W50S9B-20-Q-0006, Office Space Renovation Post Site Visit Questions, Unanswered
2 July 2020
The following are the questions received in connection with the 1 July 2020 site visit. Official answers to these questions are anticipated by 10 July 2020.
Concerning Statement of Work (SOW) 2.3, Demolition and Remaining Structure
Q1. Does the government want to save any of the items demolished/removed for future use?
Q2. The Light bar in the dining room to be removed will leave an area with no light at the entrance to the dining hall, please advise?
Q3. The drawings provided look like the drawings are incomplete looks like info is missing on top and bottom of every page, please advise?
Concerning SOW 2.4, Structural
Q4. Does the government want to have insulation in all new walls?
Q5. Are wooden doors required or will metal painted doors be acceptable?
Q6. Current walls in dining hall are wallpaper. Will the new walls require matching wallpaper or is paint acceptable?
Q7. Will raised floor area be carpeted or VCT tile?
Q8. Please advise of channels in the raised floor for comm, electrical?
Q9. The office area entering the raise floor at the door is not code compliant can the room be redesigned to allow different door access point?
Concerning SOW 2.5, Electrical
Q10. How many lighting zones are required to be dimmed?
Q11. How should lights be switched?
Q12. As per code, floor outlets will be required in place of outlets currently used. How would the government like to proceed?
Q13. Will combined outlets and ethernet floor boxes be acceptable?
Q14. Will HDMI cables be provided by government or contractor supplied?
Q15. Will HDMI cables be surfaced mount on wall and what will be location with heights?
Concerning SOW 2.8, HVAC
Q16. Will the government be able to provide the HVAC drawings for current system? If so, please do.
Q17. Concerning possible need for additional intakes: will additional supply and returns be needed in the new offices?
Concerning SOW 6.1, Drawings
Q18. The Conceptual Drawing are missing parts of the pages top and bottom please provide a complete set.
Concerning Project Over All:
Q19. Will a lay down area be provided for dumpster/material storage?
Q20. Will office equipment be removed prior to start of project?
---------------------------------- End ----------------------------------