Attachment 0001 Fluidized Bed Mixer Facility Statement of Objectives_Rev 3.pdf

PDF 202 KB Posted

Attached to
Automated Fluidized Bed Mixer Facility Modernization for end use at Pine Bluff Arsenal – CSO
Solicitation number
W519TC26ACSO
Issued by

About this file

This is a Statement of Objectives (CSO) issued by the Department of War for Pine Bluff Arsenal to acquire an automated, high-precision mixing, granulation, and drying system for modernizing colored smoke energetics production. The solicitation is issued under 10 U.S.C. § 4022 and DFARS Subpart 212.70, allowing acquisition of innovative commercial items outside traditional FAR-based procedures, with awards executed as Firm-Fixed-Price (FFP) contracts under FAR Part 12.

The required system must include at least two fluidized bed mixer granulators (FBGs) with a minimum 1,100-liter mixing volume each, an optional third unit if budget allows, and achieve a maximum re-blend rate of 4%. Core technical requirements include sub-millimeter granulation consistency, integrated material de-clumping and weighing systems, automated transfer of finished mix into 23.6 cubic-foot vessels, explosion relief venting, and modern safety sensors with fail-safe shutdown protocols. The intake air conditioning system must reduce relative humidity to the lowest reasonably achievable level using mechanical refrigeration (without desiccants) and accommodate extreme ambient conditions of 105°F with 90% humidity. The system must achieve 95% operational availability, 95% batch-to-batch repeatability, ±1.5% weighing accuracy, and include a high-speed fire suppression system with 500-millisecond response time. All product-contact surfaces must resist corrosion fatigue from processed materials including dyes, potassium chlorate, sugar, sulfur, sodium bicarbonate, magnesium carbonate, polyvinyl alcohol, and stearic acid. The solicitation follows a three-phase competitive process: Phase 1 requires a 5-page paper or 15-slide presentation with technical approach and pricing model; Phase 2 (by invitation) consists of a 30-minute presentation; Phase 3 (by invitation) requires full Statement of Work, FFP pricing, detailed engineering specifications, and logistics plan. Submissions must be emailed to Ashley Testrake (ashley.e.testrake.civ@army.mil) or Michelle Pleasant (michelle.m.pleasant.civ@army.mil) in PDF, Word, or PowerPoint format with maximum 10MB file size. All submissions must be unclassified and scanned for malicious code.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Objectives

10 November 2026

1. Authority: This CSO is issued under 10 U.S.C. § 4022 and DFARS Subpart 212.70, allowing the Department of War (DoW) to acquire innovative commercial items, technologies, or services through competitive procedures outside traditional FAR-based solicitations. All solutions will be treated as commercial items under FAR Part 12. Award may be executed as a Firm- Fixed-Price (FFP) contract(s).

2. The "Area of Interest" (AOI) / Problem Statement: The Pine Bluff Arsenal (PBA) seeks an automated, high-precision mixing, granulation, and drying system with integrated material de-clumping, weighing, and transferring solutions to modernize the production of colored smoke energetics. Current legacy systems are 25+ years old, suffer from structural fatigue, utilize obsolete PLC controls, and rely heavily on manual material handling. The desired modernized solution must maximize throughput, minimize the re-blend rate, ensure sub-millimeter granulation consistency, and integrate modern safety sensors to mitigate fire and explosion risks during the processing of pyrotechnic mixes. Additional goals are to minimize the number of operators and required maintenance.

3. Solution Parameters.

3.1. High-Precision Mixing, Granulation, and Drying System:

3.1.1. Must utilize fluidized bed mixer granulator (FBG) technology.

3.1.2. Minimum mixing volume of 1,100 liters for each FBG.

3.1.3. Procurement baseline requires at least two (2) FBGs, with an option to integrate a third (3rd) FBG if budget allows.

3.1.4. The FBG must have a minimum re-blend rate of 4%. The re-blend rate (R) shall be calculated as follows:

𝑅 ൌ ൬

𝑁ோ 𝑁் ൰ ൈ 100

Where:

𝑅 = Re-blend rate (%)

𝑁ோ= Number of re-blends in the campaign 𝑁்= Total number of batches in the campaign

3.1.5. Explosion Relief Venting: FBGs must have an explosion relief vent pointing upward and rated for an overpressure, in order to minimize the effect of a fire.

