This document appears to be a set of bid questions and government responses related to the solicitation for the PSXE242025 Repair TEC Dorm Roofs contract opportunity.
The key details are:
- The solicitation is to repair the roofs on Buildings 406, 407, and 410 at the PSXE242025 site. The scope includes removing existing roof materials down to the metal decking and installing new roofing with a minimum R-38 batt insulation.
- The government confirmed the work is only required for the areas marked "B" on the site plan, and that the existing stair canopy roofs for Buildings 406 and 407 should also be replaced.
- The solicitation number is W50S98-24-B-0005 and it is being issued by the Department of the Army Tennessee Army National Guard.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
8/15/2024 Bid Inquiry: Repair Building 410 Roof, PSXE242016
1. Sheet AS1.1 Site Plan Keynotes references work to be done at buildings 406 & 407. There is no work shown for these buildings. Can you confirm scope of work and provide drawings for these buildings?
Only those areas marked B on Sheet AS1.1 shall be replaced per “Site Plan Keynotes” The existing stair canopy roofs shall be removed and replaced to match the existing 406 & 407 stair canopy roofs.
1. Sheet S2.1 notes to remove 8lbs per sq.ft of the existing roof. Sheet AD1.1 notes call for the existing roof to be removed in it’s entirety. Can the government confirm which is correct?
All existing roof materials should be removed down to metal decking.
1. Sheet A1.4 details show insulation on top of the metal decking. There will be no insulation between the top floor and the attic space. The government will be heating the attic space in the winter months. Can the government confirm this is the intent?
If all roof insulation is removed per question #2 above, provide minimum R-38 batt insulation over vapor barrier on existing metal deck.