Bid Comment Compilation- Through RFI 87.pdf

PDF 967 KB Posted

Attached to
193rd SOW Entry Control Facility
Solicitation number
W50S92-25-B-A004
Issued by

About this file

This document is a Request for Information (RFI) for a federal construction project at a military base, containing 87 detailed questions and responses from the government covering various technical and contractual aspects of the project. The project involves constructing a new facility with electrical, security, lighting, utility, and infrastructure components, including a guard booth, vehicle barriers, fencing, and site improvements.

Key details include a bid deadline of September 26th, 2025 at 10:00 AM, with RFIs accepted until September 3rd, 2025 at 12:00 PM. The project requires hand-carried bids using SF 1442 form and a bid guarantee. Significant technical requirements involve electrical work, underground stream considerations, utility installations, stormwater systems, and specialized security infrastructure like passive and active vehicle barriers. The government will provide some site-specific materials like boring logs and has addressed numerous technical clarifications about equipment specifications, grounding requirements, aggregate materials, and installation details. Contractors must coordinate with multiple vendors and meet specific technical standards for electrical, structural, and security systems.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

1. It is noted that BLDG 80 will be occupied during construction, but will the government be using the Garage Doors located along the North East side of BLDG 80 during the construction? If yes, what kind of assistance will be needed from the contractor?

The Government will work with the Contractor for the usage of Building 80 North East Garage Doors during construction.

2. During the pre-bid walk through the underground stream was discussed in detail. The discussions were all referencing that its location is approximate, but the location has not been verified. That leaves the bidders with a question, where is it? How deep is it? Questions lead to a guess and a guess is an unknown to the Government.

And with the Government making the statement no change order will be processed for the stream if it’s in the way of our work that also opens up the project to interpretation, is the Government going to raise the elevation of the site if the aqueduct is at an elevation that is too high for new finished grades or building footings? Who is paying for that?

The project was designed with the intent of avoiding impacts to the underground stream. No grade or facility foundation deviations from the design are expected.

3. Would the government consider having GPRS or any other ground penetrating radar contractor, come to the site pre-bid and locate the exact route of the stream and the depth of the aqueduct that it runs through and provide those findings to all bidders so that we are all bidding on fact rather than assumptions.

The Government has concluded all exploratory e orts in regards to the underground stream, if the contractor feels they need to conduct this type of work then it is the responsibility of the contractor.

4. Drawing E-101 Note #6 states that the EC is responsible to contact and hire First Energy to relocate and install utility poles in the median area. Typically, this is something that would be handled by the utility customer and the EC would be responsible for coordination onsite only. Please clarify.

The Electrical Contractor will coordinate with First Energy

5. Is EC responsible to carry the security system by Advantor? If so, please provide contact information.

The Electrical Contractor is responsible for coordinating with Advantor to allow for Advantor to accomplish work associated with their system. Advantor Contact: Alexander M. Garner (garner@advantor.com, 689-323-0545)

6. Is EC responsible for data outlets shown on E-201 or will this work be performed by Advantor?

The Electrical Contractor is responsible for all work detailed in the drawings and specifications as well as coordinating with Advantor to allow for Advantor to accomplish work associated with their system. Advantor will be responsible for cabling and equipment and Electrical Contractor is responsible for pathways and boxes

7. E-601 single line diagram shows a 20A 120v power circuit for the site cameras. This conduit is not shown on the site power plan. Will all site cameras shown on Drawing E-103 require a sperate 1” conduit for 120v power?

The Contractor shall provide data conduit and power to meet Advantor’s needs established through coordination with Advantor. The conduit shall be at a minimum, ½” conduit per the Specifications.

8. Drawing E-201 shows an annunciator UPS on the north wall. Will this be provided by the security vendor?

The Contractor shall coordinate with Advantor to ensure that they provide the correct data of the equipment they will be providing where the contractor will provide raceways and boxes.

9. Who is responsible for all communication pathways for the tra ic control systems? There are no conduit sizes shown on drawing E-103. If EC is responsible, please provide conduit size requirements.

The Electrical Contractor is responsible and shall coordinate with applicable subcontractors to determine the specific conduit sizes based on the project drawings and specifications.

10. There are no conduit sizes shown on drawing E-103 for cameras. Please provide conduit size requirements.

The Contractor shall coordinate with applicable subcontractors and/or Advantor, and determine the specific conduit sizes based on the project specifications (i.e. Specification Section 26 20 00 Paragraph 3.1.4.12) and drawings.

