This solicitation and related documents provide details for a construction contract opportunity with the Department of the Army National Guard. The project requires repair of the main gate at the 103rd Air Control Squadron in Orange, Connecticut, and includes work such as asphalt paving, guard booth construction, utility relocation, fencing and landscaping. The estimated value is between $500,000 and $1 million. The North American Industry Classification code is 236220 and it is set aside for small businesses with average annual revenue below $39.5 million. The pre-bid document includes responses to contractor questions that clarify scope items such as the need for as-built drawings, security cameras, fiber specifications and the provision of a temporary guard house. Offerors must respond to all contract line items to be considered. The solicitation and amendments will be posted at beta.sam.gov.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SKXJ142001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to incorporate the RFIs and their responses, and incorporate the revisions to draw ings E-001, E-101 and ED-101, all dated 28 MAY 2020.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 8
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50SC220B0001
X 9B. DATED (SEE ITEM 11)
29-Apr-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Jun-2020
CODE
USPFO CT 103 MISSION SUPPORT CONTRACTING
100 NICHOLSON RD
BRADLEY ANGB
EAST GRANBY CT 06026-9309
W50SC2 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W50SC220B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
RFIS AND RESPONSES, 29MAY2020
Connecticut Air National Guard
ACS Orange CT SKXJ142001 Repair Main Gate Bidder Inquiries
Item RFI Response
1 Is a Full‐time QA required for this project?
No. A Full‐time QA person is not required
2 For bidding purposes can contractors assume reclaiming the existing pavement with the existing base and using that comingled mixture under the new paving? Or should contractors assume full depth removal and disposal of the existing paving including the existing base off site.
Existing paving and base material may be used as subbase only. Processed aggregate base material must be brought in from off base for under pavements. Excess material must be removed from the base
3 There appears to be some water company work and sewer work. The notes call for contractors to coordinate with the existing utility company. Can an allowance be established for any utility company fees since they will not provide pricing prior to work being performed?
For the purposes of bidding, GCs should allow for the estimated sewer and water fees to be $30,000.00, and incuded in the CLIN 0001 price. If the fees are less than $30,000.00 then the GC will issue a credit to the Government for CLIN 0001. If the fees are more than $30,000.00 then the GC must notify the Contracting Officer and a contract modification must be issued, if necessary, PRIOR to the GC paying any fees over $30,000.00.
4 Electrical scope talks about coordinating with UI for requirements on new service. UI applications require a CT Electrical License #. Are Connecticut electrical license required? Typically on Federal project it is only required to be licensed in the state where the corporate office is located.
Contractor must comply with UI requirements for electrical license
5 Are local permits required? Permits are not required for site work, but contractor must coordinate with local utility companies
6 There are some pretty extravagant fire alarm specifications for a guard shack.
Shop drawings, HVAC shut down requirements, remote annunciators, etc. Please confirm that these requirements are needed, or provide
Fire Alarm system to be removed from scope of work revised specifications applicable to this project.
7 Please confirm fire alarm scope. Is the fire alarm equipment shown on detail 3 drawing E‐001 new in the new guard shack? It is not shown on the floor plan on drawing E101 detail 2.
Detail #3 from Drawing E‐101 to be removed from scope of work. See revised drawing E‐101
8 Please provide a POC for the company that maintains the CCTV system for the relocated camera.
Michael J. Ollivier Vice President Advantor Systems 12612 Challenger Parkway, Suite 300 Orlando, FL 32826 O: (800) 438‐6415 // (407) 926‐6967 F: (877) 819‐9599 M: (559) 289‐3573 ollivier@advantor.com
9 Please provide a POC for the Notifier rep that maintains the fire alarm system.
There is no need to work with the existing fire alarm system (see revised drawings)
10 Please confirm characteristics of the fiber that needs to be pulled back and relocated to the guard shack. i.e. MM, SM, # of strands.
12 strands of single mode
11 Confirm Bid Bonds are made out to the Issuer USPFO CT 103 Mission Support Contracting. Address: 100 Nicholson Road – Bradley ANGB in East Granby, CT 06026‐9309
Bid Bonds are submitted using a Standard Form 24, which requires only information for the Principal and the Surety
12 Paving: referring to Section 321216‐3 Part 2‐Products; 2.1 the materials classes contradict materials on DWG C‐ 105 Sheet 7 of 17. It appears there are two different mixes being called for.
The DWG shows S.5 & S1; the Specification call for base as Class1 & Class 4 and Class 4 is generally not recommended at 2.” Provide clarification
Follow drawing C‐105 where shows S0.5 & S1.0
13 Is there a suggested manufacturer for the removeable bollards and are they stainless steel?
The removable bollards do not need to be stainless steel and there is not a suggested manufacturer
14 Is there a designated soil / remnants stockpile area designated?
An area will be designated later
15 Fire alarm manufacturer qualification:
Is a Monaco system required?
There is no need to work with the existing fire alarm system (see revised drawings)
16 Cameras – DWG A‐101 indicates cameras on the new guard house. Are the cameras not included in this contract as there is no specification for them?
