W519TC-23-R-2013_Amendment0001_Q-As.pdf
PDF 361 KB Posted
- Attached to
- 7-AXIS MACHINE_Solicitation_Amendment0001_and_0003 Federal contract opportunity
- Solicitation number
- W519TC-23-R-2013_SOLICITATION
About this file
This document provides answers to questions on an amendment to a solicitation for a 7-axis machine. The amendment provides clarification on several requirements for the machine, including that the right angle head must have an index angle of at most 2.5 degrees and capability for automatic tool change and through spindle coolant. A post processor for the machine programming systems at Rock Island Arsenal Joint Manufacturing and Technology Center, which uses NX and ICAM software, will also be required. The amendment further specifies that the contractor shall supply the initial cutting fluid for start-up and machine operation as part of a turnkey contract. Rock Island Arsenal will remove the existing machine.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W519TC-23-R-2013_Amendment0003.pdf | ||
| W519TC-23-R-2013.pdf | ||
| Attachment 0002 - CDRLs.pdf | ||
| Attachment 0001 - RIPD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is outlined in the AMENDMENT 0001 NARRATIVE.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Dec-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W519TC23R2013
X 9B. DATED (SEE ITEM 11)
01-Dec-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Dec-2022
CODE
ARMY CONTRACTING COMMAND - ROCK ISLAND
3055 RODMAN AVE
ROCK ISLAND IL 61299
W519TC 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W519TC23R2013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
AMENDMENT 0001 NARRATIVE
The purpose of Amendment 0001 is to answer industry questions.
Q 1) Request foundation drawings of area for machine to be located.
A 1) Whereas we have a firm idea of where the equipment will go, it can change up until we approach the actual award of a contract. A better action at this time would be for the bidding vendors to identify foundation requirements and RIA-JMTC determine if the area can support such foundation. Our current machines are installed in the likely location for the new machine. I will check with our public works department to see if such a drawing exists however I don’t want to hold up the rest of the answers while I search. This document would also need to be approved for public release which takes time.
Q 2) Right-angle head:
- What is the index angle of degree – 1 degree, 2.5 degree, or infinite?
The right angle head shall have at most, a 2.5 degree index angle. Smaller is acceptable.
- Does the drawbar need to be manual or automatic?
I believe this would need to be automatic. Can I have more clarification on the term?
- Will the right-angle head need the capability of automatic tool change to it?
The right angle head will need the capability of automatic tool change.
- Will the right-angle head require through the spindle coolant capabilities?
The right angle head will need through spindle coolant capabilities.
Q 3) Is a post processor required?
A 3) Yes. A post processor will be required in order for the equipment to be operational with our programming systems at RIA JMTC. JMTC uses NX and ICAM for the current machines.
Q 4) Is RIA removing the existing machine?
A 5) RIA will be responsible for the removal of the existing machine.
Q 5) Will the contractor be required to supply the cutting fluid?
A 6) The contractor shall be required to supply the cutting fluid for the initial start up and run off of the machine.
The contract is for a turn-key system and therefore all fluids, oils, etc. required for proof of machine operation need to be supplied by the contractor.
W519TC23R2013
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
(End of Summary of Changes)