11. Drawing E-601 panel schedules for Panels PP-101A&B show them as NEMA 1 enclosure. These panels are to be mounted on the exterior of the building; will these panels be required to have a NEMA 3R rating?

The Contractor shall coordinate with applicable subcontractors and determine the proper hardware based on the project specifications (i.e. Specification Section 26 20 00 Paragraph 2.11.1.d) and drawings. Outdoor Cabinets shall be NEMA 4X.

12. CLIN B001 Pre Fab Guard Booth – Drawing E601 one line shows that the 60A panel board for this building will be provided with the building. Will all other electrical devices (lighting, HVAC, outlets, data) be pre-installed in building or will these items need to be field installed?

The Contractor shall decide either the manufacturer will have said items installed or if the contractor will install.

13. Drawing E-505 detail #1 shows the exterior pole mounted cameras. Will these poles be provided by the security vendor? If EC is responsible, please provide specification for poles.

The Electrical Contractor is responsible for the completion of all work outlined in the project specifications and drawings and shall provide all necessary raceways and boxes to include supports.

14. Who is responsible to provide antenna pole shown on E-301 detail #4?

The Electrical Contractor is responsible for the completion of all work outlined in the project specifications and drawings and shall provide all necessary raceways and boxes to include supports.

15. Who is responsible for the tube steel support structure shown on E504 detail #1 for the overwatch equipment rack?

The Electrical Contractor is responsible for the completion of all work outlined in the project specifications and drawings and shall provide all necessary raceways and boxes to include supports.

16. Drawing E-601 one line note #7 shows the feed to the generator plug as (2) #6 and (1) #6 GND. The generator plug model listed on E-506 is for a 200A plug. Should this feed match the incoming feed to the MTS (4-#3/0 and (1)-#6

GND)?

The conduit tag from the MTS to the generator plug should be tagged as 2 and not 7.

17. E-601 one-line shows a note 11 to the water heater IWH-1 which is 2#2, 1#8G. The breaker in panel PP-101B for the water heater is only a 20amp 2pole, and the disconnect switch on E201 is only a 20amp 2pole. I assume the feed to the water heater should only be 2#12, 1#12G. Please clarify.

The conduit tag from PP-101B to IWH-1 should be tagged as 9 and not 11.

18. Drawing E-601 note #1 states to match existing MV conductor sizes from intercepted line. For pricing purposes please provide cable size of existing cables.

The existing cable size is unknown. The Contractor shall confirm the existing cable size and match as outlined in the project specifications and drawings.

19. Drawing E-101 note #8 shows intercepting the existing MV circuit in existing MV manhole. Is it known if the existing splice is a 3-way load break junction or is it a 3-way splice?

The existing cable configuration is unknown.

20. Is there supposed to be a beam at the peak of the canopy roof as shown on 2/S-210? If so what size? S-201 does call out one The Contractor shall provide a complete and usable canopy system. Per note 1 under DELEGATED DESIGN on sheet S-001, the truss system is a delegated design. The Contractor shall make determination of if a beam is or is not required supported by coordination with a truss supplier(s) as required.

22 RFI #1: Wage Determination Spec Section: 00 73 00 – Supplementary Conditions Drawing No.: n/a Building and Heavy Highway rates are included in the Supplementary Conditions Section of the specifications. Can you clarify which rates should be used, building or heavy highway rates. With a building being built it would make sense the entire project would be bid using the “Building Rates”.

CONTRACTING (Money Question)

Due to the amount of both earthwork and construction on a small building, the contractor shall utilize the appropriate wage determination from the respective building or heavy highway construction wage determination.

23 RFI #2: Geotechnical Analysis Report Spec Section: 31 00 00 Earthwork, 1.3 Subsurface Data Drawing No.: n/a The above spec section says Subsurface soil boring logs are shown in an Attachment to these specifications. I am not finding the attached Subsurface soil boring logs with the documents provided. Can you please provide this report/logs?

See the attached B-3 Boring Logs

24 RFI #3: Rock Excavation Spec Section: 31 00 00 Earthwork, 3.4 Excavation Drawing No.: n/a Spec section 31 00 00 Earthwork 3.4 Excavation says if at any time during excavation, including excavation from borrow areas, the Contractor encounters material that may be classified as rock or as hard/unyielding material, uncover such material, and notify the Contracting O icer. Do not proceed with the excavation of this material until the Contracting O icer has classified the materials as common excavation or rock excavation. Failure on the part of the Contractor to uncover such material, notify the Contracting O icer, and allow su icient time for classification and delineation of the undisturbed surface of such material will cause the forfeiture of the Contractor's right of claim to any classification or volume of material to be paid for other than that allowed by the Contracting O icer for the areas of work in which such deposits occur.