3.1.6. Intake Air Conditioning & Dehumidification (Project Scope):

3.1.6.1. FBG systems must operate on an open cycle, pulling intake air from the outside.

3.1.6.2. Full processing and conditioning of the outside intake air is part of the project scope. Steam is available for heating the intake air, but any cooling or humidity reduction equipment must be supplied as part of the project design.

3.1.6.3. The intake air treatment system must reduce relative humidity (RH) to the lowest level reasonably achievable using mechanical refrigeration without the use of desiccant systems.

3.1.6.4. The system design must fully accommodate extreme

summer outdoor ambient conditions of 105°F and 90% relative humidity.

3.1.7. Materials of Construction: All parts of the FBG system that come into contact with the mix (product-contact surfaces) shall be fabricated from materials that resist corrosion fatigue from the materials in the mix.

3.2. Material De-Clumping, Weighing, and Transferring:

3.2.1. Incoming Material & Container Handling: Determining, standardizing, and accommodating the handling and unloading of these incoming containers is part of the contractor's system design scope.

3.2.2. Outgoing Finished Mix Transfer: The outgoing completed mix must be cleanly discharged and poured into a designated 23.6 cu ft transportation vessel (refer to attachment C)

3.2.3. Material handling and processing shall be automated to reduce manual interventions.

3.2.4. Systems for all materials must minimize particulates released into the surrounding air to control combustible dust hazards.

3.2.5. Sugar and potassium chlorate are both hygroscopic; material handling systems must minimize clumping and weight gain caused by atmospheric humidity. These materials must go through active de-clumping and particle size reduction. The current process uses a sifter, but a sifter is not required as long as the particle size for the sugar is in accordance with A-A-20135, Type 1 style C and the Potassium chlorate is in accordance with MIL-DTL-150, Grade B, Class 7.

3.3. Environmental Conditions (Indoor and Outdoor):

3.3.1. Outdoor Ambient Conditions (Pine Bluff, AR):

3.3.1.1. Extreme Summer: Ambient temperatures reaching up to

105°F, average ~72% relative humidity (RH), and peak relative humidity up to 90%–95%.

3.3.1.2. Extreme Winter: Ambient temperatures dropping to 10°F (with historical extreme cold snaps reaching 0°F to 5°F), average winter relative humidity between 75% and 85%, and potential freezing precipitation.

3.3.1.3. Operability Requirement: All equipment, subsystems, and/or outdoor intake infrastructure must operate reliably across these extreme winter and summer outdoor conditions.

3.3.2. Indoor Facility Operating Conditions:

3.3.2.1. Conditioned Space Envelope: The indoor facility operating environment is maintained within an operating range of 60°F to 80°F (nominally 72°F +/-20°F) and 20% to 80% RH.

3.3.2.2. Operability Requirement: All indoor machinery, instrumentation, sensors, and electrical/control enclosures must operate continuously and reliably within this 60°F–80°F and 20%–80% RH indoor ambient envelope.

3.4. Process Flow & Architecture: The Process Flow Diagram can be seen in attachment B.

3.5. Reliability: System must achieve an operational availability of at least 95%.

3.6. Repeatability: System must deliver a minimum batch-to-batch repeatability of 95%.

3.7. Accuracy: System must maintain raw material weighing and dosing accuracy within ±1.5%.

3.8. Safety & Fire Suppression:

3.8.1. Automated "fail-safe" shutdown and venting protocols triggered by anomalous temperature or pressure spikes must be built into closed systems with pyrotechnic mixes in them.

3.8.2. All equipment must de-energize if doors are opened to cubicles.

3.8.3. Building Fire Protection Context: An existing building sprinkler system is currently installed and depicted in the facility drawings (Attachment A).

3.8.4. High-Speed Fire Suppression System: A dedicated High-Speed Fire Detection and Suppression System must be provided and must be tied directly into the existing facility fire protection system. This high-speed system must achieve a total response time of 500ms or faster, measured from initial hazard to water exiting the nozzles.

3.9. Facility Integration, Utilities & Hazardous Classified Locations: Must fit within the existing facility envelope and interface cleanly with current facility power, utility drops, and environmental controls without requiring a complete building overhaul. Building floor plans, electrical schematics, existing sprinkler layout, and plan ed Class II, Division 1, Groups F & G hazardous areas are detailed in Attachment A.

