Install Grass SOW.docx
DOCX document 30 KB Posted
- Attached to
- Install Grass- **ADDED Q&A from site visit and SCA WD Federal contract opportunity
- Solicitation number
- W50S9D24Q5001
- Issued by
- Department of the Army National Guard
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to install grass at the Washington Air National Guard facility located at Fairchild Air Force Base in Washington. The government is issuing a Request for Quote (RFQ) under solicitation number W50S9D24Q5001 for a Firm Fixed Price (FFP) contract to plant grass seed or install sod on approximately 3.8 acres.
The key requirements include: the lawn must be ready for use by July 31, 2024; the contractor must use a specific blend of grass seed; the contractor is responsible for soil amendments, weed control, and weekly site inspections; and the contractor may also be required to install Kentucky bluegrass sod. The contract period of performance is 90 days. Quotes are due by 2:00 PM Pacific Time on April 16, 2024 and will be evaluated on best value based on price and delivery date. This is a total small business set-aside acquisition under NAICS code 561730.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage Determination 2015-5537 REV 21.pdf | ||
| Grass Install Site Visit QA.docx | DOCX document | |
| Grass Layout.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Washington Air National Guard 1415 W El Paso Ave Fairchild AFB, Washington
STATEMENT OF WORK
FOR
Install Grass, B375 GJKZ 24-2896
1 GENERAL REQUIREMENTS
1.1 PURPOSE
The purpose of this project is to plant grass seed around B375 and ANG memorial site or install sod.
1.2 SITE VISIT
Interested bidders may attend a site visit prior to the bid due date. Interested offerors are encouraged to include any subject matter experts or sub-contractors required for this work. The site visit will be scheduled and advertised by the Contracting Officer (CO).
1.3 RESPONSE
Submit cost proposals to the CO. All responses must be in writing, using the request for proposal (RFP) form specified in the solicitation. All responses must be received by the date and time specified in the solicitation.
1.4 CODES AND REGULATIONS
A. All work shall be accomplished in accordance with the following regulatory codes:
1. UFC 3-201-02 Landscape Architecture
1.5 WORKMANSHIP
All work shall be accomplished in a professional manner by experienced and qualified tradespersons to the complete satisfaction of the COR.
1.6 APPROVALS AND CHANGES
A. Any changes to the terms and conditions of the contract will be issued in writing by the contracting officer prior to commencement of work or incurring costs.
B. No deviation from approved plans, specifications and general notes will be permitted without written approval from the COR. Requests for deviations or substitutions must be submitted on a substitution request form available from the COR.
C. Any contractor driven change request shall be submitted through a request for information (RFI).
1.7 WARRANTIES
All work completed under this contract shall be guaranteed by the contractor against defects in materials or workmanship for a period of one year from date of final project acceptance.
1.8 SUBMITTALS
All submittals listed below shall be submitted after award at least ten working days prior to use on site, or as noted below.
A. INITIAL SUBMITTALS
1. Submit the following items no later than the Preconstruction Meeting
a. AF 3064 (or equivalent) – Project Schedule
b. AF 3065 – Schedule of Values
2. Submit the following items at least ten working days prior to onsite work
a. Safety Plan
b. Quality Control Plan
3. The Government shall have up to five working days to review submittals
B. PRODUCT SUBMITTALS
1. Submit DD Form 1354, Transfer and Acceptance of DoD Real Property
2. The Government shall have up to five working days to review submittals.
C. HAZARDOUS MATERIALS
1. Hazardous materials must be approved prior to start of work.
2. Submit one copy of the manufacturer’s Safety Data Sheets (SDS) for all hazardous materials used during the course of the project along with the following additional information:
a. Number of components in material if it is a kit
b. Container type
c. Unit of packaging (oz, gal, lb, qt, ea, etc.)
d. Package (can, drum, bottle, cylinder, etc.)
