Industry Questions and Answers (PDF).pdf
PDF 12 KB Posted
- Attached to
- Bldg. 19 Sanitary Lift Station
- Solicitation number
- W50S9320B5005
- Issued by
-
Department of the Army National Guard
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notice ID: W50S9320B5005 Project #: Bldg. 19 Sanitary Lift Station
List of questions made by the industry.
1. Is there a standard Bid Form?
No. There’s not.
2. Can you provide the as built plans for the lift station, sanitary system and electrical system pertaining to the above mentioned lift station?
There are no as built plans available. Existing utilities PDF attached. Electrical connection and controls inside B19 Mechanical room as seen in site visit
3. Is there a technical drawing of the specified manhole and check valve pit covers?
No. Shop drawing need to be submitted for approval by contracting officer representative (COR).
4. What are the dimensions of the manhole? (Diameter & Depth)
5 feet by 8 feet
5. Do you now the manufacturer & model of the existing pumps?
Manufacturer and model not available
6. Do we have to include Submittals for pumps, controls and coating as part of our proposal?
Yes. Submittals area required for COR/CES approval
7. Since COVID-19 epidemic still uncertain, will the construction timeline be extended?
Considering that material delivery deadlines have change, being that medical equipment and materials have priority, business have limited schedules and local government agencies are closed.
An epidemic is considered an act of nature and therefore could be considered an excusable delay.
However, contractor needs to show the actual delay and effort in acquiring materials.
File details come from the government source that posted it. Updated .