Grass Install Site Visit QA.docx
DOCX document 25 KB Posted
- Attached to
- Install Grass- **ADDED Q&A from site visit and SCA WD Federal contract opportunity
- Solicitation number
- W50S9D24Q5001
- Issued by
- Department of the Army National Guard
About this file
This document is a set of questions and answers from a site visit for a federal solicitation to install grass at the Washington Air National Guard facility at Fairchild AFB.
The key details are:
The solicitation is for a firm fixed-price contract to install grass seed or sod around Building 375 and the ANG memorial site. The grass must be drought and heat resistant, with a blend of at least 70-80% tall fescue, 10-20% perennial rye, and no more than 10% Kentucky bluegrass. The contractor is responsible for site preparation, seeding/sodding, and maintenance until July 31, 2024 when the grass must be ready for use. The contractor will also be required to remove rocks larger than 0.5 inches and provide 2 inches of topsoil prior to seeding/sodding. The solicitation is a total small business set-aside under NAICS code 561730 with an annual revenue not exceeding $9.5M. Quotes are due by 2pm PT on April 16, 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage Determination 2015-5537 REV 21.pdf | ||
| Grass Layout.pdf | ||
| Install Grass SOW.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Grass Install Questions
1) Topsoil Requirement- Washington State Department of Transportation (WSDOT) Type "A" (Black Dirt). Black Dirt shall consist of a mixture of sand, silt, and decayed plant fiber. The sand content shall not exceed 60% and 1% gravel, the organic content shall not be less than 4%, and the pH shall lie between 5.5 and 7.5.
2) What size rock will be acceptable to leave behind?
¾ inch or greater rocks must be removed.
3) Will the rock need to be removed off base.
Yes, all rock that is collected greater than ¾ inch must be removed off base.