1.9 OPERATION AND MAINTENANCE MANUALS
N/A
1.10 MAINTENANCE PERSONNEL TRAINING
N/A
1.11 COORDINATION
A. The contractor shall coordinate all work with the COR.
B. Contact the COR five (5) working days in advance of mobilization on site and provide proper documentation to allow for processing of base access paperwork. This requirement includes deliveries of any kind.
C. Same day request and access is not always possible.
1.12 TEMPORARY FACILITIES
The contractor shall be provided reasonable access to existing electricity, water, and sewer utilities required to perform the work. Any work trailers or offices must be approved by the COR. If additional new temporary utility connections are required, the contractor shall pay for connections and service.
1.13 CONTRACTOR MATERIAL STORAGE
The contractor shall submit a request in writing for material storage or laydown areas not immediately inside the area of work. Exterior laydown requests must include a site plan schematic showing area in reference to existing buildings.
1.14 DAMAGE
The Contractor shall be responsible for any damage caused to any existing work areas during the entire performance of this project. The Contractor shall be responsible to rectify or replace any equipment damaged without additional expense to the Government.
1.15 QUALITY CONTROL
A. A pre-construction conference will be held by the CO at a time to the commencement of work and shall be attended by the COR, the end user, and the Contractor.
B. The purpose of this conference is to completely review the job and the specifications to confirm mutual understanding of the job content and performance.
C. The Contractor is responsible for quality control. Inspections by the COR and/or government quality assurance personnel do not alleviate the contractor from their responsibility. The Contractor shall be responsible for all applicable material testing and special inspection activities necessary to ensure the project is constructed according to code.
1.16 SCHEDULES
A. The Contractor shall begin work within 10 calendar days after the issuance of the Notice to Proceed.
B. No on-site work shall start until the Contractor has an Approved Project Schedule.
C. The period of performance shall be 90 days for this contract.
D. The COR will coordinate Contractor work schedules upon award.
E. The COR will notify the Contractor if a job site is located in a secure area.
1. The Contractor shall provide written notice to the COR at least three working days prior to working in secure areas.
2. The Contractor shall provide personnel that meet the requirements to work within the secure areas without escorts.
3. The COR will provide a letter to the Contractor granting permission for work within secure areas.
a. The notice shall include working hours, location of work, and number of workers.
b. The Contractor shall keep this letter on the jobsite at all times.
1.17 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
A. Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
B. For Contractors that do not require CAC but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31- 101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
C. All commercial, contractor, and sub-contractor’s vehicles are subject to random inspections each time they enter the base.
D. If badges will be issued, they will be issued by the 92d Security Forces Squadron (SFS) to the contractor through the 141 CES COR. Badges shall be issued, tracked, and collected in accordance with instructions from Security Forces.
1. The following are the requirements and procedures for the contractor:
a. Contractors working in Controlled or Restricted areas or any areas on the flightline must be issued a specific contractor identification badge or be escorted. (Parts of this project are located on the flightline)
1.18 HOURS OF WORK
A. Normal hours of operation for construction are 6:00 am through 4:30 pm Tuesday through Friday, excluding any federally recognized holidays.
B. Requests to work outside the normal work hours must be made to the COR at least three working days in advance. The COR may reject requests at the convenience of the government. Failure to make requests at least three working days in advance may result in being denied base access or being required to leave the base.
1.19 CUTTING AND PATCHING
A. Cutting and patching includes cutting into existing structures to provide for the performance of the work and subsequent fitting and patching as required to restore surfaces disturbed, damaged or otherwise altered to their original or specified condition.
B. Visual Requirements: Do not cut and patch work in a manner that would result in substantial visual evidence of cut and patch work. Remove and replace work judged by the COR to be cut and patched in a visually unsatisfactory manner.
C. If possible, retain the original installer or fabricator, or another recognized experienced and specialized firm to cut and patch.
D. Use materials for cutting and patching that are identical to existing materials. If identical materials are not available, or cannot be used, use materials that match existing adjacent surfaces to the fullest extent possible with regard to visual effect. Use materials for cutting and patching that will result in equal-or-better performance characteristics.