3A) The spec suggests the site is classified, the specification should then include a paragraph further outlining the details and have a quantity to include in the bid and a unit price for an add/deduct to adjust for actual quantities.

The Specification defines di erent classifications of soils but doesn’t establish that the site is classified.

3B) Also provide a timeline for the KO to visit the site and confirm the material, the last time this situation was encountered it took 6 weeks for that individual to come to the site.

The Contracting O icer Specialist or the Contracting O icer Representative work on the installation and will respond in a timely manner.

3C) Please include what the Engineer and Government considers hard material and what criteria the material has to meet before it is considered rock.

The Contractor shall refer to Specification Section 31 00 00, paragraphs 1.2.10 and 1.2.13 for clarification.

3D) Are contractors to include costs in their bid to remove rock if encountered or will contractors be paid above their contract value if rock is indeed encountered? The Contractor is not expected to encounter rock during this project.

3E) If rock excavation needs to be included in the proposal, can you provide allowances/unit prices? The Contractor is not expected to encounter rock during this project.

25 RFI #4: Unsuitable Soils At Design Subgrade Elevation Spec. Section: 31 00 00 Earthwork, 3.4 Excavation Drawing #: n/a Spec section 31 00 00 Earthwork 3.4 Excavation says excavate to contours, elevation, and dimensions indicated. Excavate soil disturbed or weakened by Contractor's operations, and soils softened or made unstable for subsequent construction due to exposure to weather. Use material removed from excavations meeting the specified requirements in the construction of fills, embankments, subgrades, shoulders, bedding (as backfill), and for similar purposes to minimize surplus material and to minimize additional material to brought on site. Do not excavate below indicated depths except to remove unstable material as determined by the Government and confirmed by the Contracting O icer. Remove and replace excavations below the grades shown with appropriate materials as directed by the Contracting O icer.

If unsuitable/unstable materials are encountered at the required subgrades will the contractor be paid above the contract value to remove and replace with suitable material?

The government is currently not anticipating any unstable soil conditions during the excavation. However, if unstable materials are discovered, the contractor shall notify the government for the consideration of a change order to remedy the unstable soil condition.

26 RFI #5: Excess Material Spec. Section: 31 00 00 Earthwork Drawing #: n/a Is there a disposal location(s) on the owner’s property to stockpile excess cut material if generated? If so what type of material can go to this disposal location? Or will contractors need to figure on hauling o excess cut material to an approved o site location?

The Government has a local location where spoils can be deposited with the site owner’s coordination and approval. Reference Drawing Sheet G-003 Note 2 for details. In addition to pre-coordination and approval, this requires record keeping for the amount of material removed and deposited at the local site.

27 RFI #6: Aggregate Backfill Of Utility Trenches Spec. Section: 31 00 00 Earthwork, 3.6.1 Trench Backfill, 3.6.1.4 Final Backfill Drawing #: C-504, Detail 3 – Typical Pipe Trench Is aggregate material required for final backfill of all utilities in proposed newly paved areas or can excavated material (satisfactory materials) be used as backfill?

Acceptable backfill shall comply with Specification Section 31 00 00, Paragraph 1.2.6.

28 RFI #7: Unit Prices For Stormwater Utilities Spec. Section: 33 40 00 Stormwater Utilities , 1,1 Unit Prices Drawing #: n/a The above spec section references unit prices for di erent storm application installations. Can you please clarify if stormwater will indeed be installed on a unit price format??????

The intent is to have the project as firm fixed price for the complete project construction. There are no planned unit prices for the contract.

29 RFI #8: Watertight Connectors For Storm Structures Spec Section: 33 40 00 Stormwater Utilities, 2.3.2 Mortar, 2.3.7 Resilient Connectors Drawing No.: n/a Spec section 33 40 00, 2.3.2 says to provide mortar for pipe connections to drainage structures conforming to ASTM C270 however spec section 2.3.7 says provide flexible, watertight connectors conforming to ASTM C923/C923M for connecting pipe to manholes and inlets. Are water tight gaskets required for storm structures or can standard brick/mortar parged pipe connections at the storm structures be acceptable? These gaskets require larger structures and result in significant increased costs for the precast structures (about 70 – 80% increase).

Either connection method is acceptable per the requirements established in the project Specifications.