3.10. Air Conditioning and Humidity Control: There is no excess facility refrigeration capability available. Any additional cooling, refrigeration, chilled water, or active humidity reduction equipment required for process conditioning must be supplied as part of the contractor's project scope and equipment design.

3.11. Steam Utility: Steam is provided by an on-site 150 hp firetube boiler rated at 5000 lb/hr, with a second redundant boiler available.

3.12. Compressed Air Utility: Compressed air is supplied by two (2) Sullair 100 hp air compressors, each rated at 457 CFM @ 125 psi.

3.13. Electrical Utility: See Electrical drawings

3.14. Governing Safety, Siting & Combustible Dust Standards: All explosive safety siting, combustible dust mitigation, and equipment installation must comply with the following governing standards:

3.14.1. DESR 6055-09: Defense Explosives Safety Regulation, DoD Explosives Safety Standards (latest version dated November 25, 2025).

3.14.2. AR 385-10: Army Regulation, The Army Safety and Occupational Health Program (latest version dated 24 July 2023).

3.14.3. DA PAM 385-64: Department of the Army Pamphlet, Ammunition and Explosives Safety Standards (latest version dated 24 July 2023).

3.15. Operational Sustainment & Staffing Goals: System design must satisfy the additional operational goals of minimizing the number of direct operators and minimizing routine and preventative maintenance requirements over its operational lifecycle.

3.16. Chemicals to be weighed and mixed:

3.16.1. Dyes and Obscurant Materials:

3.16.1.1. Dye, Red III: MIL-DTL-3284

3.16.1.2. Dye, Violet IV: MIL-DTL-3691

3.16.1.3. Dye, Solvent Yellow 33: MIL-DTL-51485

3.16.1.4. Dye, Solvent Green 3: MIL-DTL-3277

3.16.1.5. Terephthalic Acid (TA): Drawing/Spec 13-19-824

3.16.1.6. Pentaerythritol (PE): Drawing/Spec 36-1-317

3.16.2. Oxidizers:

3.16.2.1. Potassium Chlorate: MIL-P-150 (Grade B / Grade B, Class 7) or MIL-DTL-150 (Grade B, Class 7)

3.16.3. Fuels:

3.16.3.1. Sulf u r , Grade E: MIL-S-487

3 . 16 . 3 . 2 . Sugar: Type 1, Style C (A-A-20135) or Type 1, Class D ( A - A - 2 013 5 )

3.16.4. Coolants and Burn Rate Modifiers:

3.16.4.1. Sodium Bicarbonate, Class 1: A-A-374

3.16.4.2. Magnesium Carbonate: MIL-M-11361 (Grade B), MIL-

DTL-11361

3.16.5. Binders and Processing Aids:

3.16.5.1. Polyvinyl Alcohol: MIL-P-265

3.16.5.2. Stearic Acid: MIL-S-271

4. Project Phases.

Phase Requirement Goal

Phase 1: Solution Brief 5-page paper or 15−slide deck.

High-level technical fit and company viability.

Phase 2: The Pitch 30-minute virtual or in−person presentation.

Deep dive into technical approach and team expertise.

Phase 3: Quote Full Statement of Work (SOW) and Pricing.

Site visit, work out scope, and final negotiations and award of the Prototype.

4.1. Phase 1: Solution Brief: Vendors will submit a concise paper (5 pages or less) or a 15-slide presentation detailing their technical approach and quoted business/acquisition model along with commercial specification sheet. Topics that need to be covered should include description of solution, implementation approach, capability availability, scalability, benefits, challenges, key deliverables / milestones, pricing model / term duration. An emphasis should be put on processing the sugar and potassium chlorate without absorbing humidity. The government will evaluate these submissions to determine if the quoted solution merits further consideration. Only vendors whose Phase 1 submissions are deemed highly viable will be invited to participate in Phase 2.

4.2. Phase 2: The Pitch (By Invitation Only): Upon notification from the Contracting Officer, selected quoter(s) will have fifteen (15) calendar days to prepare an approximate 30-min presentation and answer questions on the quoted solutions.

