SOPs, and materiel maintenance and ISM Operating Manual.

Random sampling (shop/activity scheduled periodically)

Lot: All in-process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.

AQL: 95%

5.1.4 Perform technical inspections in accordance with the maintenance request.

Quality: IAW AR 750-1, DA PAM 750-8, applicable LIS publications, installation policies and procedures, external and internal SOPs, and materiel maintenance (COR) guidance.

Random (shop/activity scheduled periodically)

Lot: All in-process and completed work orders, files, logs, and SOPs at time of

MATERIEL MAINTENANCE SUPPORT

5.2.1 Perform repairs IAW work request and applicable equipment TMs or equivalent publications.

Quality: Repairs will be IAW the maintenance request and to standards, to include estimated task times, as stated in current equipment Technical Manuals (TMs), Technical Bulletins (TBs), Modification Work Orders (MWOs), Safety of Use Messages (SOUMs), Special Technical Inspection and Repairs (STIRs), other applicable Government technical publications, or OEM equivalent publications when a Government technical publication is not available.

Random sampling

Lot: All in-process and completed work as well as all existing records and files within the shop or activity undergoing

5.2.1 Ensure minimum rejection rates for mechanical and electrical repair work completed are met in order to meet first time pass rates.

Quality: IAW AR 750-1, Appendix B-11, paragraphs (a-d)

Random (shop/activity scheduled periodically)

Lot: Equipment that has completed the repair cycle and has been deemed as ready for issue (RFI) back to the customer.

AQL: 97% for mechanical AQL: 98% for electrical

5.2.12 Perform all air conditioning & refrigeration maintenance / repair services.

Quality: IAW40 CFR, Part 82, and applicable state and federal regulations, and the installation environmental regulations and directives. Quality: Special measurement items ordered IAW directive IAW AR 700-84.

Random (shop/activity scheduled periodically)

Lot: All in-process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.

AQL: 95%

MATERIEL MAINTENANCE – PROGRAMS/EFFORTS

5.3.2 Meet performance metrics found in AR 750-1 for base operations metrics.

Timeliness: Tasks completed within time allowed by the specific equipment publication or within times estimated at work induction or other program standard as designated by Chief, Materiel Maintenance/COR.

Quality: Perform maintenance IAW the maintenance request and to standards, to include estimated task times, as stated in current equipment TMs, TBs, MWOs, SOUMs, STIRs, other applicable government technical publications, or OEM equivalent publications when a government technical publication is not available.

Random (shop/activity scheduled periodically)

Lot: All in-process and completed work as well as all existing records and files within the shop or activity undergoing surveillance.

AQL: 95%

5.3.8 Maintain, repair, and replace tires on rims.

Quality: IAW TM 9-2610-200-14

Random (shop/activity scheduled periodically)

Lot: The number of line items on receipts processed on the day of surveillance.

5.3.9 Provide wheel alignment support.

Quality: IAW applicable TMs and standards.

Random (shop/activity scheduled periodically)

Lot: All in process and completed work related to replacing front axle components (tie-rod/sway bar).

5.3.10 Perform glass repairs for vehicles.

Quality: Glass shall be installed to original design configurations with seals that are air and watertight.

Random (shop/activity scheduled periodically)

Lot: All in process and completed glass repair work as well as all existing logs and files at time of surveillance.

AQL: 95%

5.3.11 Perform maintenance and services of sensitive items.

Quality: AR 190-11, AR 710-2 and AR 750-1.

Monthly

Lot: All parts/items in process

AQL: 100%

5.3.11 Maintain physical security of the Material Maintenance Arms room and sensitive items.

Timeliness: Notify the COR immediately of the discovery of a missing sensitive item or major administrative discrepancy.

Quality: IAW AR 190-11, AR 710-2, AR 750-1, DA PAM 750-8, and local SOPs.

Random (shop/activity scheduled periodically)

Lot: All in process and completed sensitive item work as well as all existing records and files within the shop or activity undergoing surveillance.

AQL: 100%

5.3.12 Management of Small Arms Repair Parts (SARP).

Quality: IAW AR 710-2, AR 750-1, and ASC Supplement 750-1

Monthly

Lot: All parts in process

AQL: 100%

ALLIED TRADES—Should this be deleted?

5.4.1 Perform welding, and Non-destructive testing as required.

Timeliness: Work completed IAW time estimates given at work induction.