30 RFI #9: Deflection Testing Spec Section: 33 40 00 Stormwater Utilities, 3.8.1.1 Deflection Testing Drawing No.: n/a Storm Drainage Utilities Spec 33 40 000 Section 3.8.1.1 references Deflection Testing for each run of storm pipe. Deflection testing of storm pipe is no longer considered an industry standard practice which involves pulling a mandrel through each run of pipe by hand. Is deflection testing indeed required?

The Contractor will refer to Section 33 40 00 Paragraph 3.3 regarding deflection testing. The Contractor may propose through the submittal process an alternative method of confirming satisfactory installation that complies with the project drawing and specifications.

31 RFI #9: Mandrel Testing Spec Section: 33 40 00 Stormwater Utilities, 3.8.1.1.1 Mandrel Testing Drawing No.: n/a

Storm drainage Utilities Spec 33 40 00 Section 3.8.1.1.1 references Mandrel testing for each run of storm pipe for the project. Mandrel testing of storm pipe is no longer considered an industry standard practice. This requires pulling a mandrel through each run of pipe by hand which is very time consuming and costly. Is mandrel testing indeed required?

The Contractor shall comply with the project Specifications and Drawings and may propose an alternative method of confirming satisfactory installation that complies with the project drawing and specifications through the submittal process.

32 RFI #10: Borrow Site Spec Section: 31 00 00 - Earthwork Drawing No.: n/a In order to achieve final grades, the site appears to be short material where import is required. Can contractors utilize material from the spoil/borrow area located to the east/southeast of the site to make the fills required for the site?

The Contractor shall refer to Drawing G-003, Note 2 for further clarification. The use of Harrisburg International Airport earth material requires coordination, approval, and volume receipts in addition to meeting all the project Specifications and Drawings.

33 RFI #11: Aggregate Base Course Spec Section: 32 11 23 Aggregate Base Course Drawing No.: n/a In reference to spec section 32 11 23 Aggregate Base Course: Can any reference related to P-209 (FAA) aggregate material be removed from the spec and be replaced with PennDot Approved 2A stone for aggregate base course?

No references to P-209 could be found in Specification Section 32 11 23.

34 RFI #12: Road-Mix Asphalt Paving Spec Section: 32 12 16.16 Road-Mix Asphalt Paving Drawing No.: n/a In reference to spec section 32 12 16.16 Road-Mix Asphalt Paving. Can any reference to FAA asphalt mixes be removed from the spec and be replaced with PennDot approved Superpave HMA mixes related to all asphalt paving? If PennDot approved Superpave HMA mixes can be used, please provide esal count and SRL requirements?

No references to FAA asphalt mixes could be found in the project Specification.

35 RFI #13: Concrete Hatched Area Around Gate House Spec Section: n/a Drawing No.: C102 – Layout Plan Drawing C102 – Site Layout Plan appears to show concrete hatching around the majority of the Gate House within the curb limits. Does this entire area receive concrete or can topsoil be installed around the edges of the proposed sidewalks?

The Contractor shall provide concrete in the entire area as indicated in the project drawings.

36 RFI #14: Concrete Median Island Pavement Spec Section: n/a Drawing No.: C102 – Layout Plan, C-506 Civil Details, Detail 4 Concrete Median Islands Can you provide the thickness of aggregate material required under the concrete median?

The Contractor shall refer to Drawing C-506, Detail 4. The Aggregate Base Course shall go down to the level of Aggregate Base Course under adjacent pavement.

37 RFI #15: Structural Backfill For the Retaining Wall Spec Section: 32 32 23.13 Segmental Concrete Block Retaining Wall – Various Sections, 31 00 00 Earthwork, 2.1.1 Structural Fill Drawing No.: C102 – Layout Plan, C-204 Retaining Wall Plan, S-301 Retaining Wall & Concrete Foundation Details

– Detail 4 On drawing S-306, detail 4 – Typical Retaining Wall Detail appears to show aggregate material as backfill behind a 12” aggregate drainage layer. Spec section 31 00 00, 2.1.1 says structural backfill and leveling pad material for the retaining wall shall consist of PennDot coarse aggregate No. 57. Can you specify the aggregate backfill limits behind the 12” drainage layer of stone? Some engineers require a 45 degree aggregate wedge behind the drainage layer and other engineers specify dirt backfill. Please clarify the required limits of aggregate backfill beyond the drainage layer.

The Contractor shall refer to Specification section 32 32 23.13, paragraph 3.3.2. Additionally, Drawing S-306, Detail 4, no section of aggregate fill shall be less than 12” behind the blocks.