Security Cameras are provided and installed by the government
17 If cameras are included in the contract, please provide basis of design or approved supplier list. Provide mounting information as well
Security Cameras are provided and installed by the government
18 What is the construction type and dimensions of the existing guard house? Can you provide a photo for demolition purposes?
See attachments. Exhibit 1
19 Is there any issue with mounting the guard booth exhaust fan through the roof as opposed to the wall mount as this will impact level 5 wall?
No, as long as it is protected
20 The AC unit in the guard house has a ballistic protective cover. Is a protective cover required for the exhaust fan?
Yes, it requires protection whether mounted through the wall or through the roof as stated in #19
21 Specification Section 012000‐1, Part 1,
1.1 Scope; B – states to provide a
trailer to be used as a temporary guard house during construction. Please provide the dimensional and interior requirements for this trailer, and approximate location.
The Government will provide the temporary guard house
22 The electrical drawings call for a fiber cable from the existing communications vault to the D‐Marc.
Unable to locate specifications as to what is required; please provide
See response to #10
23 Specification Section 012000 Temp Offices states the contractor to furnish one contractor construction trailer and one Government use trailer. Is a single 40’ double office or similar acceptable or are both trailers required?
A trailer/space office for the government is not required
24 Specification Section 021000 Storage states the contractor is to construct a temporary storage shed. Is a Conex storage container acceptable?
Yes, a Conex storage container is acceptable
25 The drawings show to reuse the existing electrical panel to be installed at the new guard house. The guard house manufacturers include this main panel and pre‐wire it all. Should the manufacturer not include?
A new panel is required
26 Is rigid steel conduit required for all stub ups? Conduit to the guardhouse is mounted on the exterior surface correct?
Yes
27 The plans and specs show a fire alarm system but it is not shown in the building, is one required?
No (see revised drawings)
28 The plans and specs show cameras on the building but give no information on them, are they provided by the GC or the Government?
Security Cameras are provided and installed by the government
29 The plans and specs show gate controllers and key cards, are they provided by the GC or the Government?
The existing gate controllers, wireless panic buttons and card readers may be reused for this project. New conduit, loop detectors and wiring are required
30 Section 033053 – Concrete: DWG C‐ 503; Detail 2: confirm no objection to a Monolithic pour for the concrete slab at the guard house?
No objection
31 DWG E‐001, Detail #3, requires a new antenna. These range in price; provide manufacturer and model number required.
None required (see revised drawings)
32 Section 012000‐11(1.29)(A&B): provide a source / location for temp power to office trailer(s) and temp guard house (if needed).
Temporary power can be pulled from UI Pole #4684. The GC should coordinate with UI for their requirements. An account with a separate meter must be setup and installed for the construction trailer and the GC shall pay the utility bill. The existing service for the current guard shack also feeds the fire protection pump house and cannot be turned off. The GC may relocate the existing meter/service to the pump house and work back from there
33 Is there a need for testing for PCBs, Asbestos & lead at the original guard house?
There is no need for testing
34 Is data required in the guardhouse and if so, provide quantity & type of lines
Three cat 6 Quads are required as shown on E‐101. Lines (cat 6) are not required
35 Is there a basis of design for the CCTV system? If so, provide specifications
Security Cameras are provided and installed by the government
36 Is there a basis of design for the Access Control System? If so, provide specifications
See response to #29
37 Is there a Contractor currently maintaining the fire alarm system? If so, what is their contact information?
There is no need to work with the existing fire alarm system (see revised drawings)
38 Provide specifications for the Fiber Optic Cable for the telephone service
There is no new fiber optic requirements for telephone service
39 Will town of Orange permit fees be waived for this project?
There are no permit fees for the town of Orange
40 There is no specific information provided for the water closet, lavatory and floor clean out. Is this design specific to each guard house manufacturer or are there specification requirements the owner can provide?
These items are specific to the manufacturer
41 Drawing E101, Work note #8 Fiber optic cable – How many strands and what type of fiber cable? Who performs the terminations and what type of fiber patch panel / fiber connections.
See response to #10
42 Drawing E101, Work note #14 – Terminate tele services to demark Backboard. There is no information on
See Drawing E001. The fiber lines to be relocated are the ones to be terminated in the fiber patch panel located inside the cabinet(demarc backboard).
(End of Summary of Changes) any telephone backbone cables on plans and specs. Please advise
43 Are Tele/Data outlets pre‐wired with the guard house? If not what type of cable, patch panel, jacks, etc.
Three cat 6 Quads are required as shown on E‐101. Lines (cat 6) are not required, conduits as needed with pull strings. The following is needed: A Cabinet, a 24 port rack mount network switch, a rack mount UPS and a fiber patch panel. The Network switch needs to have a rack mountable enclosure that supports 24 * 10/100/1000 POE+ Ethernet ports with 4*1G SFP uplink ports and provides up to 390W POE power with up to 30W per port;
Switching Capacity 88 Gbps; RAM 4 G; Flash Memory 2G.
The cabinet needs to be intended for IT equipment (racks, proper venting/airflow, etc.) and able to fit the required items.