25-4-05 Quality Assurance Surveillance Plan.xls

XLS spreadsheet 42 KB Posted

Attached to
Airlock Doors - Rock Island Arsenal
Solicitation number
W519TC27RA013
Issued by

About this file

This is a Quality Assurance Surveillance Plan (QASP) template document in spreadsheet format. The file is designed to establish monitoring and evaluation procedures for contractor performance on the Airlock Doors project at Rock Island Arsenal. While the specific performance metrics and surveillance activities are not detailed in the provided file reference, this QASP would typically outline inspection schedules, acceptance criteria, testing protocols, and performance standards that the contractor must meet throughout the contract execution period. The plan serves as the government's tool for ensuring the contractor delivers compliant products and services in accordance with the solicitation requirements for the airlock door installation and construction activities at Rock Island Arsenal's Joint Manufacturing and Technology Center.

View the file

Other files

File Type Posted
W519TC27RA013.pdf PDF
RIPD E4000-25-4-05 Airlock Wall B299 (R1) (10-Nov-26).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QASP

TaskContract ReferenceFrequencyPerformance StandardAcceptable Quality LevelSurveilance MethodSurveilance Date(s)Performance LevelNotes
Site ConferenceSheet 1 - Security NotesOnceEach individual working at the site must receive this information for safety and accountability purposes. May be updated if additional personnel come to the work site. May be performed as part of the badging process.100%Visual/Roster
Work RosterSheet 1 - Security NotesDailyMust be maintained for safety and security purposes. Must show who is at the work-site at any given time.90%Written Roster
Project TimelineDictated by contractOnceTo be provided within 1-week of award of the contract. Must show plan for completion prior to the date stated in the contract. May be adjusted during performance provided within project completion date.100%Visual/Written
Site InspectionSheet 1 - Security NotesDailyObserve work is being performed safely and in accordance with the contractor provided timeline and IAW the contracted Scope of Work90%Visual
Materials InspectionsSheet 1 - Notes 1-17RandomMaterials provided by the contractor may be inspected to ensure that they meet the contracted Scope of Work and minimum industry and design standards. (e.g. slump or temperature tests of incoming concrete)100%Visual/ Measurement
Final InspectionSheet 1 - Notes 1-17OnceVerify that all work is completed IAW the contracted Scope of Work100%Visual

&LRock Island Arsenal Quality Assurance Surveillance Plan&CAirlock Wall&RTARA-LG-25-4-05

DATE: 06-10-2026