38. Reference specification section 31 63 26 – Drilled Caissons.

Paragraph 1.5.1 indicates that subsurface soil data logs are included in the drawings. However, we have been unable to locate this information in the drawings. Is there a geotechnical report that can be provided or shall the site be deemed unclassified?

See the attached B-3 Boring Logs

39. Reference C-120

Please confirm that all government and contractor access to the base during phase 2A will be via a secondary existing secured entrance.

All Government and Contractor access to the base will be via a secondary gate once the primary gate is no longer useable.

40. Reference specification section 01 45 00.

Provided the Quality Control Manager meets the qualifications of section 1.6, may this individual also function as the project superintendent?

The Government may allow the Quality Control Manager to also serve as the Project Superintendent. This would be approved on a case-by-case basis with a request submitted from the Contractor to the Government.

41. Reference specification section 01 45 35.

Paragraph 1.3.9 seems to indicate that the structural engineer of record must be retained by the prime contractor and must assume responsibility for the overall design and review of all submittals. This is a highly unusual requirement that appears to shift all responsibility for the overall structural design to the contractor. Please clarify the intent of this paragraph.

This is an odd requirement and not a common situation, however, HDR would normally be retained to provide a Structural Engineer to fill this role. Since there is no contract in place for construction support services with HDR and PA ANG does not have a structural engineer that can fill this role, the specification was edited to require the contractor to hire the engineer.

These inspections and structural engineer of record role must be performed for the project to be code compliant.

42. Reference specification section 05 12 00.

Please confirm if the steel fabrication shop must be AISC certified.

The Contractor shall comply with the project Specification which require various drawings, documents, fabrication, testing, and assemblies to comply with specific AISC specifications.

43. Reference E101 notes 7 & 8.

Please confirm the existing underground feeder size and vault configuration.

The Government has no further information to provide. The Contractor shall confirm all existing conditions.

44. Reference S-100 Foundation Note 10 This note and the corresponding schematic plan show an existing culvert directly adjacent to new caisson foundations. The caisson foundations are noted to be drilled 21-ft minimum. Is the depth of the existing culvert known?

The Government has no further information to provide. The Contractor shall confirm all existing conditions.

45. The plans & specifications do not appear to indicate any new Division 21 - Fire Suppression Systems or Division 28 – Fire Alarm Systems. Please confirm that there are no life safety systems included in this project.

Specification Division 21 and Division 28 do not apply to this project.

46. Will the government consider postponing the bid date to allow time for this information to be processed and responsible pricing obtained?

The government has postponed the solicitation to Friday, September 26th. Please see solicitation for Specific Time and Location (noted in the Instruction to O ers).

47 RFI #15: Aggregate Surfacing Material For Truck Off Tracking Area

Spec Section: n/a Drawing No.: C301 Roadway Typical Sections

What type of aggregate material should be used for the 8” aggregate surfacing for the Truck Off Tracking Area shown on drawing C301?

The Contractor shall reference project Specification Section 32 15 00.

48 RFI #16: Retaining Wall Engineered Drawings (Duplicate later) Spec Section: 32 32 23.13 Segmental Concrete Block Retaining Wall Drawing No.: C-204 Retaining Wall Plan Elevation

Are there stamped engineered drawings available for the proposed retaining wall?

The Contractor shall ensure the retaining wall is designed and approved in accordance with Drawing S-001, Design Note 3.

49 RFI #17: Maximum Allowable Particle Size of Fill Material (Duplicate later) Spec Section: 31 00 00 Earthwork Drawing No.: n/a

Please confirm the maximum allowable diameter of fill material to be placed under grass/landscaping areas, under walks and pavements, and under building pads.

The Contractor shall ensure fill material complies with project Specification Section 31 00 00, Paragraph 1.2.6.

50 RFI #18: RCP Pipe Requirements (Duplicate later) Spec Section: 33 40 00 Stormwater Utilities Drawing No.: n/a What installed leakage test is required on the RCP pipe? Section 3.8.3.1 states the remedy if the pipe fails a leakage test, but nowhere is an installed leakage test specified. Please clarify or remove Section 3.8.3.1 from the project specifications.

Specification 33 40 00 paragraph 3.8.3.1 can be removed from the specifications.

51 RFI #17: Aggregate Surfacing Material For Truck O Tracking Area

Spec Section: n/a

Drawing No.: C301 Roadway Typical Sections

What type of aggregate material should be used for the 8” aggregate surfacing for the Truck O Tracking Area shown on drawing C301?