Quality: Work performed IAW work request and applicable military and industry standards. Welding

Random (shop/activity scheduled periodically)

Lot: All in process and completed welding, as well as all existing logs and files at time of surveillance.

performed by AWS certified welders;

NDI performed by ANSI/ASNT CP-189 certified persons.

5.4.2 Perform metal machining, and fabrication operations and Non-destructive testing as required.

Timeliness: Work completed IAW time estimates given at work induction.

Quality: Work performed IAW work request and applicable military and industry standards. NDI performed by ANSI/ASNT CP-189 certified persons.

Random (shop/activity scheduled periodically)

Lot: All in process and completed metal machining and fabrication work as well as all existing logs and files at time of surveillance.

AQL: 95%

5.4.3 Prepare and paint supported equipment and components as required to perform materiel maintenance.

Timeliness: Work completed IAW time estimates given at work induction.

Quality: Work completed IAW AR 750- 1, applicable equipment TM 43-0139, TB 43-0209 and industry standard.

Random (shop/activity scheduled periodically)

Lot: All in process and completed body shop work as well as all existing logs and

5.4.3.1 Operate and maintain Materiel Maintenance paint booths and breathing air machines.

Quality: IAW OSHA 29 CFR 1910-107, AR 200-1

Periodic

Lot: All materiel maintenance paint booths and breathing air machines at time of surveillance.

AQL: 100%

5.4.4 Perform body repair services.

Timeliness: Work completed IAW time estimates given at work induction.

Quality: Work completed IAW AR 750- 1, applicable equipment TM, and industry standard.

Random (shop/activity scheduled periodically)

Lot: All in process and completed body shop work as well as all existing logs and

REPAIR PARTS AND MATERIEL MANAGEMENT TASKS

5.5.1 Perform shop supply services;

use the automated Army supply

Quality: IAW AR 750-1, AR 710-2, DA

PAM 25-30, AR 725-50, DA PAM 710-2-

Random (shop/activity scheduled periodically) system as the primary means of attaining materiel.

2; AR 740-1; AR 735-5; AR 710-1; AR

710-3; DA Pam 710-7; AR 710-3, AR 710-4; FEDLOG; and LIS user’s manual

Lot: All in-process and completed work orders, requisitions, requests, files, records, SOPs, and stockage at time of surveillance.

AQL: 95%

5.5.6 Manage Standard Pricing (SP) items.

Timeliness: Meet SP turn- in criteria for timeliness of turn-ins.

Quality: IAW DFAS-IN Reg 37-1 Chapter 13, finance & accounting policy, implementation, unserviceable turn-ins, and current army guidance.

Periodic

Lot: The numbers of SP items processed during the period at time of surveillance.

PRODUCTION CONTROL

5.6.1 Operate a production control capability that effectively manages the maintenance workload; provide personnel technically capable of performing all tasks found in the applicable maintenance LIS End User Manual. Operate multiple equipment receiving points; provide order statuses.

Timeliness: Work completed IAW time estimates given at work induction.

Quality: IAW work request, AR 750-1, DA PAM 750-1, DA PAM 750-8, applicable LIS publications, local policies and procedures.

Random

Lot: All in process and completed work as well as all existing logs and files at time of surveillance

AQL 95%

FOOD SERVICE EQUIPMENT

5.7.1 Provide preventive, scheduled, and unscheduled repair

services.

Quality: IAW Density list

Bi-Weekly

Lot: All in process and completed work as well as all existing records and files within the shop or activity undergoing

AQL:90%

5.7.2 Perform inspections, services, and maintenance.

Quality: IAW applicable technical manual / manufacturer's instructions.

Random

Lot: All in process and completed work as well as all existing records and files within the shop or activity undergoing

AQL: 90%

5.7.3 Provide unscheduled

maintenance.

Timeliness: Unscheduled maintenance service calls are responded to within 24 hours or 1 business day of notification from DFAC maintenance

POC.

Random

Lot: All in process and completed work as well as all existing records and files within the shop or activity undergoing

5.7.4 Utilizing ODCs to perform

maintenance tasks.

Quality: ODCs approved by DFAC

Manager are utilized when contractor does not possess a unique skillset needed to complete a repair/service.

Random

Lot: All in process and completed work as well as all existing records and files within the shop or activity undergoing

File details come from the government source that posted it. Updated .