B08_Attachment_0003_PWS_Description_26Q3178.pdf
PDF 132 KB Posted
- Solicitation number
- W519TC26Q3178
About this file
This is a Statement of Work for the replacement of fire tubes on two Cleaver-Brooks boilers (Model CB200-250-150ST, Serial Numbers L54363 and L54362) located in Building 165 at the McAlester Army Ammunition Plant (MCAAP). A severe leak in an isolated fire tube has rendered both units inoperable, requiring restoration to safe operational status.
The contractor shall mobilize a certified boiler mechanic and supply all necessary specialized tools, piping, hardware, and electrical components to complete the work. Technical execution includes cutting two flush patches on each side of the fire tunnel (or utilizing tube ligament repair as a secondary option if flush patching is infeasible), removing legacy fire tubes and installing government-furnished replacement tubes, and performing seal welding in accordance with applicable ASME codes. The contractor is responsible for performing a hydrostatic test of both boilers up to standard operating pressure to verify structural integrity and completing formal closing/sealing of both waterside and fireside of the vessels. Daily housekeeping is required to restore the work area to pre-work condition, with the contractor responsible for disposing of generated waste into government-provided dumpsters. All work must be completed within 30 calendar days of mobilization during normal business hours (Monday through Friday, excluding federal holidays) unless authorized in writing by the Contracting Officer. The contractor must comply with all OSHA guidelines and USACE EM 385-1-1 safety regulations and is responsible for damage caused directly by contractor personnel or equipment. All contractor personnel must be U.S. citizens, pass background checks for MCAAP entry credentials, and coordinate gate access at least two business days prior to mobilization. The Government will furnish replacement fire tubes, utilities (electricity, water, sanitary facilities), and on-site trash dumpsters.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Boiler Fire Tubes — Building 165 (MCAAP)
1.0 Background and Scope
The McAlester Army Ammunition Plant (MCAAP) has a requirement to replace the fire tubes on Boiler No. 1 and Boiler No. 2 located in Building 165. A severe leak in an isolated fire tube has rendered the units inoperable. The contractor shall mobilize a certified boiler mechanic to perform all necessary labor, cutting, welding, installation, and testing required to return both boilers to safe operational status.
2.0 Equipment Details
The work shall be performed on the following government-owned equipment:
Equipment Description Model Number Serial Number Location
Boiler No. 1 Cleaver-Brooks CB200-250-150ST L54363 Building 165
Boiler No. 2 Cleaver-Brooks CB200-250-150ST L54362 Building 165
3.0 Technical Requirements & Contractor Tasks
The Contractor shall perform the following tasks:
• Mobilization: Mobilize a qualified boiler mechanic to the job site. The contractor shall supply all necessary specialized tools, piping, hardware, and electrical components required to complete the installation.
• Technical Execution:
• Cut two (2) flush patches on each side of the fire tunnel. If a flush patch is technically unfeasible, a tube ligament repair shall be utilized as the secondary option.
• Remove legacy fire tubes and install the government-furnished replacement fire tubes.
• Perform seal welding of tubes as necessary in accordance with applicable ASME codes.
• Testing & Restoration:
• Perform a hydrostatic test ("hydro") of the boilers up to standard operating pressure to verify structural integrity.
• Complete the formal closing/sealing of both the waterside and fireside of the vessels.
• Housekeeping: Clean and restore the work area to its pre-work condition daily.
The contractor is responsible for disposing of contractor-generated waste into the government-provided dumpsters.
4.0 Government-Furnished Property (GFP) and Services
The Government will provide the following to facilitate the work:
• Materials: Replacement fire tubes (to be received, unloaded, hauled, and staged near the boilers by the Government).
• Utilities: Electricity, water, and access to sanitary facilities.
• Disposal: On-site trash dumpsters for work-related waste.
5.0 Period of Performance and Hours of Work
• Hours: All work shall be performed during normal business hours, Monday through Friday, excluding federal holidays, unless authorized in writing by the Contracting Officer (KO).
• Timeline: The contractor shall complete all work within (30) calendar days of mobilization.
6.0 Safety and Liability
• Safety Standards: The contractor shall comply with all OSHA guidelines and USACE EM 385-1-1 safety regulations.
• Liability: The contractor is responsible for any damage caused directly by their personnel or equipment during execution. The contractor is not liable for pre-existing damage, or waste left behind by third parties.
7.0 Security Requirements (Installation Access)
• All contractor personnel must be U.S. citizens and must pass a background check to obtain entry credentials to MCAAP.
• The contractor shall coordinate gate access and escort requirements with the POC least (2) business days prior to mobilization.