The Contractor shall ensure aggregate material complies with project Specification Section 32 15 00.

52 RFI #18: Retaining Wall Engineered Drawings (DUPLICATE)

Spec Section: 32 32 23.13 Segmental Concrete Block Retaining Wall

Drawing No.: C-204 Retaining Wall Plan Elevation

Are there stamped engineered drawings available for the proposed retaining wall?

53 RFI #19: Maximum Allowable Particle Size of Fill Material (DUPLICATE)

Spec Section: 31 00 00 Earthwork

Drawing No.: n/a

Please confirm the maximum allowable diameter of fill material to be placed under grass/landscaping areas, under walks and pavements, and under building pads.

54 RFI #20: RCP Pipe Requirements (DUPLICATE)

Spec Section: 33 40 00 Stormwater Utilities

Drawing No.: n/a

What installed leakage test is required on the RCP pipe? Section 3.8.3.1 states the remedy if the pipe fails a leakage test, but nowhere is an installed leakage test specified. Please clarify or remove Section 3.8.3.1 from the project specifications

55 RFI #19: Existing Underground Stream

Spec Section: n/a

Drawing No.: S-100, C-104, C-206

Referenced at the pre-bid meeting for the project an existing underground stream appears to be present onsite. With no information on the exact location or material make up, will contractors be compensated above the contract value if the underground stream is in the limits of any excavation?

The information provided in the specifications, drawings and the onsite covert outlet identifies the depth, the stream is slow moving to almost a stand still. As excavation occurs, the Government is expecting that the area will take more time to remove material and expose if necessary, the stream structure. The Government will be on-site to ensure that the structure is not damaged. If unforeseen conditions occur an RFI would be submitted and together the Government and the contractor will come together to solve the problem. The contractor is responsible for quality control and the Government is responsible for quality assurance, if the Government finds that during excavation that the contractor was ripping and tearing with the knowledge of the structure underneath, they would be held responsible. The Easement data for the Post Run Storm Sewer is shown on sheet V-

102. In addition, shown on X-101 is the storm sewer easement and a grey dashed line on X-101 as well as other sheets indicate the location of the storm sewer that was GPR Located (Image below for clarity). The GPR locate of the stream was done the best that should be and in locations, the stream gets deep, and the centerline could not be precisely determined. The depth of the stream was not picked up with any accuracy. The GPR data indicated that at the south east end of the site, the top of the stream was 1’ to 2’ below the surface. The outfall of the stream is also exposed on the airport property not far from the PA ANG lease area boundary. Please also see Attachments PRC_CS, PRC_C1, PRC_S1, PRC_S2, PRC_XS1, PRC_XS2, PRC_XS3, Post Run Culvert.

56 RFI #20: Bedding and Initial Cover For Utilities

Spec Section: 31 00 00 Earthwork, 2.1.6 Utility Bedding Material

Drawing No.: C-504, Detail 3 Typical Pipe Trench Detail

Can Penn Dot Certified AAashto #57 stone be used for bedding and initial cover for site utilities (stormwater and sanitary) which is industry standard in Pennsylvania? Aashto #57 stone is the same type of stone required for the backfill of the proposed retaining wall. Coarse aggregates listed in spec section 2.1.6 for utility bedding are not industry standard in Pennsylvania.

Aashto#57 stone is acceptable as bedding material.

57 RFI #21: Asbestos Abatement Survey Of Existing Building

Spec Section: 02 41 00 Demolition, 1.2.3 General Requirements

Drawing No.: X-101 Site Demo Plan

Has an Asbestos Abatement Survey been done for the existing building that needs to be demolished? Will contractors be compensated above their contract value if asbestos is encountered during demolition?

The Asbestos survey indicates that building 62 does not have areas containing such material and building 61 had two samples taken and came back negative (the report stated that a non-destructive investigation was conducted) . If during the demolition it is discovered that such material exists the contractor shall cease operations and submit an RFI to ask what does the Government intends to do.

58 Drawing E-503 - Wedge Barriers are called out as M30/P1 on both plans and specifications – this is atypical. Generally all ACP systems incorporate an M50 barrier – please confirm that only M30 is required.

At a minimum of M30 rating is required as the design was calculated for this rating . If the contractor wants to provide something greater than M30, it is acceptable.

59 Orange Fence (BOD Ameristar K8/L2 Stalwart) – is called out with fence. “Wall and AVB Fence..” Is this supposed to be post and cable only or include fence? There is a detail about the distance to retaining wall that is semi-concerning considering the depth of the foundations required for this fence type.

