This is a Questions and Answers document dated 17 November 2026 for a Fluidized Bed Mixer Facility contract opportunity. The document addresses 24 questions submitted by potential contractors regarding facility specifications, process requirements, equipment scope, and solicitation administration details.

Key technical clarifications include: the facility roof height varies approximately 15 to 21 feet; utilities specifications are detailed in sections 3.10 to 3.13 of the revised Problem Statement Rev 3; material currently passes through a sifter after discharge from the fluid bed and is discharged into a Glatt transportainer; incoming process air humidity specifications are in section 3.1.6.3 of the revised statement; potassium chlorate requires de-clumping but oversized materials should not be discarded; a separate HEPA filter bank exhausts air to the atmosphere with a dust separator recommended before the filters; Class II Division 1 Groups F and G apply in designated areas per drawing E-100; the system uses only water-based polyvinyl alcohol formulation with no acetone; fluidization operates on an open cycle with water vapor only; and a high-speed fire detection and suppression system is within contractor scope per section 3.8. The 30% throughput improvement requirement has been removed and replaced with a request for the highest throughput possible with contractor-provided options. The facility is a remodeled empty space, and material handling battery limits and design suggestions are open to contractor proposals. The amendment validity period was clarified as 240 days, and Problem Statement Rev 3 has been issued to supersede previous revisions. DoD 4145.26 does not apply to this contract. Solicitation extensions may occur for answering questions, providing new documents, or releasing updated drawings.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers 2

17 November 2026

Questions received:

1. Room/Facility dimensions to ensure proposed equipment will fit in existing space.

2. Utilities available- electric- voltage, amps, etc, steam-if so pressure, water-hot, cold-flow pressure, chilled water-glyco% gas? Compressed air-pressure, flow.

3. Current process flow and times, recovery efficiency?

4. Can you share general current process parameters-airflow, spray rate, etc.

5. How is material brought into facility -bags, drums, super snacks etc. to be unloaded/weighed

6. After discharge from fluid bed is material screened or milled?

7. What is material discharged into? Drums, bags, etc.

8. Is there a specification for incoming process air humidity/RH?

9. Potassium chlorate- does it require milling or just screening? Is there a particle size target-ok to screen and discard oversized materials or should they be milled?

10. Is dust collection required after the fluid bed filters?

11. Is the entire facility Class 1 Div 1 rated or just the processing rooms- is it safe to assume technical areas are non hazardous rated?

12. Bulk density of starting and finished blend.

13. The amendment cited Problem Statement Rev 02 dated 15 September 2026, but the issued file is Rev 01 dated 03 August 2026. Which revision Governs, and will Rev 02 be released?

14. The submission packet requires Class and II, Division 1. The problem statement specifies Class II Division 1 Groups F and G only. Which classification controls and which groups apply?

15. At what process step and quantity per bath is acetone introduced? Is nitrocellulose introduced as a lacquer spray or as fiber at another step?

16. Is an inserted, closed- cycle fluidization system with solvent recovery required, or is open-cycle with vapor abatement acceptable?

17. Where do material handling battery limits begin and end: drum, tote, tank, or tanker receipt? Is this a new facility or a refit?

18. What target batches per day or campaign volume should the operational plan size against?

19. The amendment states packages remain valid for sixty (240) days. Which period is intended? 60 or 240?

20. Do DoD 4145.26 and explosive safety sitting requirements govern the layout in addition to combustible dust standards?

21. What is the current throughput of the legacy system (batch size, batches per shift, and cycle time) against which the minimum 30% throughput improvement will be measured?

22. Is there an existing high-speed fire detection and suppression system in the building that new equipment must tie into, or is a new system in the contractor’s scope?

What response time is required? Is the facility open to recommendations that improve safety and compliance?

23. Must a single mixer process both the water -based (polyvinyl alcohol) and the acetone-based (nitrocellulose) formulations, or may they run on separate equipment?

24. I noticed it has been extended a few times and wanted to see if I could use it as an opportunity to learn. When things such as these are extended, is it because the solutions are not meeting the intent of the CSO and the gov needs to extend to continue to find the best solution, or is it tied to things such as funding for these projects?

Answers:

1. See attachment 0007 and 0008. The roof varies approximately 15' to 21'.

2. See 3.10 to 3.13 in revised statement of objectives, Attachment 0001 Fluidized Bed

Mixer Facility Problem Statement Rev3. See Attachment 0007 and 0008.

3. The 30% improvement is throughout is no longer a requirement. This is reflected in

Attachment 0001.

4. See 3.1.6 in the revised Attachment 0001. The mixer needs to be able to change these setpoints and should be treated as average settings.

5. The Government is looking for suggestions and options, please provide them along with your solutions. This would be part of creating this mix facility.

6. It currently goes through a sifter.

7. See Attachment 0009 32-620ME-52 Glatt transportainer.

8. See 3.1.6.3 in revised Attachment 0001.

9. Yes, there is de-clumping involved. We don’t want to discard oversized materials.

See 3.2 in revised statement of objectives.

10. There Is a separate hepa filter bank before the air is exhausted into the atmosphere.

A dust separator installed before the hepa filters would help with filter life.

11. Class II Div 1 Group F&G in areas. See drawing E-100 in Attachment 0007 and 0008.

There is no Class 1 Div 1.

12. That is not needed. We changed to a minimum bowl size.

13. Rev 3 is provided along with this amendment, please see the attachments in SAM.

14. Class II Dic 1 Group F&G in areas. See drawing E-100 in Attachment 0007 and 0008.

15. There is no acetone.

16. Open cycle, the only vapor should be water.

17. We are looking at all reasonable options. This is a remodeled empty facility.

18. The Government is requesting the highest throughout as possible but the contractor is responsible for providing options.

19. The Amendment, Attachment 0005, has been updated to show 240 days.

20. No, DoD 4145.26 is for contractors. See 3.14 in revised statement of objective, Attachment 0001 Fluidized Bed Mixer Facility Problem Statement Rev3.

21. The 30% improvement in throughput is no longer a requirement. This is part of the statement of objectives in newest revision, Attachment 0001 Fluidized Bed Mixer Facility Problem Statement Rev3.

22. Yes, a high speed fire detection and suppression system will be in the scope. See

3.8 in revised statement of objectives for governing standards.

23. We only use water- based polyvinyl alcohol formulation.

24. There are multiple reasons as to why we will extend a solicitation, such as needing to answer questions, provide new documents or drawings.