This is a procurement specification for asphalt delivery to a federal military installation. The Hawaii Air National Guard (HIANG) requires procurement and delivery of not-to-exceed (NTE) 120 tons of HI State Mix 4 on August 10, 2026, and NTE 116 tons of HI State Mix 5 on August 11, 2026, to Building 3428 at Joint Base Pearl Harbor-Hickam, Hawaii 96853. Payment will be based on actual tonnage supplied at contractor-provided unit prices per ton.
Delivery specifications require trucks to arrive beginning at 0930 each morning, with asphalt dumped directly into a paver operated by HIANG at a rate of 20 tons every 20 minutes (or one ton per minute). A representative from the 154 Civil Engineer Squadron will coordinate final trucking times and quantities. While quantities may vary between the two mixes, the total combined cost cannot exceed the quoted amount without written approval from the Contracting Officer. Contractors must reference the Hawaii Department of Transportation website for mix design specifications. The map image identifies the haul route from Mamala Ray Drive and the dump location at Building 3428.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1 - Solicitation - W50SLF26QA010.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Asphalt for HIANG – B3428 Pad
Procure and deliver not to exceed (NTE) 120 tons of HI State Mix 4 on 10 Aug 2026 and NTE 116 tons of HI State Mix 5 on 11 Aug 2026. Payment will be based on actual tonnage supplied. Contractor to supply pricing in the table below.
Price per Ton
Tons (aprox) Cost
State 4 120 State 5 116
Deliver to 360 Mamala Bay Drive Building 3428, Joint Base Pearl Habor-Hickam, HI 96853 and dump the asphalt into a paver operated by HIANG. First truck arrival time each morning is 0930. 20 tons of asphalt to be delivered every 20 minutes, or one (1) ton per one (1) minute. A representative from the 154 CES will provide final coordination on trucking times and quantities. Quantities may vary but the total cost between both may not exceed the total quote without written approval from the Contracting Officer.
Reference the HIDOT website for information on the mix designs:
http://hawaiiasphalt.org/guide/modules/04_pavement_types/04_standard_hawaii_mixes.htm http://hawaiiasphalt.org/guide/modules/04_pavement_types/04_standard_hawaii_mixes.htm