Per drawing C-107, Orange is M40 P2 RATED CABLE PASSIVE BARRIER WITH CABLE REINFORCED FE6-TR-84 HIGH SECURTIY PERIMETER FENCING. Install must include both vehicle barrier in front of a separate high security perimeter fencing. Fencing does not require cable reinforcement in this location. It is acceptable to utilize the existing fence that was to be demolished, where applicable.

60 Blue Fence (milcon) – this fence is not crash rated. Confirm that that is acceptable?

Correct, this matches existing perimeter.

61 Slide gates – these slide gates are not doable as shown at opening of 40’ and 55’ – Are other solutions acceptable?

Bi-parting gates might be possible. Also confirm that these gates are not to be crash rated.

Gates must be sliding gates and cable reinforced. Slide gates may be permitted to slide in differing directions/bi-parting with approval from the Government. Slide gates are not required to be crash rated.

62 Please provide specification/crash requirements for traffic arms.

Refer to drawing C-107, traffic arms shall be B&B ARMR MODEL 714 MANUAL TRAFFIC ARM or approved equal.

63 Do the crash rated bollards require any covers?

Refer to drawing C-107, crash rated bollards should be FIVE M30 P1 RATED AMERISTAR BULWARK FIXED BOLLARDS or approved equal. Bollard are exterior and shall be capable of surviving the local weather.

64 Specs and control panel drawing indicate wrong way and overspeed requirements – however site plan does not indicate point detection locations and set points. Please clarify.

Refer to Drawing E-103 as it shows point detection locations as keynotes 4 and 7; Specification Section 34 75 13.13 paragraph 2.15 states set point speed.

65 Spec 34 75 13.13 / 3.10.5.4 and 3.10.6 both mention endurance testing – but endurance testing spec section is not included. Please confirm that endurance testing is not going to be required on this project.

Endurance test is not required on this project. That test is only required on Army projects.

66 Appendix section 1.6 – quadrupole loops – drawings show dual barriers in same lane that taper to single lane. Spec requires “diagonal quadrupole loop” that is 76 feet long. How do we separate these between lanes?

The design is based on a 9 second Hybrid Beacon Scheme which should have a VPD before the barriers of only 20 foot in length. In addition, the outbound lane is only one lane that requires two barriers to cover the full width. If induction loops are used, they must cover full paved lane width.

67 Confirm local control panel diagrams on E-506 are opposite because they should be two barriers at the outbound and one barrier at the inbound.

Refer to details on drawing E-501 for LOCAL CONTROL PANEL AT INBOUND BARRIER and LOCAL CONTROL PANEL AT OUTBOUND BARRIER should have their titles switched. The outbound lane has two barriers and the inbound lane has one barrier.

68 The B&B Armr Model 714 drop arms seems to be discontinued since Ameristar bought B&B. Is there a preferred replacement?

If B&B Armr Model 714 drop arms are not available, TAPCO Manual Lift Barrier Gate or HIGHWAY SIGNALS Manual Lift Barrier Gate Arm are both acceptable equals.

69 The detail for the sliding gates shows 24' opening but the fence plan (C-107) show 48' and 54' respectively. These openings are too big for a single slide gate. Do they want double slide gates? If they want double gates, there may be a safety issue with the sidewalk.

The Detail is a generic detail. These Gates must be slide gates and cable reinforced. Slide gates may be permitted to slide in differing directions/bi-parting with approval. Gates are not required to be crash rated.

70 On the slide gates, what is going to keep the cable from getting tangled when the gate opens and closes?

Slide gates must include cable reinforcement and provisions for maintaining cable in both closed and open positions. Cables shall be disconnected and connected as required to operate the sliding gate. Generic details are shown on C-511 and specific details may be different depending on the selected manufacturer.

71 Is a single fence system an option for the passive barrier system (all Gibraltar or all Ameristar)?

Manufacturers selected on plans illustrate the basis of design for systems. Contractor may propose any passive barrier systems desired provided the alignment and barrier ratings are met or exceeded. If any alignments change, contractor shall provide supporting calculations for impact ratings required.

72 Are there Specifications for the passive systems, traffic arms, and crash beams (I didn't see anything specifically for them)?

All ratings for passive systems are included on the plan sheets. Basis of design manufacturers are listed for reference. The foundation and supporting element must be according to manufacturer guidance to obtain the listed ratings on the drawings.

