A02_Attachment 0002_CAAA FORM 702-37 Ball Bearings.pdf

PDF 123 KB Posted

Attached to
BALL BEARINGS
Solicitation number
W519TC-26-Q-BALL
Issued by

About this file

This is a Quality Assurance Acquisition Review Attachment that establishes quality requirements and testing procedures for a ball bearings contract dated March 23, 2026 (Control No. MS 19060-1008).

The quality assurance requirements specify standard inspection under FAR 46.202-3, with government contract quality assurance performed at destination per FAR 46.4. Acceptance will occur at destination per FAR 46.5. Preservation, packaging, and packing must comply with ASTM D 3951 (Commercial Packaging). Certified material/analysis is required, and the Contracting Activity Quality Assurance (CAAA) requires seven days to perform test/evaluation in accordance with MS 19060-1008 prior to approval or disapproval. First article testing will be government-performed under FAR 9-308-2 with Clause 52.209-4, requiring 10 units in accordance with MS 19060-1008 and notification of disposition within 7 calendar days. The government testing performance requirement specifies 100% of all drawing characteristics must be tested. No pre-award survey or post-award conference has been requested, and no alternate bids with or without first article approval or approved first article as part of contract quantity are anticipated. This document serves as the quality control framework for the ball bearings acquisition.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE

ACQUISITION REVIEW ATTACHMENT - PART 1

1. FAR CONTRACT QUALITY REQUIREMENTS - FAR 46.2:

2. GOVERNMENT CONTRACT QUALITY ASSURANCE - FAR 46.4

3. ACCEPTANCE - FAR 46.5

a.

c.

Commercial Items - FAR 46.202-1

Contractor Inspection - FAR 46.202-2 - Clause 52.246-1 a.

a.

b.

b.

Higher Level - FAR 46.202-4 - Clause 52.246-11 e.

Other

Certificate of Conformance FAR 46.315- Clause 52.246-15 d.

Clause

Other

ISO 9001

Source

Source

Destination

Destination

FAT WAIVED f. FAT REQUIRED b.

4. PREPARATION FOR DELIVERY:

Additional Requirements

Marking in accordance with MIL-STD-129.

of

Preservation, Packaging, and Packing in accordance with

Preservation, Packaging, and Packing in accordance with of Commodity Specification.

Level

ASTM D 3951 (COMMERCIAL PACKAGING)

Level e.

c.

d.

a.

b.

Preservation, Packaging, and Packing in accordance with

Standard Inspection - FAR 46.202-3:

Signature

CAAA FORM 702-37, May 09

5. PRE-AWARD SURVEY REQUESTED - FAR 9.106

6. POST AWARD CONFERENCE REQUESTED - FAR 42.503

7. CERTIFIED MATERIAL/ ANALYSIS REQUIRED (Attached)

8.

DAYS REQUIRED FOR CAAA TO PERFORM TEST/EVALUATION IN

ACCORDANCE WITH

9. QUALITY ASSURANCE PROVISIONS SAMPLING INSPECTION ATTACHED

10. QUALITY ASSURANCE LETTER OF INSTRUCTION TO BE PROVIDED TO DCMA

WHEN CONTRACT AWARDED

11. QUALITY ASSURANCE PROVISIONS SAMPLING INSPECTION ATTACHED

PRIOR TO APPROVAL/ DISAPPROVAL

CONTROL NO: DATE:

Ball Bearings 23 March 2026

X

X

X

X

X

X

X 7

MS 19060-1008

QUALITY ASSURANCE

ACQUISITION REVIEW ATTACHMENT - PART 2

1. FIRST ARTICLE TESTING AND APPROVAL - FAR 9.3

a. CONTRACTOR TESTING - FAR 9-308-1- Clause 52.209-3 with Alternate 1.

Units in accordance with

Test Notification calendar days prior to test.

calendar days.

calendar days.

First Article report within

Notification of disposition within

b. GOVERNMENT TESTING - FAR 9-308-2 - Clause 52.209-4 with

Units in accordance with c.

d.

e.

f.

(1) calendar days. Notification of disposition within 7777

Alternate bids with/ without First Article.

Approved First Article as part of contract quantity.

Approved First Article to serve as manufacturing standard.

Estimated cost of Government Performed Testing

CONTRACTOR TESTING

Performance/ Characteristics a.

2. REQUIREMENTS :

(2) Technical Requirements for Test

(3) Data to be submitted

GOVERNMENT TESTINGb.

(1) (2)Performance/ Characteristics Technical Requirements for Test

CAAA FORM 702-37, May 2009

CONTROL NO: DATE:

Ball Bearings 23 March 2026

X

MS 19060-100810

100% of all drawing characteristics

2026-03-23T09:36:49-0400
NOLLEY.GINA.L.1274379029

File details come from the government source that posted it. Updated .