QUESTIONS AND ANSWERS
W50S9H-21-Q-0002 – 20ft. Mobile Barrier
Question 1: Is the requirement for two (2) transmitters, one (1) transmitter and one (1) transceiver, or two (2) transmitters and two (2) transceivers?
Answer 1: The requirement is for two (2) transmitters (remotes) and one (1) transceiver (antenna to receive the wireless signal).
Question 2: Is hot-dip galvanization required prior to specified paint finish and if so, shall hot-dip galvanized certification certificates be issued to provide proof of application?
Answer 2: The Government requires that the product be “corrosion resistant”. There is not a requirement for the hot-dip galvanization method, however if that is how your company provides corrosion resistance, please provide proof of application.
Question 3: Will offloading/uploading upon delivery will be performed by the Customer/End User and are there any advance shipping instructions?
Answer 3: The Government will assist with unloading operations and has loading ramps accessible for offloading rolling materials. If required, the Government also has the capability of offloading with a 10,000 lbs. forklift. Items in excess of 10,000 lbs. would require additional offloading capability by the contractor.
Question 4: Are there any advance personnel and personnel vehicle access badging or clearance documents required to be prepared in advance?
Answer 4: No, the Government will provide the awarded contractor with the Entry Access Listing (EAL) to fill out after contract award for personnel and vehicle access.
Question 5: Are both classroom and field training required? What are the training start and completion time periods?
Answer 5: The Government would prefer to have both classroom and field training included in this contract.
Scheduling of training will occur after award of the contract.
Question 6: Will power to the location where the system is to be installed be supplied prior to on-site arrival of manufacturer personnel?
Answer 6: The site where the system is to be installed will have power capabilities.
Question #7: What type of power is located near the location of the proposed barrier?
Answer 7: Power will be suppled via onsite generator to maximize portability. 110/240 power is available should temporary use turn to enduring operation.
Question #8: What is the distance from the proposed barrier location to the power source?
Answer 8: Power is sub 20’ from proposed barrier location
Question #9: Will the mobile barrier simply be placed onto the existing flat roadway and connect the power or will there need to be more civil work for installation? If you could expand upon the total scope of “installation”, it would be helpful.
Answer 9: Installation will include placing the barrier onto the existing flat roadway. Further civil work will not be required.
Question #10: Can the barrier’s power cables be on top of the surface or will they require excavation to be placed underground?
Answer 10: Should shore power be used in the gate’s operation, power cables may be on top of the surface.
Question #11: How many people will be in attendance for the training?
Answer 11: 4-6 personnel
Question 12: The specification calls for “hitch/tow capable”. Does this mean you would like the barrier trailer to be included in the price for the barrier or just to offer the capability for future mobile use in general?
Answer 12: Please include the price of the barrier trailer as a line item. The requirement is for the barrier to remain portable for rapid deployment.