73 Specification section 08 11 16, 1.5 Quality Control, Paragraph 1.5.1 Shop Drawings references a blast calc requirement however we cannot locate the specified blast loads in the specifications. Confirm where specified blast loads can be found or if blast ratings for the aluminum doors and frames are applicable to this project.

Refer to the last sentence of paragraph 1.5 of section 08 11 16, “A qualified blast engineer must perform testing or calculations for door system design resistance to specified blast loads.”, can be removed.

74Dwg E102 - what is the height of the light poles for P1 fixtures?

The P1 fixtures should have a mounting height of 30’. Below is a foundation detail for the poles.

P1 is described as a cobra head. I do not see anything requiring arms for the poles. This could be correct as is. I question if they want mast arms.

If the light fixture requires the mast arms then they shall be required

75 Spec 1.8.2 of 265600 - talks of an Exterior Lighting Control SYSTEM. I do not see any system. Do we need photocells for P1. Confirm or clarify.

The contractor shall install photocells for this fixture type

76 Dwg E203 - Note 1 states to connect down leads to ground ring and ground rod. What drawing is the ground ring shown for the canopy structure?

The canopy and lightening protection shall be connected to the building grounding ring (drawing E-602). The steel columns /structure shall be grounded to a ground rod then to the ring.

77 Dwg E602 - Is there a ground ring to encompass the 3 footings for the canopy structure and tie ins to the structure? Is there a ground ring attachment for the guard booth? The Contractor shall connect the canopy structure to a ground rod then connect to the ground loop around the guard shack building

Do we need to provide grounding at each of the pop up vehicle barriers? Grounding for pop-up vehicle barriers shall be according to the manufacturers requirements for the barriers. Equipment Ground Conductor is routed with power cables to barriers.

Is there an isolated counterpoise and/or grounding requirements for the antenna? Antenna pole shall be grounded per Specification Section 26 20 00 Paragraph 3.1.11 and as required for a compete and certified lighting protection system.

Whose scope of work is it to provide the Antenna? The prime contractor would determine which subcontractor would be responsible for the purchase and installation.

78 Dwg E501 - Who scope is it to provide the control panels and PLC system?

The prime contractor is ultimately responsible for the bid package, who they deem would provide that to them is up to them.

79 Please verify that all electrical equipment outdoors is to be NEMA 3R. The drawings do not indicate this rating?

All equipment that is considered outdoors needs to meet the UFC and NEC requirements

80 Will there active or passive vehicle barriers in the scope of work? Yes, there will be active and/or passive barriers included in this project’s scope of work.

81 FAR 52.236-13 Accident Prevention (page 27/71) requires EM385 Compliance - will a Level 1 SSHO be required or will Level 2 suffice? FAR 52.236-13 requires the contractor to comply with the requirements of USACE Manual EM 385-1-1.

While it does not mention a level, it does list SSHO requirements at 01.A.17.

82 RFI #16: Is there a specific format for the proposal? The contractor shall complete the pricing information for all CLINS on the SF 1442 AND provide a bid guarantee IAW with 52.228-1 as referenced in the solicitation document.

83 Will the government consider postponing the bid date to allow time for this information to be processed and responsible pricing obtained? The government intends to postpone the bid opening until Friday September 26th, 2025 at 10:00AM.

Location is located in the “Instructions to O erors” Division of the Solicitation document. Additionally, the deadline for RFIs has been extended to 12:00pm on Wednesday, September 3rd, 2025. Any RFIs submitted after this time will not be answered.

84 Will the government consider postponing the bid date to allow time for this information to be processed and responsible pricing obtained? The government intends to postpone the bid opening until Friday September 26th, 2025 at 10:00AM.

Location is located in the “Instructions to O erors” Division of the Solicitation document. Additionally, the deadline for RFIs has been extended to 12:00pm on Wednesday, September 3rd, 2025. Any RFIs submitted after this time will not be answered.

85 Is this an incumbent contract? If so, could you please provide the previous award number? There is not an incumbent for this requirement.

86 What is your preferred method for receiving proposals? This requirement is an Invitation for Bid, and all bids shall be delivered in person at the specified time listed in the solicitation (Block 13) and at the specified location listed in the solicitation (Section 00 21 00-Instructions).

87 Please clarify what is to be included with our proposal? The contractor shall complete the pricing information for all CLINS on the SF 1442 AND provide a bid guarantee IAW with 52.228-1 as referenced in the solicitation document.

87 Are electronic delivery of bids accepted? Unfortunately, all bids are required to be hand-carried and input into the sealed bidding bid box at the specified bid opening date/time.