QUESTIONS AND ANSWERS

W50S9H-21-Q-0002 – 20ft. Mobile Barrier

Question 1: Is the requirement for two (2) transmitters, one (1) transmitter and one (1) transceiver, or two (2) transmitters and two (2) transceivers?

Answer 1: The requirement is for two (2) transmitters (remotes) and one (1) transceiver (antenna to receive the wireless signal).

Question 2: Is hot-dip galvanization required prior to specified paint finish and if so, shall hot-dip galvanized certification certificates be issued to provide proof of application?

Answer 2: The Government requires that the product be “corrosion resistant”. There is not a requirement for the hot-dip galvanization method, however if that is how your company provides corrosion resistance, please provide proof of application.

Question 3: Will offloading/uploading upon delivery will be performed by the Customer/End User and are there any advance shipping instructions?

Answer 3: The Government will assist with unloading operations and has loading ramps accessible for offloading rolling materials. If required, the Government also has the capability of offloading with a 10,000 lbs. forklift. Items in excess of 10,000 lbs. would require additional offloading capability by the contractor.

Question 4: Are there any advance personnel and personnel vehicle access badging or clearance documents required to be prepared in advance?

Answer 4: No, the Government will provide the awarded contractor with the Entry Access Listing (EAL) to fill out after contract award for personnel and vehicle access.

Question 5: Are both classroom and field training required? What are the training start and completion time periods?

Answer 5: The Government would prefer to have both classroom and field training included in this contract.

Scheduling of training will occur after award of the contract.

Question 6: Will power to the location where the system is to be installed be supplied prior to on-site arrival of manufacturer personnel?

Answer 6: The site where the system is to be installed will have power capabilities.

File details come from the government source that posted it. Updated .