4.3. Phase 3: Full Quote Request (By Invitation Only): If the Government determines a Phase 2 Solution Summary has merit, the vendor will be formally invited to a site visit to Pine Bluff Arsenal; then to submit a Phase 3 Full Quote. The Phase 3 Quote serves as the baseline for negotiations.

A Phase 3 request will require comprehensive documentation to support a contract award, including but not limited to:

4.3.1. Statement of Work (SOW): The Quoter shall submit SOW

detailing the delivery, installation, compliance mechanisms, maintenance responsibilities (if applicable), and execution of the quoted acquisition model

4.3.2. Pricing Detail: A Firm-Fixed Price (FFP) submission detailing granular pricing for equipment, delivery, installation, and any specific relevant terms.

4.3.3. Detailed Technical Specifications: Engineering drawings proving material standards, dimensions, type, safety features, handling, and specialized options.

4.3.4. Logistics Plan: Lead Times, transportation, site delivery, and setup procedures to Pine Bluff Arsenal. During all phases, the Government reserves the right to negotiate the terms of the scope, Intellectual Property/Data Rights, and final Price prior to executing an award.

5. Selection Criteria.

5.1. Phases 1 and 2 will be evaluated holistically based on the following primary criteria:

5.1.1. Technical Merit and Innovation: The Government will assess the technical viability of the quoted solution through review of the submitted briefs and commercial specification sheets. Evaluators will verify the solution's ability to meet the minimum parameters outlined in Section 3. Furthermore, the Government will evaluate the innovative nature of the quoted commercial acquisition/business model and its effectiveness.

5.1.2. Importance to Agency Programs: The Government will evaluate the potential impact of the solution on PBA’s operational readiness along with the safety and environmental compliance posture.

5.1.3. Financial Feasibility: The Government will review the submitted Rough Order of Magnitude (ROM) to determine if the estimated costs are realistic for the quoted technical approach, and whether sufficient funding is available, or likely to become available, to execute the quoted business model.

5.2. Phase 3 Full Quoted Requests will be evaluated across the following primary criteria:

5.2.1. Technical Approach and Risk: The Government will evaluate the vendor’s draft SOW to assess how well it defines the scope of work, delineates Government versus Contractor responsibilities, and meets the overarching objectives of the problem statement. Additionally, the Government will review the submitted engineering specifications and regulatory compliance matrix to ensure structural integrity and the efficacy of the proposed safety/monitoring mechanisms.

5.2.2. Price Reasonableness: The Government will evaluate the initial Firm-Fixed-Price (FFP) submission. Through evaluation and potential negotiation, the Contracting Officer must determine that the final agreed-upon prices are fair and reasonable pursuant to applicable commercial pricing guidelines. The Government will evaluate the total lifecycle cost and the specific mechanics of ownership transfer as needed. In addition, the cost of running the line (including number of operators, required maintenance, re-blend rate, and production rate) will be considered during evaluation.

5.2.3. Execution, Schedule, and Logistics: The Government will assess the vendor’s proposed execution and logistics plan. This includes evaluating the feasibility of the proposed delivery timeline, site preparation requirements, and adherence to DoW installation security protocols.

5.3. SELECTION AND AWARD. The Government will notify vendors in writing whether their Phase 1 submission was selected to proceed to Phase 2. The same will be done from Phase 2 to 3. The decision to select a Solution Summary for Phase 3, or to award a contract following Phase 3, is at the sole discretion of the Government.

The Government reserves the right to award a contract to the vendor(s) whose proposal offers the greatest overall value and innovative benefit to PBA, price and other factors considered. Additionally, the Government reserves the flexibility to make multiple awards or no award under this

CSO.

6. Submission Information.

6.1. Points of Contact:

6.1.1. Primary: Ashley Testrake, ashley.e.testrake.civ@army.mil.

6.1.2. Secondary: Michelle Pleasant, michelle.m.pleasant.civ@army.mil.

6.2. Phase 1 Solution Summary must be submitted electronically via email to the Primary and Secondary Points of Contact listed in Section 6.

Submissions must be in PDF, Word, or PowerPoint format. The maximum allowable email size is 10MB. Do not submit files via .zip format or third-party cloud links.

6.3. Security Warning: All submissions shall be UNCLASSIFIED and must be pre-scanned for malicious code. Files found to contain viruses or that are corrupted will be deemed non-responsive. Army Contracting Command - Rock Island is not responsible for unreadable files.