E. Restore surfaces of patched areas to match adjacent finishes. Where necessary, extend finish restoration into retained adjoining work in a manner, which will eliminate of patching and refinishing.
1.20 CLEAN-UP
A. The contractor shall clean up and remove from the site all rubbish. The contractor shall leave the premises in a clean, orderly and safe condition, acceptable to the COR.
B. Protect existing building or structures including exterior landscaping and interior contents from damage, dirt and dust during construction related activities.
1.21 ENVIRONMENTAL COMPLIANCE
A. Spill Notification: The contractor shall notify the COR upon spilling any quantity of hazardous materials/waste. Spill Containment Control and Countermeasures shall be provided by the contractor in accordance with 20 CFR 112.
B. Hazardous Materials Storage: Ensure all hazardous materials stored outdoors are placed in secondary containment in accordance with 40 CFR.
C. Hazardous Waste: All hazardous waste generated from the use of hazardous materials shall be disposed offsite. The contractor shall make the COR aware of all hazardous waste through the Hazmat disclosure process and provide all required documentation.
1.22 FACILITY SERVICE OUTAGES
If the project requires any facility utility outages, the contractor shall provide a written request at least 72 hours before planned outage period and receive approval from 141st CES COR before disconnection.
1.23 PARKING
Adequate on-site parking for contractor vehicles will be designated by the Government.
2 CONTRACTING MANPOWER REPORTING APPLICATION (CMRA)
Contracting Manpower Reporting: The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Air Force collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at http://www.ecmra.mil/.
3 DESCRIPTION OF WORK
The contractor shall verify all dimensions, elevations, and site conditions prior to starting construction. The area is approximately 3.8 acres.
Base Bid
3.1 The lawn must be ready for use by July 31, 2024.
3.2 The finished lawn to be drought and heat resistant.
3.3 Only an established blend of not less than 70-80% tall fescue, 10-20% perennial rye and not more than 10% Kentucky Blue Grass will be considered.
3.4 The contractor shall use equipment designed specifically for sandy loam soil to seed at a depth of 0.25 to 0.50 inches.
3.5 The contractor shall use a sod quality seed that has 0% weed seed content and provide percentages and purity labels. Jonathan Green’s Black Beauty Ultra or equal shall be used.
3.6 Seeding shall use a rate of 200-300 pounds per acre (dry weight).
3.7 No filler, straw, or sticker shall be used.
3.8 Contractor will provide irrigation requirements to optimize grass blend germination and health.
3.9 Contractor is responsible for any and soil amendments and fertilizer until 31 July 2024.
3.10 Contractor shall be responsible for a post and pre-emergent weed control application prior to seeding and not later than 16 July 2024.
3.11 Contractor shall make weekly site inspections over a two-month period prior to July 31, 2024, to ensure optimal plant growth and quality.
3.12 Contractor will provide mowing requirements to optimize grass health.
3.13 The grass shall have a park like appearance, dense, dark green lawn without bare spots exceeding one square foot at any place. Contractor is responsible for filling in any bare spots exceeding 0.5 SF at 30 days after seeding.
3.14 Contractor will use a landscape rake to remove rocks prior to laying topsoil.
3.15 Contractor will lay 2 inches of topsoil prior to seeding.
Option 1
3.16 The contractor will procure Kentucky bluegrass sod from the same farm with one cut if possible.
3.17 Sod must be delivered and installed by the contractor within 72 hours of the cut.
3.18 Irrigation will already be installed, at the time of the sod project.
3.19 Irrigation heads and valve boxes will be protruding above ground. Contractor to cut sod around heads and valve boxes.
3.20 Contractor is responsible for any damage to the irrigation during the topsoil (if applicable) and sod install.
3.21 Contractor will be responsible to repair any dying or damaged sod for up to 30 days after install provided all the watering requirements are met.
3.22 Sod must lay on at least two inches of topsoil that is provided and graded by the contractor.
3.23 Sod is cut to fit the design of the area.
3.24 ATTACHMENTS
A. Grass Layout
- END OF STATEMENT -